Textbook Question
Chapter 3, Problem 9P
Task time estimates for the modification of an assembly line at Jim Goodale’s Carbondale, Illinois, factory are as follows:
ACTIVITY | TIME (IN HOURS) | IMMEDIATE PREDECESSORS |
A | 6.0 | --- |
B | 7.2 | --- |
C | 5.0 | A |
D | 6.0 | B, C |
E | 4.5 | B, C |
F | 7.7 | D |
G | 4.0 | E, F |
- a. Draw the project network using AON.
- b. Identify the critical path.
- c. What is the expected project length?
- d. Draw a Gantt chart for the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows:
Activity
Activity Description
Immediate Predecessor
Activity time (days)
A
Identify Client Base
―
33
B
Develop Client Prospectus
―
21
C
Perform Design Analysis
―
35
D
Program Back End
A, B, C
47
E
Program Front End
A
13
F
Project Consolidation
D, E
11
(a) For the given project, fill in the nodes of the network diagram below.
A
E
33
13
Start
B
D
F
Finish
Time
21
47
11
Time
C
35
(b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns.
Activity
Earliest Start (ES)
Latest…
Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows:
Activity
Activity Description
Immediate Predecessor
Activity time (days)
A
Identify Client Base
―
44
B
Develop Client Prospectus
―
35
C
Perform Design Analysis
―
46
D
Program Back End
A, B, C
43
E
Program Front End
A
27
F
Project Consolidation
D, E
36
(a) For the given project, fill in the nodes of the network diagram below.
A
E
44
27
Start
B
D
F
Finish
Time
35
43
36
Time
C
46
(b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns.
Activity
Earliest Start (ES)
Latest…
a) Table Q3a. shows the logic for a particular project.
(i) Construct a network diagram showing the various logical activity
relationships from this information
(ii) Perform a forward and backward pass to complete the activity
boxes
(iii) Highlight the critical path on your diagram and state the earliest
project completion time.
Time (days)
Activity
A
Precedence
В
A
3
C
A
4
4
E
B
2
F
В
4
G
3
H
D
6
J
Е, F
3
K
G
4
L
G
7
H, I
J, К, L
М, N
Table Q3a
M
N
8
Chapter 3 Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
Ch. 3 - Prob. 1EDCh. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...
Ch. 3 - Describe how expected activity times and variances...Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - Prob. 20DQCh. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - Prob. 1PCh. 3 - Prob. 2PCh. 3 - Prob. 3PCh. 3 - Prob. 4PCh. 3 - Prob. 8PCh. 3 - Prob. 13PCh. 3 - Prob. 15PCh. 3 - Prob. 17PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 33PCh. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Time Activity (in hours) Immediate Predecessor(s) A B C D E F G 7.0 6.7 6.0 8.0 5.1 7.7 6.0 A B, C B, C D E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in C Figure 1 A B Figure 2 B F E F Earrow_forwardBuild a PERT Analysis for a 3-month project with 6 activities (A to F) and 5 nodesarrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B C D E F G H A B (c) Develop the activity schedule for the project. Earliest Activity Start с D E Description Survey building site Develop initial design Obtain board approval F G Select architect Establish budget Finalize design Obtain financing Hire contractor H 0 0 7 18 18 25 25 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen This answer has not been graded yet. 38 (b) Identify the critical path. (Enter your answers as a comma-separated list.) B.C.EFH ✓ Immediate Predecessor X X x 2 0 7 21 18 25 X 27 A, B с 38 с D, E E F, G Latest Start x x X Time (weeks) 5 X 7 x 10 3 5 13 11 6 5 18 22 25 38 36 47 Earliest…arrow_forward
- Part 1: Below matrix shows one of the important data used in project management, identify the name of the matrix and explain the roles of each person involved in this matrix. Total= 10 marks Facilities Plant Mgr HR Security Project Mgr Identify a minimum of three asphalt R contractors from Angie's List Arrange for contractor visits and quotes Review quotes and references, A R make contractor selection Review and finalize contract, lock in plant shutdown week R Communicate project to shutdown maintenance crew, make sure all R vehicles are removed from the lot Provide security gate access codes for asphalt crew by June 15 A Oversee the project during the plant shutdown week, ensure it is A R completed on time R = Responsible, A = Accountable, C = Consulted, I = Informedarrow_forwardTask time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity AB A E F G Time (in hours) 7.0 7.2 5.0 8.0 4.5 7.7 5.0 Immediate Predecessor(s) || | < B, C B, C D E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in Figure 1 Figure 2 Figure 3 Figure 1 B Figure 2 B Figure 3 A F E E LL F F Narrow_forwardThe following table contains information related to the major activities of a research project. Use the information to do the following: a. Draw a precedence diagram using AOA , AON and Gantt chart. b. Find the critical path using CPM. c. Determine the expected length of the project. Activity Predecessor Time in days A 2 D A 6 E D 7 H E 2 F A 3 G F 5 В 3 в 6 J 5 K J 8 12 M 1 N M 11 N 13 End Н, G, К, Оarrow_forward
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Activity Predecessor(s) Time (days) 4 5 3 III B 10 A, D 3 C 5 G E, F 12 This exercise contains only part a. a) The correct precedence diagram for the project is shown in ABCDEF Ñ GW 8 w or C A B F Figure 2 A B O-O Figure 3 B E E Earrow_forwardNB: Answer all the questions within 30 mins Table 1 Activity Predecessor Duration (weeks) A - 5 B A 4 C A 5 D B 6 E C 3 F D, E 4 Use Table 1 to calculate the following: Draw the resultant Gantt chart. Construct the PERT/CPM chart for the tasks as they appear in Table 1.[1] HINT: Do not forget the Start Date and Finish Date for each task. Indicate at minimum three dependent task patterns. Indicate all the multiple successor tasks. Indicate all the multiple predecessor tasks. Show the critical path of this project. Justify why the given critical path is valid.arrow_forwardConsider a project having the following ten activities: Immediate Activity A Time (weeks) Predecessors none 7 B none 3 A 5 А, В С, D 6 E 4 F D 4 G C 9 E, G E, F H, I H 8 I J 5 a)Construct AON diagram for the following data. b) Identify path, path duration and critical path c) Conduct CPM analysis by identifying ES, EF, LS, LF d) What is the slack for each activity and the critical path?arrow_forward
- Build a PERT Network Diagram for a 3-month project with 6 activities (A to F) and 5 nodesarrow_forwardTask time estimates for a production line setup project at XYZ Company are as follows; Activity Time (in hours) Immediate Predecessor A 6.0 7.2 5.0 A В, С В, С D 6.0 E 4.5 F 7.7 D 4.0 Е, F a. Draw the project network using AON. b. Draw Gantt chart. c. Identify the critical path, d. What is the expected project length? e. What is the slack time for individual activity? f. Determine ES, EF, LS, and LF for each activityarrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: This exercise contains only part a a) The correct precedence diagram for the project is shown in Activity Immediate Predecessor(s) Time (days) A BCDEF G 1100 AD C E. F 3 5 1 10 5 8 SE Flaure 1 A В Figure 2 A 6 F Figure 3 A B Earrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY