Intermediate Accounting
Intermediate Accounting
3rd Edition
ISBN: 9780136912644
Author: Elizabeth A. Gordon; Jana S. Raedy; Alexander J. Sannella
Publisher: Pearson Education (US)
bartleby

Videos

Textbook Question
Book Icon
Chapter 8, Problem 8.5BE

Estimating Variable Consideration. Gear Garage Inc. enters into a contract to provide services totaling $80,000. The contract includes a potential performance bonus based on when Gear Garage completes the services. Gear Garage estimates the following scenarios for completion. Determine the expected value of the bonus under each scenario. Ignore any constraints on variable consideration.

Probability
Complete within Bonus Scenario 1 Scenario 2 Scenario 3
3 days $10,000 65% 50% 0%
5 days $ 6,000 10% 40% 90%
8 days $ 2,000 25% 10% 10%
Blurred answer
Students have asked these similar questions
Determining the Transaction Price for a Revenue Contract A contractor enters into a revenue contract with a customer to build customized equipment for $180,000 with a performance bonus of $99,000 that will be paid based on how quickly the equipment is completed. The amount of the performance bonus decreases by 15% of the original bonus per week for every week beyond the agreed upon completion date. The contractor has had experiences with similar contracts and thus has the data to predict the timing of completion of the contract. Therefore, the contractor concludes that the expected value method is the best predictor of revenue. The contractor estimates that there is a 60% probability that the contract will be completed by the agreed-upon completion date, a 35% probability that it will be completed one week late, and a 5% probability that it will be completed two weeks late. Complete the following table in order to determine the transaction price for revenue recognition for the…
Sandhill Construction enters into a contract witha customer to build a warehouse for $910000 on March 30, 2021 with a performance bonus of $40000 if the building is completed by July 31, 2021. The bonus is reduced by $8000 each week that completion is delayed. Sandhill commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 70% August 7, 2021 20% August 14, 2021 5% August 21, 2021 5% The transaction price for this transaction is O $673400 O $946400 O $665400 O $910000
Oriole Construction enters into a contract with a customer to build a warehouse for $ 860000 on March 30, 2021 with a performance bonus of $ 60000 if the building is completed by July 31, 2021. The bonus is reduced by $ 12000 each week that completion is delayed. Oriole commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2021 60% August 7, 2021 30% August 14, 2021 5% August 21, 2021 5% The transaction price for this transaction is $ 913400 $ 557400 $ 860000 $ 569400

Chapter 8 Solutions

Intermediate Accounting

Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Prob. 8.19BECh. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Prob. 8.13ECh. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Prob. 8.17ECh. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Prob. 8.9PCh. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Prob. 8.12PCh. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 2FSCCh. 8 - Prob. 1SSCCh. 8 - Prob. 1BCC
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Revenue recognition explained; Author: The Finance Storyteller;https://www.youtube.com/watch?v=816Q6pOaGv4;License: Standard Youtube License