Using the data on the table, determine the following using transit rule.
Using Enumeration Method - list all paths and total duration.
Activity
Predecessor
Normal time
Normal cost
Crash time
Crash cost
Max Crash Time
Slope
A
-
12
$200
9
$350
B
A
8
$300
8
$300
C
A
9
$250
7
$450
D
B
6
$400
5
$600
E
B,C
5
$150
4
$225
F
C
10
$500
9
$650
G
D,E,F
8
$400
6
$900
QUESTION 6
RING 1
RING 2
$1
1 CAL
$5
MAJOR STREET
$2
O none
$6
BARRIER
= Phase Number
= Protected Movement
$3
MINOR STREET
$4
= Permitted Movement
Pedestrian Movement
BARRIER
In this ring and barrier diagram, what sequencing is used for the protected left turns?
O lead-lead
lead-lag
lag-lag
Knowledge Booster
Similar questions
- Find the station kilometer of point B with curb radii of R1 and R2 according to the information given.arrow_forwardQUESTION 2 RING 1 RING 2 1 $5 MAJOR STREET $2 $6 BARRIER - Phase Number = Protected Movement 43 MINOR STREET $4 Permitted Movement - Pedestrian Movement BARRIER In this ring and barrier diagram, which phase pairs constitute a concurrency group? phase pair containing phases 1 and phase 2 & phase pair containing phase 3 and phase 4 O phase pair containing phase 1 and phase 5 & phase pair containing phase 2 and phase 6 phase pair containing phase 1 and phase 2 & phase pair containing phase 5 and phase 6 O phase pair containing phase 5 and phase 6 & phase pair containing phase 3 and phase 4arrow_forwardRING 1 RING 2 $1 1 $5 MAJOR STREET $2 OJL $6 BARRIER = Phase Number = Protected Movement $3 MINOR STREET $4 = Permitted Movement >= Pedestrian Movement BARRIER In this ring and barrier diagram, which phase pairs constitute a concurrency group? O phase pair containing phases 1 and phase 2 & phase pair containing phase 3 and phase 4 phase pair containing phase 1 and phase 5 & phase pair containing phase 2 and phase 6 O phase pair containing phase 1 and phase 2 & phase pair containing phase 5 and phase 6 O phase pair containing phase 5 and phase 6 & phase pair containing phase 3 and phase 4arrow_forward
- Given the following data on a route survey of a proposed road, determine the following; FHD = 50 m. a. stationing of the limits of free haul b. length of overhaul STATION END AREA (m²) STATION END AREA (m?) CUT FILL CUT FILL 2 + 000 20 + 120 + 140 + 160 20 + 020 30 60 80 + 040 + 060 + 080 + 100 40 20 + 180 20 10 2 + 200 10arrow_forward$1 $5 MAJOR STREET 42 lead-lag lag-lag none 46 BARRIER -Phase Number -Protected Movement 43 MINOR STREET LU Permitted Movement >-Pedestrian Movement BARRIER In this ring and barrier diagram, what sequencing is used for the protected left turns? lead-leadarrow_forwardThe following cross-section notes of the road was examined to calculate volumes. The width of the roadway is 12m -12 -3 -6 4 +6 -6 +24 -9 STA 5+040 +6 -15 -4.5 -6 -6 30 -12 -7 -8 STA 5+140 Compute the volume between two stations using end area method.arrow_forward
- Using Enumeration Method - list all paths and total duration. Use the chart provided for the infomation needed Activity Predecessor Normal time Normal cost Crash time Crash cost Max Crash Time Slope A 5 $200 4 $350 B A 8 $220 8 $220 C B 6 $250 4 $650 D A 9 $500 5 $600 E A,C 10 $150 9 $500 F E 10 $500 9 $650 G D,F 8 $400 6 $900arrow_forwardRING 1 RING 2 $1 2 $5 MAJOR STREET $2 LL $6 Stri BARRIER = Phase Number = Protected Movement $3 MINOR STREET $4 = Permitted Movement >= Pedestrian Movement BARRIER In this ring and barrier diagram, which phases cannot be reversed in their sequencing? phase 1 and phase 2 phase 5 and phase 6 phase 1 and phase 5 phase 3 and phase 4arrow_forwardRING 1 RING 2 $1 2 $5 lead-lag lag-lag MAJOR STREET none $2 $6 BARRIER Phase Number = Protected Movement 43 MINOR STREET $4 = Permitted Movement = Pedestrian Movement In this ring and barrier diagram, what sequencing is used for the protected left turns? O lead-lead BARRIERarrow_forward
- RING 1 RING 2 $1 MAJOR STREET $2 11 сл 46 YPI BARRIERI Phase Number = Protected Movement $3 MINOR STREET $4 Permitted Movement >= Pedestrian Movement BARRIER In this ring and barrier diagram, which phases cannot be reversed in their sequencing? phase 1 and phase 2 phase 5 and phase 6 phase 1 and phase 5 phase 3 and phase 4arrow_forwardUsing the following trip distribution matrix and road network: a) Identify the minimum path between each TAZ pair. b) Estimate the traffic flow on each linkarrow_forwardFrom the given cross-section of the proposed barangay road. determine: a) The volume between the two stations using Prismoidal Formula b) The volume between the two stations using end area applying Prismoidal correctionarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Solid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,