Managerial Accounting (5th Edition)
5th Edition
ISBN: 9780134128528
Author: Karen W. Braun, Wendy M. Tietz
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 3.23AE
Determine the cost of a job (Learning Objectives 2, 3, & 4)
Fontaine Furniture started and finished Job 310 during April. The company’s records show that the following direct materials were requisitioned for Job 310:
Lumber: 45 units at $4 per unit
Padding: 13 yards at $14 per yard
Upholstery fabric: 25 yards at $30 per yard
Labor time records show the following employees (direct labor) worked on Job 310:
Penny Rawls: 12 hours at $13 per hour
Mark Frizzell: 16 hours at $22 per hour
Fontaine allocates manufacturing
Requirements
- 1. Compute the total amount of direct materials, direct labor, and manufacturing overhead that should be shown on Job 310’s
job cost record. - 2. Job 310 consists of twelve recliners. If each recliner sells for $750, what is the gross profit per recliner?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The computer workstation furniture manufacturing that Santana Rey started is progressing well. As of the end of June,
Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs.
Direct materials
Direct labor
Overhead applied
Job 602
$ 1,400
800
320
Job 602 was started in May, and the following costs were assigned to it in May: direct materials, $700; direct labor, $250;
and overhead, $100. Jobs 603 and 604 were started in June. Overhead cost is applied with a predetermined rate as a
percent of direct labor costs. Jobs 602 and 603 are finished in June, and Job 604 is expected to be finished in July. The
company's predetermined overhead rate did not change over these months.
Required 1
Required:
1. What is the cost of direct materials used in June for each of the three jobs and in total?
2. What is the cost of direct labor used in June for each of the three jobs and in total?
3. What predetermined overhead rate is used in June?
4. How much…
Jagjit Company designs and builds retaining walls for individual customers. On August 1, there were two jobs in process: Job 93 with a beginning balance of $8,650, and Job 94 with a beginning balance of $7,270. Jagjit applies overhead at the rate of $9 per direct labor hour. Direct labor wages average $16 per hour. Data on August costs for all jobs are as follows:
Job 93
Job 94
Job 95
Job 96
Direct materials
$910
$4,590
$3,330
$1,270
Direct labor cost
2,080
4,800
2,400
960
During August, Jobs 95 and 96 were started. Job 93 was completed on August 17, and the client was billed at cost plus 40%. All other jobs remained in process.
efer to the list below for the exact wording of text items within your job-order cost sheets.
Amount Descriptions
Applied overhead
Beginning balance
Direct labor
Direct materials
Total
Required:
1.
Calculate the number of direct labor hours that were worked on each job in August.
2.
Calculate the…
The computer workstation furniture manufacturing that Santana Rey started in January is progressing well. As of the
end of June, Business Solutions's job cost sheets show the following total costs accumulated on three furniture jobs.
Job 602
Job 603
Job 604
Direct
$1,800
$3,300
$2,700
materials
Direct
900
1,480
2,300
labor
Overhead
450
740
1,150
Job 602 was started in production in May, and these costs were assigned to it in May: direct materials, $600; direct
labor, $250; and overhead, $125. Jobs 603 and 604 were started in June. Overhead cost is applied with a
predetermined rate based on direct labor costs. Jobs 602 and 603 are finished in June, and Job 604 is expected to be
finished in July. No raw materials are used indirectly in June. (Assume this company's predetermined overhead rate did
not change over these months.)
Required:
