Question
- A) A crew of mechanics at the Highway Department Garage repair vehicles that break down at an average of λ = 7.5 vehicles per day (approximately Poisson in nature). The mechanic crew can service an average of μ = 12 vehicles per day with a repair time distribution that approximates a negative exponential distribution.
(a) What is the utilization rate for this service system?
(b) What is the average time before the facility can return a breakdown to service?
(c) How much of that time is spent waiting for service?
(d) How many vehicles are likely to be in the system at any one time?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 4 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A new customer walks into SLC Barber Shop every 60 minutes on average, with a standard deviation of the interarrival times being 60 minutes. At SLC Barber Shop, the average service time is 30 minutes, with a standard deviation of service times being 45 minutes. 1. What is the utilization of the barber? 2. What is the CVa? 3. What is the CVp?arrow_forwardWho are the internal customers using a self-service kiosk in a hotel?arrow_forwardDefine a possible service guarantee for each of the following services: a. College classes b. A theatre performance c. Buying a used cararrow_forward
- 4 SCMarrow_forward1. Summarize the service failures associated with this experience. 2. What might the travel agency do to improve its customers’ service experience?arrow_forwardI have no idea, please help me! 1. Assume that the arrival rate is increased to 1 customer per minute and that the service rate is increased to 1.25 customers per minute. Compute the following operating characteristics for the new system: P0, Lq, L, Wq , W, and Pw. Does this system provide better, or poorer service compared to the original system? Discuss any differences and the reason for these differences.arrow_forward
- In an M/M/1 queueing system, the arrival rate is 5 customers per hour and the service rate is 7 customers per hour. If the service process is automated (resulting in no variation in service times but the same service rate), what will be the resulting performance measurements? (Round all answers to three decimals.) What is the utilization? What is the expected number of customers in the system (L)? What is the expected waiting time (in hours) for the system (W)? What is the expected number of customers in the queue (Lq)? What is the expected waiting time (in hours) in the queue (Wq)?arrow_forwardPasquist Water Company (PWC) operates a 24-hour facil-ity designed to efficiently fill water-hauling tanker trucks.Trucks arrive randomly to the facility and wait in line to ac-cess a wellhead pump. Since trucks vary in size and the filling operation is manually performed by the truck driver, the timeto fill a truck is also random.a. If the manager of PWC uses the multiple-server modelto calculate the operating characteristics of the facility’swaiting line, list three assumptions she must make regard-ing the behavior of waiting trucks and the truck arrivalprocess.b. Suppose an average of 336 trucks arrive each day, thereare four wellhead pumps, and each pump can serve anaverage of four trucks per hour.▪ What is the probability that exactly 10 trucks will arrivebetween 1:00 p.m. and 2:00 p.m. on any given day?▪ How likely is it that once a truck is in position at a well-head, the filling time will be less than 15 minutes?c. Contrast and comment on the performance differencesbetween:▪…arrow_forwarddo parts A,B,C,D for mearrow_forward
- Explore the concept of self-healing systems and their relevance in minimizing downtime and optimizing system performance.arrow_forwardA mechanic at the Department of Maintenance makes minor repairs to faulty golf electric carts. The carts break down at an average rate of 4 carts per day and breakdowns are distributed according to the Poisson distribution. The mechanic can service an average of 6 carts per day with a repair time distribution that approximates a negative exponential distribution. Assume an 8 hour day. a- What is the utilization rate for the mechanic? b- What is the average time in hours that a cart is out of service?arrow_forward19-33 Waiting times, manufacturing cycle times. The IVplast Corporation uses an injection molding ma- chine to make a plastic product, Z39, after receiving firm orders from its customers. IVplast estimates that it will receive 40 orders for Z39 during the coming year. Each order of Z39 will take 120 hours of machine time. The annual machine capacity is 6,800 hours. 1. Calculate (a) the average amount of time that an order for Z39 will wait in line before it is processed and (b) the average manufacturing cycle time per order for Z39.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.