Duration of activity A = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity A = 5 + 4 (5) + 25 / 6 Duration of activity A = 8   Duration of activity B = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity B = 3 + 4 (5) + 8 / 6 Duration of activity B = 5   Duration of activity C = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity C = 7 + 4 (5) + 8 / 6 Duration of activity C = 6   Duration of activity D = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity D = 4 + 4 (4) + 5 / 6 Duration of activity D = 4   Duration of activity E = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity E = 10 + 4 (19) + 34 / 6 Duration of activity E = 20   Duration of activity F = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity F = 3 + 4 (14) + 18 / 6 Duration of activity F = 13 Duration of activity G = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity G = 6 + 4 (16) + 20 / 6 Duration of activity G = 15   Duration of activity H = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity H = 32 + 4 (44) + 65 / 6 Duration of activity H = 46   Duration of activity I = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity I = 12 + 4(17) + 25 / 6 Duration of activity I = 18   Duration of activity J = Optimistic + 4 (Most Likely) + Pessimistic / 6 Duration of activity J = 2 + 4 (8) + 18 / 6 Duration of activity J = 9   Activity Precedence Duration A -- 8 B -- 5 C A 6 D B 4 E B 20 F C,D 13 G E 15 H F 4 I G,H 18 J G 9   Questions: 1. Draw an AON network diagram and calculate its early start, early finish, late start and late finish times, floats (Free and total) for each activity. Make sure you fully label all nodes in the network. 2. Identify the project’s critical path and its length.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Duration of activity A = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity A = 5 + 4 (5) + 25 / 6

Duration of activity A = 8

 

Duration of activity B = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity B = 3 + 4 (5) + 8 / 6

Duration of activity B = 5

 

Duration of activity C = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity C = 7 + 4 (5) + 8 / 6

Duration of activity C = 6

 

Duration of activity D = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity D = 4 + 4 (4) + 5 / 6

Duration of activity D = 4

 

Duration of activity E = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity E = 10 + 4 (19) + 34 / 6

Duration of activity E = 20

 

Duration of activity F = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity F = 3 + 4 (14) + 18 / 6

Duration of activity F = 13


Duration of activity G = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity G = 6 + 4 (16) + 20 / 6

Duration of activity G = 15

 

Duration of activity H = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity H = 32 + 4 (44) + 65 / 6

Duration of activity H = 46

 

Duration of activity I = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity I = 12 + 4(17) + 25 / 6

Duration of activity I = 18

 

Duration of activity J = Optimistic + 4 (Most Likely) + Pessimistic / 6

Duration of activity J = 2 + 4 (8) + 18 / 6

Duration of activity J = 9

 

Activity

Precedence

Duration

A

--

8

B

--

5

C

A

6

D

B

4

E

B

20

F

C,D

13

G

E

15

H

F

4

I

G,H

18

J

G

9

 

Questions:

1. Draw an AON network diagram and calculate its early start, early finish, late start and
late finish times, floats (Free and total) for each activity. Make sure you fully label all
nodes in the network.


2. Identify the project’s critical path and its length.

Start
(D)
Ⓒ
(G₁)
H
End
Transcribed Image Text:Start (D) Ⓒ (G₁) H End
Expert Solution
Step 1: Definning Critical Path:

A key idea in project management is the critical path, which is used to estimate the quickest time frame for completion of a project. It outlines the order in which the various tasks must be completed in order for the project to be finished on time. The project's total schedule will be directly impacted by any delays in tasks that are on the critical path.

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.