1. What is the cost of the raw materials used in June for each of the three jobs and in total?
2. How much total direct labor cost is incurred in June?
3.…
Chapter 3 Solutions
Managerial Accounting (5th Edition)
Ch. 3 - (Learning Objective 1) For which of the following...Ch. 3 - (Learning Objective 2) Which of the following...Ch. 3 - (Learning Objective 2) Which of the following...Ch. 3 - (Learning Objective 3) The amount of manufacturing...Ch. 3 - (Learning Objective 4) Which of the following is...Ch. 3 - (Learning Objective 5) Which of the following is...Ch. 3 - (Learning Objective 5) Assuming the amount of...Ch. 3 - Prob. 8QCCh. 3 - Prob. 9QCCh. 3 - Prob. 10QC
Ch. 3 - Identify product costs, period costs, and product...Ch. 3 - Decide on product costing system (Learning...Ch. 3 - Determine the flow of costs between inventory...Ch. 3 - Understanding key document terms in a job cost...Ch. 3 - Compute a professional billing rate (Learning...Ch. 3 - Prob. 3.6SECh. 3 - Continuation of S3-6: compute total allocated...Ch. 3 - Continuation of S3-7: determine over- or under...Ch. 3 - Prob. 3.9SECh. 3 - Calculate job cost and billing at appliance repair...Ch. 3 - Calculating overallocated or underallocated...Ch. 3 - Prob. 3.12SECh. 3 - Record manufacturing labor costs (Learning...Ch. 3 - Prob. 3.14SECh. 3 - Prob. 3.15SECh. 3 - Understanding key terms (Learning Objectives 1, 2,...Ch. 3 - Identify type of costing system (Learning...Ch. 3 - Prob. 3.18AECh. 3 - Determine the cost of a job and use it for pricing...Ch. 3 - Compute a predetermined overhead rate and...Ch. 3 - Prob. 3.21AECh. 3 - Prob. 3.22AECh. 3 - Determine the cost of a job (Learning Objectives...Ch. 3 - Compare bid prices under two different allocation...Ch. 3 - Analyze manufacturing overhead (Learning...Ch. 3 - Record manufacturing overhead (Learning Objectives...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze T-accounts (Learning Objectives 2, 3, 5, ...Ch. 3 - Job cost and bid price at a consulting firm...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Identify type of costing system (Learning...Ch. 3 - Understand the flow of costs in a job cost shop...Ch. 3 - Prob. 3.33BECh. 3 - Prob. 3.34BECh. 3 - Prob. 3.35BECh. 3 - Sustainability and job costing (Learning...Ch. 3 - Determine the cost of a job (Learning Objectives...Ch. 3 - Compare bid prices under two different allocation...Ch. 3 - Analyze manufacturing overhead (Learning...Ch. 3 - Record manufacturing overhead (Learning Objectives...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze T-accounts (Learning Objectives 2, 3, 5, ...Ch. 3 - Prob. 3.43BECh. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze Manufacturing Overhead (Learning...Ch. 3 - Use job costing at an advertising agency (Learning...Ch. 3 - Use job costing at a consulting firm (Learning...Ch. 3 - Prepare job cost record (Learning Objectives 2, 3,...Ch. 3 - Determine and record job costs (Learning...Ch. 3 - Determine flow of costs through accounts (Learning...Ch. 3 - Analyze Manufacturing Overhead (Learning...Ch. 3 - Use job costing at an advertising agency (Learning...Ch. 3 - Use job costing at a consulting firm (Learning...Ch. 3 - Prepare job cost record (Learning Objectives 2, 3,...Ch. 3 - Determine and record job costs (Learning...Ch. 3 - Determine flow of costs through accounts (Learning...Ch. 3 - Job costing or process costing for wedding...Ch. 3 - Discussion Questions 1. Why would it be...Ch. 3 - Unwrapped or How Its Made Go to www.YouTube.com...Ch. 3 - Ethics involved with choice of cost driver...Ch. 3 - Prob. 3.61ACTCh. 3 - Issues with cost of job (Learning Objectives 2, 3,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Source Documents For each of the following independent situations, give the source document that would be referred to for the necessary information. Required: 1. Direct materials costing 460 are requisitioned for use on a job. 2. Greiners Garage uses a job-order costing system. Overhead is applied to jobs based on direct labor hours. Which source document gives the number of direct labor hours worked on Job 2004-276? 3. Pasilla Investigative Services bills clients on a monthly basis for costs to date. Job 3-48 involved an investigator following the clients business partner for a week by automobile. Mileage is billed at number of miles times 0.75. 4. The foreman on the Jackson job wonders what the actual direct materials cost was for that job.arrow_forwardCycle Specialists manufactures goods on a job order basis. During the month of June, three jobs were started in process. (There was no work in process at the beginning of the month.) Jobs Sprinters and Trekkers were completed and sold, on account, during the month (selling prices: Sprinters, 22,000; Trekkers, 27,000); Job Roadsters was still in process at the end of June. The following data came from the job cost sheets for each job. The factory overhead includes a total of 1,200 of indirect materials and 900 of indirect labor. Prepare journal entries to record the following: a. Materials used. b. Factory wages and salaries earned. c. Factory Overhead transferred to Work in Process d. Jobs completed. e. Jobs sold.arrow_forwardRIRA Company makes attachments such as backhoes and grader and bulldozer blades for construction equipment. The company uses a job order cost system. Management is concerned about cost performance and evaluates the job cost sheets to learn more about the cost effectiveness of the operations. To facilitate a comparison, the job cost sheets for Job 206 (for 50 backhoe buckets completed in October) and Job 228 (for 75 backhoe buckets completed in December) were pulled and presented as follows: Management is concerned about the increase in unit costs over the months from October to December. To understand what has occurred, management interviewed the purchasing manager and quality manager. Purchasing Manager: Prices have been holding steady for our raw materials during the first half of the year. I found a new supplier for our bulk steel that was willing to offer a better price than we received in the past. I saw these lower steel prices and jumped on them, knowing that a reduction in steel prices would have a very favorable impact on our costs. Quality Manager: Something happened around mid-year. All of a sudden, we were experiencing problems with respect to the quality of our steel. As a result, weve been having all sorts of problems on the shop floor in our foundry and welding operation. a. Analyze the two job cost sheets and identify why the unit costs have changed for the backhoe buckets. Complete the following schedule to help in your analysis: b. How would you interpret what has happened in light of your analysis and the interviews?arrow_forward
- Pidris Drop Anchor takes special orders to manufacture sail boats for high-end customers. Prepare journal entries to record the transactions below and prepare job cost sheets for September. a. Purchased raw materials on credit, $145,000. b. Materials requisitions: Job 240, $48,000; Job 241, $36,000; Job 242, $42,000; indirect materials were $12,000. c. Time tickets used to charge labor to jobs: Job 240, $40,000; Job 241, $30,000; Job 242, $35,000, indirect labor is $25,000. d. The company incurred the following additional overhead costs: depreciation of factory building, $70,000; depreciation of factory equipment, $60,000; expired factory insurance, $10,000; utilities and maintenance cost of $20,000 were paid in cash. e. Applied overhead to all three jobs. The predetermined overhead rate is 190% of direct labor cost. f. Transferred jobs 240 and 242 to Finished Goods Inventory. g. Sold job 240 for $300,000 for cash. h. Closed the under- or over-applied overhead account balance. Job Cost…arrow_forwardRemote Education Technology, Incorporated started and finished job number B67 during June. The job required $47,800 of direct material and 400 hours of direct labor at $26 per hour. The predetermined overhead rate is $5 per direct-labor hour. Required: Prepare journal entries to record the incurrence of production costs and the completion of job number B67.arrow_forwardAt the end of June, the job cost sheets at Ace Roofers show the following costs accumulated on three jobs. Job 6 $33,000 At June 30 Direct materials Direct labor Overhead applied Additional Information a. Job 5 was started in May, and the following costs were assigned to it in May; direct materials, $6,000; direct labor, $1,800; and applied overhead, $900. Job 5 was finished in June. b. Job 6 and Job 7 were started in June; Job 6 was finished in June, and Job 7 is to be completed in July. c. Overhead cost is applied with a predetermined rate based on direct labor cost. The predetermined overhead rate did not change across these months. Job 5 $ 15,000 Direct materials requisitioned in June 8,000 4,000 Job 7 $27,000 21,000 10,500 14,200 7,100 Required 1. What is the total cost of direct materials requisitioned in June?arrow_forward
- Finley Educational Products started and finished job number B67 during June. The job required $4,600 of direct material and 40 hours of direct labor at $17 per hour. The predetermined overhead rate is $5 per direct-labor hour.Required: Prepare journal entries to record the incurrence of production costs and the completion of job number B67.arrow_forwardInformation on Kwon Manufacturing’s activities for its first month of operations follows: Purchased $100,300 of raw materials on credit. Materials requisitions show the following materials used for the month. Job 201 $ 48,500 Job 202 23,900 Total direct materials 72,400 Indirect materials 8,920 Total materials used $ 81,320 Time tickets show the following labor used for the month. Job 201 $ 39,500 Job 202 12,900 Total direct labor 52,400 Indirect labor 24,500 Total labor used $ 76,900 Applied overhead to Job 201 and to Job 202 using a predetermined overhead rate is 80% of direct materials cost. Transferred Job 201 to Finished Goods Inventory. (1) Sold Job 201 for $164,660 on credit. (2) Record cost of goods sold for Job 201. Incurred the following actual other overhead costs for the month. Depreciation of factory equipment $ 32,300 Rent on factory building (payable) 530 Factory utilities (payable) 830 Expired factory insurance…arrow_forwardRequired information (The following information applies to the questions displayed below.) At the end of June, the job cost sheets at Ace Roofers show the following costs accumulated on three jobs. Job 5 $ 15, 400 8, 400 4, 200 Job 6 $ 33, 200 14, 600 7, 300 At June 30 Job 7 Direct materials $ 27, 200 21,400 10, 700 Direct labor Overhead applied Additional Information a. Job 5 was started in May, and the following costs were assigned to it in May: direct materials, $6,200; direct labor, $2,000; and applied overhead, $1,100. Job 5 was finished in June. b. Job 6 and Job 7 were started in June; Job 6 was finished in June, and Job 7 is to be completed in July. c. Overhead cost is applied with a predetermined rate based on direct labor cost. The predetermined overhead rate did not change across these months. 3. What is the predetermined overhead rate? Predetermined overhead ratearrow_forward
- Redwoods Company designs and builds exotic furniture for individual customers. On March 1, there were two jobs in process: Job 400 with a beginning balance of $23,000 and Job 402 with a beginning balance of $6,000. Overhead costs are applied by using a rate of 50% of direct labor costs. Both jobs are unfinished on March 31. Data on March costs for both the jobs are as follows: Job 400 Job 402 Direct materials $6,000 $ 10,000 Direct labor cost 4,000 13,000 What is the total of the work-in-process account on March 31? a.$38,000 b.$58,490 c.$45,000 d.$70,500 e.None of these choices are correct.arrow_forwardInformation on Kwon Manufacturing’s activities for its first month of operations follows: a. Purchased $101,100 of raw materials on credit. b. Materials requisitions show the following materials used for the month. Job 201 $ 49,300 Job 202 24,700 Total direct materials 74,000 Indirect materials 9,720 Total materials used $ 83,720 c. Time tickets show the following labor used for the month. Job 201 $ 40,300 Job 202 13,700 Total direct labor 54,000 Indirect labor 25,300 Total labor used $ 79,300 d. Applied overhead to Job 201 and to Job 202 using a predetermined overhead rate of 80% of direct materials cost. e. Transferred Job 201 to Finished Goods Inventory. f. Sold Job 201 for $167,060 on credit. g. Incurred the following actual other overhead costs for the month. Depreciation of factory equipment $ 33,100 Rent on factory building (payable) 610 Factory utilities (payable) 910 Expired factory insurance 4,100 Total other factory overhead costs $…arrow_forwardInformation on Kwon Manufacturing’s activities for its first month of operations follows: Purchased $101,900 of raw materials on credit. Materials requisitions show the following materials used for the month. Job 201 $ 50,100 Job 202 25,500 Total direct materials 75,600 Indirect materials 10,520 Total materials used $ 86,120 Time tickets show the following labor used for the month. Job 201 $ 41,100 Job 202 14,500 Total direct labor 55,600 Indirect labor 26,100 Total labor used $ 81,700 Applied overhead to Job 201 and to Job 202 using a predetermined overhead rate of 80% of direct materials cost. Transferred Job 201 to Finished Goods Inventory. Sold Job 201 for $169,460 on credit. Incurred the following actual other overhead costs for the month. Depreciation of factory equipment $ 33,900 Rent on factory building (payable) 690 Factory utilities (payable) 990 Expired factory insurance 4,900 Total other factory overhead costs $ 40,480…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Cost Accounting - Definition, Purpose, Types, How it Works?; Author: WallStreetMojo;https://www.youtube.com/watch?v=AwrwUf8vYEY;License: Standard YouTube License, CC-BY