13. The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 7.610. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14. Table 7.6 Database Design Project Data Activity A B с D E G H Normal Time (days) 6 4 3 2 6 2 A 4 Normal Cost ($) 1,000 800 600 1,500 900 1,300 900 500 Crash Crash Time Cost (days) ($) 5 2 2 4 - 4 2 1,200 2,000 900 2,000 1,200 1,400 900 900 Immediate Predecessor(s) A, B B C.D a. What is the project's duration if only normal times are used? b. What is the minimum-cost schedule? E m G

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Note:-

  • Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
  • Answer completely.
  • You will get up vote for sure.
13. The Advanced Tech Company has a project to design an integrated information
database for a major bank. Data for the project are given in Table 7.610.
Indirect project costs amount to $300 per day. The company will incur a $150
per day penalty for each day the project lasts beyond day 14.
Table 7.6 Database Design Project Data
Normal
Time
Activity (days)
A
B
C
D
E
F
G
H
6
4
3
2
6
2
&
Normal
Cost ($)
1,000
800
600
1,500
900
1,300
900
500
Crash
Time
(days)
5
2
2
4
4
4
2
Crash
Cost
($)
1,200
2,000
900
2,000
1,200
1,400
900
900
Immediate
Predecessor(s)
A, B
B
C. D
a. What is the project's duration if only normal times are used?
b. What is the minimum-cost schedule?
c. What is the critical path for the minimum-cost schedule?
E
E
G
Transcribed Image Text:13. The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in Table 7.610. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14. Table 7.6 Database Design Project Data Normal Time Activity (days) A B C D E F G H 6 4 3 2 6 2 & Normal Cost ($) 1,000 800 600 1,500 900 1,300 900 500 Crash Time (days) 5 2 2 4 4 4 2 Crash Cost ($) 1,200 2,000 900 2,000 1,200 1,400 900 900 Immediate Predecessor(s) A, B B C. D a. What is the project's duration if only normal times are used? b. What is the minimum-cost schedule? c. What is the critical path for the minimum-cost schedule? E E G
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.