Concept explainers
Compute the early, late, and slack times for the activities in the network that follows, assuming a time-constrained network. Which activities are critical? What is the time-constrained project duration?
Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any resource scheduled beyond the shaded area will delay the project.
Assume you have only three resources and you are using a computer that uses software that schedules projects by the parallel method and following heuristics. Schedule only one period at a time!
Minimum slack
Smallest duration
Lowest identification number
Keep a log of each activity change and update you make each period—e.g., period 0-1, 1-2. 2-3, etc. (Use a format similar to the one on page 259.) The log should include any changes or updates in ES and slack times each period, activities scheduled, and activities delayed. (Hint: Remember to maintain the technical dependencies of the network.) Use the resource load chart to assist you in scheduling (see figures 8.4 and 8.5).
List the order in which you scheduled the activities of the project. Which activities of your schedule are now critical?
Recompute your slack for each activity given your new schedule. What is the slack for activity 1? 4? 5?
Want to see the full answer?
Check out a sample textbook solutionChapter 8 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
- Determine all of the various real-time scheduling options that are accessible to the team working on the project.arrow_forwardIn a traditional project, the project manager saves the project schedule as a baseline plan in project management software. During the course of the project, the variance reports are created to show the difference between planned and actual activities. Project monitoring and control is different in agile projects than traditional projects. In an agile project, different tools and techniques are used to monitor and control project schedules. How does it help a project manager to monitor cost and schedule in a traditional project? There are different techniques for monitoring schedule performance in a traditional project. One method is a schedule variance report. How is a schedule variance report different from schedule variance in earned value? Does the role of the project manager change when monitoring and controlling agile projects?arrow_forwardYou are one of three carpenters assigned to complete a short construction project. Right before the start of the project, one of your fellow carpenters was hospitalized and will not be available to work on the project. Develop a resource-constrained schedule in the loading chart that follows to see how long the project will take with only 2 carpenters. Be sure to record the order in which you schedule the activities using the scheduling heuristics. Activities A, B, C, D, E, G, and H require 2 carpenters to complete. Activity F requires only 1 carpenter. No splitting of activities is possible. You will receive a bonus if the project is completed within 15 days. Should you start planning how you will spend your bonus? E 10 2 2 2 2 A 2 4. 5 10 2 2 2 10 H 12 2 1 10 10 12 Legand ES ID EF Use the tolowing houristics: Minimum siack Smallest duration SL. LS DURLF Lowest identincation number Resource ID RES DUR ES LF SL O 3 4 10 11 12 13 14 15 16 17 18 A 2 B 2 1 C 2 D 2 2 2 2 2 2 Resources…arrow_forward
- Describe is the cheapest way to cancel some activities in order to reduce the (estimated) project duration to the specified level in operations management in project scheduling ?arrow_forwardUsing the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery)= hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Deliver Suit Cut and Sew 1 2 Assume that orders for suits have been listed in the above table in the order in which they were receivedarrow_forwardYou have prepared the following schedule for a project in which the key resources is a tractor. There are three tractors available to the project. Activities A and D require one tractor to complete while activities B, C, E and F require 2 tractors.Develop a resource-constrained schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Record the early start (ES), late finish (LF) and slack (SL) for the new schedulearrow_forward
- Task C is directly preceded by two tasks–task A and task B. Task A has an expected task completion time of five weeks and an ES time of week 6. Task B has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The ES for activity C is?arrow_forwardUsing the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including of the suits. delivery) = hours (enter your response as a whole number). Times Taken for Different Activities (hours) Deliver Suit Cut and Sew Using Johnson's rule for 2-machine scheduling, the sequence is 1 2. For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits 3 (including delivery) = hours (enter your response as a whole number). Assume that orders for suits have been listed in the above table in the order in which they were received. Of the two developed schedules, V rule gets the schedule finished sooner.arrow_forwardYou may need to use the appropriate technology to answer this question. Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. A project network with 11 activities and 13 directed arcs is shown. Activity Start is connected to activity A. Activity A…arrow_forward
- Different scheduling methods for different types of service activities, such as restaurants, hospitals, and airlines, should be classified.arrow_forwardproject scheduling uses the schedule, discuss the relevance of it to project managerarrow_forwardUsing the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery)= 22 hours (enter your response as a whole number). Using Johnson's rule for 2-machine scheduling, the sequence is 3-2-1 For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits (including delivery)= hours (enter your response as a whole number). D Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits Times Taken for Different Activities (hours) Cut and Sew Suit 1 2 3 5 Deliver 2 3 6 D Assume that orders for suits have been listed in the above table in the order in which they were received.arrow_forward
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON