Program Description Answer

A network diagramming technique that is used to predict total project duration is PERT.

Hence, the correct answer is option “A”.

Blurred answer
Students have asked these similar questions
1. Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated duration. 2. Identify all the paths on the network diagram and note how long they are. 3. What is the critical path for this project and how long is it? 4. What is the shortest possible time needed to complete the project?
10 Which of the following is a classic organizational structure? A Functional B Projectized C Composite D Matrix 11 Defining a new project or a new phase of an existing project relates to A Initiating process. B. Planning process C Scope management process D. Control process 12 If you are developing a Project Management Plan, how should you determine the level of detail to be included in the plan? A Always only provide a summary or high level plan B Include only the details your manager specifically requested C Always provide the maximum level of detail possible D. Provide the level of detail based on the project complexity and application area 13 Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied? A. Crashing B. Reserve Analysis C. Forecasting D. Last Tracking 14.…
bMetrics for static testing and path testing should be talked about in depth, as should the cost savings to cost ratio of how static testing and path testing help project managers save money.
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning