Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
12th Edition
ISBN: 9780134741062
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 4, Problem 7P

Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these Linus must be processed by a machine that Macon considers to be their process bottle neck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. Table 4.2 provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 20 percent capacity cushion is best.

Chapter 4, Problem 7P, Macon Controls produces three different types of control units used to protect industrial equipment

  1. How many machines are required to meet minimum (pessimistic) demand, expected demand, and maximum (optimistic) demand?
  2. How many machines are required if the operations manager decides to double lot sizes?
  3. If the operations manager has three machines and believes that the plant can reduce setup time by 20 percent through process improvement initiatives, does that plant have adequate capacity to meet all demand scenarios without increasing lot sizes?

Blurred answer
Students have asked these similar questions
Scenario The KOREAN factory of Hi-Tech Metal, Inc. primarily manufactures plumbing system parts for gas pipes, drainage pipes, water supply pipes and hoses etc. A mainframe computer was used for scheduling, but it took a lot of time and unnecessarily put heavy workload on scheduling managers and on-site workers. Following are the associated problems to meet customers’ needs Lengthy 3 to 4 days schedule drafting time, caused by mainframe computer’s long processing time. Inflexibility of mainframe computer to sudden order changes, leading to tedious manual calculation and direct on-site adjustment Extra workload for on-site workers One-month base scheduling that cannot meet customers’ need, Task 3 Considering above scenario identify the manufacturing system for the components [Based on the stakeholder, strategic goals , explain the manufacturing system]
Scenario The KOREAN factory of Hi-Tech Metal, Inc. primarily manufactures plumbing system parts for gas pipes, drainage pipes, water supply pipes and hoses etc. A mainframe computer was used for scheduling, but it took a lot of time and unnecessarily put heavy workload on scheduling managers and on-site workers. Following are the associated problems to meet customers’ needs Lengthy 3 to 4 days schedule drafting time, caused by mainframe computer’s long processing time. Inflexibility of mainframe computer to sudden order changes, leading to tedious manual calculation and direct on-site adjustment Extra workload for on-site workers One-month base scheduling that cannot meet customers’ need, Task 4 Considering above scenario justify improvements and alternatives to design and manufacturing of plumbing system. [Improvements, alternative systems, explain the IoT systems and Industry4.0 impacts]
Scenario The KOREAN factory of Hi-Tech Metal, Inc. primarily manufactures plumbing system parts for gas pipes, drainage pipes, water supply pipes and hoses etc. A mainframe computer was used for scheduling, but it took a lot of time and unnecessarily put heavy workload on scheduling managers and on-site workers. Following are the associated problems to meet customers’ needs Lengthy 3 to 4 days schedule drafting time, caused by mainframe computer’s long processing time. Inflexibility of mainframe computer to sudden order changes, leading to tedious manual calculation and direct on-site adjustment Extra workload for on-site workers One-month base scheduling that cannot meet customers’ need, Task 1 Considering above scenario Summarize the design process for the finished component [Identify components, explain the utilities and design process (5/7/10 step) for components]
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY