Question
Chapter 3, Problem 3.6SE
To determine
To calculate: Calculate predetermined manufacturing
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
The following information is provided to you:
Time taken to produce first 8 shock pads 640 hours
Time taken to produce first 16 shock pads 1200 hours
Calculate the learning curve
The following information is provided to you:
Direct labour needed to make first machine. 1000 hoursLearning curve. 80%Direct labour cost. R300 per hourDirect materials cost. R180000 per machine
Fixed cost for machines at each cumulative production R800000
Calculate the total direct hours required to manufacture four (4) machines. ( Indicate both average time per unit as well as cumulative time per unit for all theunits)
Calculate the total costs to manufacture 4 machines
can you provide step by step solution to every question?
If a 70% learning curve is used, using the cumulative average time model, the cumulative direct labor hours required to produce a total eight units would be:
Chapter 3 Solutions
Managerial Accounting (5th Edition)
Ch. 3 - (Learning Objective 1) For which of the following...Ch. 3 - (Learning Objective 2) Which of the following...Ch. 3 - (Learning Objective 2) Which of the following...Ch. 3 - (Learning Objective 3) The amount of manufacturing...Ch. 3 - (Learning Objective 4) Which of the following is...Ch. 3 - (Learning Objective 5) Which of the following is...Ch. 3 - (Learning Objective 5) Assuming the amount of...Ch. 3 - Prob. 8QCCh. 3 - Prob. 9QCCh. 3 - Prob. 10QC
Ch. 3 - Identify product costs, period costs, and product...Ch. 3 - Decide on product costing system (Learning...Ch. 3 - Determine the flow of costs between inventory...Ch. 3 - Understanding key document terms in a job cost...Ch. 3 - Compute a professional billing rate (Learning...Ch. 3 - Prob. 3.6SECh. 3 - Continuation of S3-6: compute total allocated...Ch. 3 - Continuation of S3-7: determine over- or under...Ch. 3 - Prob. 3.9SECh. 3 - Calculate job cost and billing at appliance repair...Ch. 3 - Calculating overallocated or underallocated...Ch. 3 - Prob. 3.12SECh. 3 - Record manufacturing labor costs (Learning...Ch. 3 - Prob. 3.14SECh. 3 - Prob. 3.15SECh. 3 - Understanding key terms (Learning Objectives 1, 2,...Ch. 3 - Identify type of costing system (Learning...Ch. 3 - Prob. 3.18AECh. 3 - Determine the cost of a job and use it for pricing...Ch. 3 - Compute a predetermined overhead rate and...Ch. 3 - Prob. 3.21AECh. 3 - Prob. 3.22AECh. 3 - Determine the cost of a job (Learning Objectives...Ch. 3 - Compare bid prices under two different allocation...Ch. 3 - Analyze manufacturing overhead (Learning...Ch. 3 - Record manufacturing overhead (Learning Objectives...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze T-accounts (Learning Objectives 2, 3, 5, ...Ch. 3 - Job cost and bid price at a consulting firm...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Identify type of costing system (Learning...Ch. 3 - Understand the flow of costs in a job cost shop...Ch. 3 - Prob. 3.33BECh. 3 - Prob. 3.34BECh. 3 - Prob. 3.35BECh. 3 - Sustainability and job costing (Learning...Ch. 3 - Determine the cost of a job (Learning Objectives...Ch. 3 - Compare bid prices under two different allocation...Ch. 3 - Analyze manufacturing overhead (Learning...Ch. 3 - Record manufacturing overhead (Learning Objectives...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze T-accounts (Learning Objectives 2, 3, 5, ...Ch. 3 - Prob. 3.43BECh. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze Manufacturing Overhead (Learning...Ch. 3 - Use job costing at an advertising agency (Learning...Ch. 3 - Use job costing at a consulting firm (Learning...Ch. 3 - Prepare job cost record (Learning Objectives 2, 3,...Ch. 3 - Determine and record job costs (Learning...Ch. 3 - Determine flow of costs through accounts (Learning...Ch. 3 - Analyze Manufacturing Overhead (Learning...Ch. 3 - Use job costing at an advertising agency (Learning...Ch. 3 - Use job costing at a consulting firm (Learning...Ch. 3 - Prepare job cost record (Learning Objectives 2, 3,...Ch. 3 - Determine and record job costs (Learning...Ch. 3 - Determine flow of costs through accounts (Learning...Ch. 3 - Job costing or process costing for wedding...Ch. 3 - Discussion Questions 1. Why would it be...Ch. 3 - Unwrapped or How Its Made Go to www.YouTube.com...Ch. 3 - Ethics involved with choice of cost driver...Ch. 3 - Prob. 3.61ACTCh. 3 - Issues with cost of job (Learning Objectives 2, 3,...
Knowledge Booster
Similar questions
- Bordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardTo complete the first setup on a new machine took an employee 100 minutes. Using an 80% incremental unit-time learning model indicates that the second setup on the new machine is expected to take ________. Select one: a. 70 minutes b. 80 minutes c. 120 minutes d. 60 minutesarrow_forwardA home builder needs to schedule labor for the construction of 24 homes in a subdivision. In the past the builder has noted a 90% learning rate. If the first home requires 2000 labor hours to build, estimate the time required to build: a. The 4th house b. The 15th house c. All 24 housesarrow_forward
- E-LEARNING SYSTEM (ACADEMIC) E-LEARNING SERVICES SQU LIBRARIES - The correct answer is: Objectivity and verifiability Company XYZ is currently producing AND selling 10,000 units of product A. At this level, the total product cost was $60,000. This included $10,000 direct materials, $20,000 direct labor and $30,000 manufacturing overhead cost, which included 20% fixed manufacturing overhead cost. The selling and administrative expenses were $100,000, which included $60,000 variable selling and administrative costs. Assume that the selling price per unit $20, how much was the total contribution margin? O a. $134,000 O b. $194,000 O c. None of the given answers O d. $104,000 O e. $86,000 The correct answer is: $86,000 A period cost includes all EXCEPT: e here to search Lr Ps Quiz One: Att. DELL F2 F3 F4 F5 F6 F7 F8 BIO F9 F10 F11 #3 $ & 3 r 5 0 67 7 V 8 A 99arrow_forward$4-3 Compute departmental overhead rates (Learning Objective 1) Snyder Snacks makes potato chips, corn chips, and cheese puffs using three different pro- du es wi the same manufacturing plant. Currently, Snyder uses a single plant- wide overhead rate to allocate its $3,311,500 of annual manufacturing overhead. Of this amount, $2,070,000 is associated with the potato chip line, $763,000 is associated with the corn chip line, and $478,500 is associated with the cheese puff line. Snyder's plant is currently running a total of 17,900 machine hours: 11,500 in the potato chip line, 3,500 in the corn chip line, and 2,900 in the cheese puff line. Snyder considers machine hours to be the cost driver of manufacturing overhead costs. 1. What is Snyder's plantwide overhead rate? 2. Calculate the departmental overhead rates for Snyder's three production lines. Round all answers to the nearest cent. 3. Which products have been overcosted by the plantwide rate? Which products have been undercosted by…arrow_forwardSharon Glessing, controller for Janson Company, has noticed that the company faces a 80 percent learning rate for its specialty design line. In planning the cost of the latest design, Sharon assumed that the first set of units would take 1,100 direct labor hours. She decided to use this information in budgeting for the cost of the total project, which would involve the manufacture of 16 sets. Direct labor is paid $40 per hour. 1. Complete the table below showing results by row for total production of: one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) (Round Cumulative Total Time answers to the nearest whole number.) 2. What is the total labor cost if Janson Company makes eight sets? Sixteen sets? (Use the rounded answers in the subsequent computations). 3. Using the logarithmic function, complete the table below showing results by row for each of unit sets one through eight. (Round hour answers to two significant digits.)…arrow_forward
- solve within 30 minsarrow_forwardThe following scenario relates to 5 questions. Bear Co has developed a new model of television. The estimated labour time for the first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight units produced Note: The learning index for a 75% learning curve is-0-415. Overhead production costs must be estimated based on a previous model, the Leonardo, that was made by Bear Co. Production quantities and total overhead costs for the last four months of production of the Leonardo were as follows: Month Output Total overhead cost (units) $ September 1,800 278,200 October 2,000 310,000 November 1,700 252,900 December 1,000 200,000 The first phase of production has now been completed for the new television. The first unit actually took 12-5 hours to make and the total time for the first eight units was 34-3 hours, at which point the learning effect came to an end. What is the actual learning rate, and did the labour force learn more quickly or less quickly than…arrow_forwardYour firm designs training materials for computer training classes, and you have just received a request to bid on a contract to produce a complete set of training manuals for an 8-session class. From previous experience, you know that your firm follows a 90% learning rate. For this contract, it appears that the effort will be substantial, running 400 hours for the first session. Your firm has an average cost of labor of $60/hour and the overhead is expected to run a fixed $1000 per session. The customer will pay you a flat fixed rate per session (Per Session Price.) If your profit markup is 12%, what will be the Total Price, the Per Session Price, and at what session will you break even? Answer the following four questions: What is the Total Price? This is what you would charge the customer so that you can have your profit markup of 10% over all of your costs. To calculate this, first figure out your cost per each session, add them up, and then add your profit. What is the Per…arrow_forward
- The following scenario relates to 5 questions. Bear Co has developed a new model of television. The estimated labour time for the first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight units produced Note: The learning index for a 75% learning curve is -0.415. Overhead production costs must be estimated based on a previous model, the Leonardo, that was made by Bear Co. Production quantities and total overhead costs for the last four months of production of the Leonardo were as follows: Month Output Total overhead cost (units) $ September 1,800 278,200 October 2,000 310,000 November 1,700 252,900 December 200,000 1,000 You have been asked to estimate the variable overhead cost per unit of the new television by assuming that it will be the same as for the Leonardo, using the information provided for the last four months of its manufacture, and applying a 6% inflation rate. What is the variable cost per unit using the high-low method (to two decimal…arrow_forwardA professional division at a business school provides several development programs that have been tailored to the specific training needs of both the public and private sectors. The program director is planning to offer a one-full-day course in risk management to be sold at $2,250 plus orientation fee (5%) per participant. The division incurs a cost of $45,000 for promotion, classroom space, staff and instructor’s salary, as well as a cost of $240 per participant for refreshments, lunch, course material, a gift package, and a framed certificate of completion. How many participants need to register in the course for it to be worthwhile to offer it? Round to two decimal places. Group of answer choices 21.20 26.86 36.72arrow_forwardThe actual and planned data for Underwater University for the Fall term were as follows: Actual Planned Enrollment 4,500 4,125 Tuition per credit hour $120 $135 Credit hours 60,450 43,200 Registration, records, and marketing costs per enrolled student $275 $275 Instructional costs per credit hour $64 $60 Depreciation on classrooms and equipment $825,600 $825,600 Registration, records, and marketing costs vary by the number of enrolled students, while instructional costs vary by the number of credit hours. Depreciation is a fixed cost. Prepare a variable costing income statement showing the contribution margin and operating income for the Fall term. Underwater University Variable Costing Income Statement For the Fall Term Revenue $ Variable costs: Registration, records, and marketing costs $ Instructional costs Total variable costs $ Contribution margin $ Depreciation on classrooms and equipment Operating income…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning