To determine

The percent completed, revenue and gross profit for all the years.

Given information:

Contract price is $700,000.

Actual construction cost for 2018 is $140,000.

Actual construction cost for 2019 is $130,000.

Actual construction cost for 2020 is $160,000.

Estimated total cost for 2018 is $400,000.

Estimated total cost for 2019 is $360,000.

Estimated total cost for 2020 is $430,000.

Blurred answer
Students have asked these similar questions
Casio Co. recognizes construction revenue and expenses using the percentage-of-completion method. During 2020, a single long-term project was begun, which continued through 2018 Information on the project follows: 12/31 Accounts Receivable balance Construction expenses for year Gross Profit recognized in year Bangs during year The 12/31/21 CIP balance is Select one O $50,000 Ob 1322,000 O 1619.000 Od $106.000 O $112,000 2020 $100,000 105,000 122,000 100,000 20121 $300.000 192,000 200,000 420.000
Mikell Builders contracted to build a high-rise for $10,000,000. Construction began in 2020 and is expected to be completed in 2022.  Data for 2020 and 2021 are:     2020 2021 2022         Costs to date 4,500,000 7,200,000 8,600,000 Estimated costs to complete 3,000,000 1,200,000 0                       Mikell uses the percentage-of-completion method.               Required:   Compute the amount of gross profit (loss) that Mikell must report for 2020. Compute the amount of gross profit (loss) that Mikell must report for 2021. Compute the amount of gross profit (loss) that Mikell must report for 2022. Assume instead that Mikell uses the completed contract method. Compute the amount of gross profit (loss) that Mikell must report for each the three years - 2020, 2021, and 2022.
Paul Constructions has entered into a contract beginning January 1, 2020, to build a pool. It has been estimated that the pool will cost P300,000, and will take three years to construct. The pool will be billed to the purchasing at P450,000. The following data pertain to the construction period.   2020   135,000   165,000   2021   210,000   90,000   2022   0   Cost to date:   Estimated cost to complete.   Progress billing to date. Cash collected to date   135.000 120.000   275.000 250,000   450,000 450.000   During 2020, Costs incurred include P15,000 standard materials stored at the site to be used in 2022 to complete the project. Using the percentage of completion method, compute the recognize gross profit for 2022:   a. 52,500 b. 45,000 c. 97.500 d. 150,000   2. The CIP net of Progress billing is   a. 27.500 current liability b. 32,500 current asset c. 167,500 current asset. d. 102,500 current liability

Chapter 8 Solutions

Intermediate Accounting

Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Prob. 8.19BECh. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Prob. 8.13ECh. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Prob. 8.17ECh. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Prob. 8.9PCh. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Prob. 8.12PCh. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 2FSCCh. 8 - Prob. 1SSCCh. 8 - Prob. 1BCC
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education