Question
thumb_up100%
You have prepared the following
and D require one tractor to complete while activities B, C, E and F require
2 tractors.
Develop a resource-constrained schedule in the loading chart that follows.
Use the parallel method and heuristics given. Be sure to update each period as
the computer would do. Record the early start (ES), late finish (LF) and slack
(SL) for the new schedule
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 2 images
Knowledge Booster
Similar questions
- Stan's No Touch Car Wash is looking to implement a new ERP system. Colin Alexander has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. Tasks Predecessors mu_t sigma_t Start 0 0 A start 25 12 B A 17 14.11 C A 45 46.35 D A 32 15.36 E A 37 10.36 F C,D 10 11.8 G B,F 41 15.17 H E,G 44 44.44 end H 0 0 Colin has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: Metric Description E[ES_i] Expected early start time for task i E[EF_i] Expected early finish time for task i E[LS_i] Expected late start time for task i E[LF_i] Expected late finish time for task i Pr(S_i =< t) Probability the start time for task I =< t Pr(F_i =< t) Probability the finish time for task I…arrow_forwardAll projects utilise several different resources to successfully complete the project successfully tothe customer or sponsors requirements.Resources add another dimension to planning and scheduling. This includes people, materials,equipment, tool, facilities and so forth.The quantity and availability of these resources are often limited and cause project to face risks orconstraints which needs to be managed carefully.With the above statements , differentiate between Resource smoothing and resourcelimited scheduling then to substantiate your answer by providing at least two (2) situations whereresource limited scheduling may occurarrow_forwardBefore a master schedule can be created what action is needed? A. Aggregate the aggregate plan into specific model numbers B. Disaggregate the specific model numbers C. Disaggregate the aggregate plan into specific model numbers D. Aggregate the specific model numbers into product families E. Disaggregate the business plan to create product families e.arrow_forward
- A project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Schedule Variance (SV)?arrow_forwardDetermine all of the various real-time scheduling options that are accessible to the team working on the project.arrow_forwardAn activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity is on week 10 and $35,000 were spent and is 40% completed. What is the BCWS for this activity?arrow_forward
- Saint Teresa's Hospital is looking to implement a new ERP system. Russell Trent has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. Task Pred Mean Std Var Start 0 0 0 A Start 20 19.4 376.36 B A 14 11.34 128.5956 C A 45 34.65 1200.623 D A 15 11.55 133.4025 E B,C,D 7 6.72 45.1584 F E 37 42.55 1810.503 G E 27 27.27 743.6529 H E 43 14.62 213.7444 I E 28 19.04 362.5216 J F,G,H,I 13 13.52 182.7904 End J 0 0 0 Because Russell has studied project management at the University of Portland, he knows that the he should incorporate a time buffer into any estimates for the project's makespan. If Russell wants to quote a 92% makespan: Quoted Makespan = Time Buffer =arrow_forwardConsider the following network for conducting a two-week (10 working days) computer training class: (a) refer to the pic I uploaded :)) Construct a schedule showing: ESs for all activities LSs for all activities Slacks for all activities Critical patharrow_forward1. The activities involved in the construction of a certain project are given in Table 1. One resource type will be used during the contract. Determine minimum level of the resource required to complete the project. a) Draw the precedence network and perform the CPM calculations. b) Prepare the Bar chart, Resource load table and and resource histogram (for both Early start time and Late start time) c) Allocate the required resources, then level them so that the contractor does not use more than six laborers at any time. Preceded Duration Laborers by Activity |(Days) A B 7 4 C A 3 3 D А,В 5 3 E C,D 2 2.arrow_forward
- Given the following activity network: Three nodes - A1, A2, A3; two paths - A1, A2 and A1, A3. Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the latest completion time of A3? A. 7 B. 15 C. 10 D. 13arrow_forwardFor the activity times and network model below, What is the expected completion time? ________ What is the critical path? ____________ Activity Time A 3 B 2 C 2 D 4 E 3 F 2arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Expert Answers to Latest Homework Questions
Q: Can you please solve this following requirements on these general accounting question?
Q: I won't correct answer general Accounting
Q: I Want Correct Option
Q: Hi expert please give me answer general accounting question
Q: General Accounting
Q: 2023/2024
Note/ Answer all questions
ملاحظة يرجى تسليم الأسئلة
Sample (A)
Maximum Mark
First Course…
Q: Need help with this general accounting question not use ai please don't
Q: Owner3 equity for our company solve this accounting questions
Q: Please need answer the following requirement for this general accounting question
Q: Please provide answer accounting questions
Q: Please Give me answer of this Question as possible fast too
Q: General Accounting Question solve this one
Q: What is the total standard cost for one unit of product that would appear on a standard cost card…
Q: Need help with this accounting questions
Q: Please see attachment for details
Q: Hii expert need help
Q: What is the net income under absorption costing get solution
Q: Please need answer the general accounting question
Q: Compute the following requirements on these general accounting question
Q: Do fast answer of this accounting questions
Q: Please provide this question solution general accounting