Question
Chapter 26, Problem 1ADM
To determine
Lead Time: Lead time is the time consumed for the creation of a product. It refers to the time period between the time the order is placed and the product is completed. Lesser lead time creates a more competitive edge for the company.
Lead Time = Wait time + Process time + Queue time + Move time + Inspection Time
Wait time – Wait time refers to the time the product has to wait before the actual production begins.
Queue time – Queue time refers to the time the product spends waiting in a queue to be processed.
Move time – Move time refers to the time the product spends moving from one process to another.
To Suggest: Changes in the process to reduce the lead time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Sunshield Insurance takes 15 days to make payments on insurance claims. Claims are processed through three departments: data input, claims audit, and claims adjustment. The three departments are located in different buildings, approximately one hour apart from each other. Claims are processed in batches of 200. Each batch of 200 claims moves through three departments on a wheeled cart. Management is concerned about customer dissatisfaction. Hence, the implementation of the following measures is adopt by the management to reduce lead time.
Adopt just-in-time principles in its claims payment operations
Switching from paper forms to electronic forms
Design claims payment "cells" that are organized around different types of insurance products or customers rather than processes
Implement a "pull" scheduling processes.
Please provide explanation for each measure on how it reduces the lead time of Sunshield. Thanks
A typical dentist’s office has a complicated mix of dental procedures and significant setup times; thus, it is similar to a job shop. Suppose a dentist works a 9-hour day with one hour for lunch and breaks. During the first six months the practice is open, he does all the work, including cleaning and setting up for the next dental procedure. Setup and processing times for three procedures are shown in the Microsoft Excel Online file below. Also shown are the number of appointments and demand for each type.
On a particular day, there are two scheduled first appointments for single tooth crowns (see last column of the table in the Microsoft Excel Online file below), one second appointment for a single tooth crown, three tooth-whitening appointments, four first appointments for a partial denture, one second appointments for a partial denture, and three third appointments for a partial denture. Assume there is one setup time per dental procedure to set up and clean the equipment and room…
A customer support call center receives an average of 20 calls per hour, and it employs
number of agents to answer the calls. If an agent takes on average 30 minutes to answer a
call, what is the minimum number of agents need to ensure that average customer waiting
time is less than 1 minutes? (You can assume CVa = CVp = 1).
17
15
13
11
Chapter 26 Solutions
Financial & Managerial Accounting
Ch. 26 - Prob. 1DQCh. 26 - Prob. 2DQCh. 26 - Why is a product-oriented layout preferred by lean...Ch. 26 - Prob. 4DQCh. 26 - Prob. 5DQCh. 26 - Why would a lean manufacturer strive to produce...Ch. 26 - Prob. 7DQCh. 26 - Prob. 8DQCh. 26 - Prob. 9DQCh. 26 - Why is the direct labor cost category eliminated...
Ch. 26 - Prob. 11DQCh. 26 - Prob. 12DQCh. 26 - Prob. 13DQCh. 26 - Lead time Rough Riders Inc. manufactures jeans in...Ch. 26 - Lean features Which of the following are features...Ch. 26 - Lean accounting The annual budgeted conversion...Ch. 26 - Cost of quality report A quality control activity...Ch. 26 - Process activity analysis Roen Company incurred an...Ch. 26 - Prob. 26.1EXCh. 26 - Prob. 26.2EXCh. 26 - Lean principles Active Apparel Company...Ch. 26 - Lead time analysis Palm Pals Inc. manufactures toy...Ch. 26 - Reduce setup time Hammond Inc. has analyzed the...Ch. 26 - Calculate lead time Flint Fabricators Int....Ch. 26 - Calculate lead time Williams Optical Inc. is...Ch. 26 - Prob. 26.8EXCh. 26 - Prob. 26.9EXCh. 26 - Lean principles for a restaurant The management of...Ch. 26 - Prob. 26.11EXCh. 26 - Lean accounting Westgate Inc. uses a lean...Ch. 26 - Lean accounting Modern Lighting Inc. manufactures...Ch. 26 - Lean accounting Vintage Audio Inc. manufactures...Ch. 26 - Pareto chart Meagher Solutions Inc. manufacture....Ch. 26 - Prob. 26.16EXCh. 26 - Pareto chart for a service company Three Rivers...Ch. 26 - Cost of quality and value-added/non-value-added...Ch. 26 - Process activity analysis The Brite Beverage...Ch. 26 - Process activity analysis for a service company...Ch. 26 - Prob. 26.21EXCh. 26 - Prob. 26.1APRCh. 26 - Lead time Sound Tek Inc. manufactures electronic...Ch. 26 - Lean accounting Dashboard Inc. manufactures and...Ch. 26 - Pareto chart and cost of quality report for a...Ch. 26 - Prob. 26.1BPRCh. 26 - Lead time Master Chef Appliance Company...Ch. 26 - Lean accounting Com-Tel Inc. manufactures and...Ch. 26 - Pareto chart and cost of quality report for a...Ch. 26 - Prob. 1ADMCh. 26 - Turn around time in an operating room of a...Ch. 26 - Prob. 3ADMCh. 26 - Ethics in Action In August, Lannister Company...Ch. 26 - Prob. 26.3TIF
Knowledge Booster
Similar questions
- Golding Bank provided the following data about its resources and activities for its checking account process: Required: 1. Calculate the capacity cost rate for the checking account process. 2. Calculate the activity rates for the four activities. If the total number of statements issued was 20,000, calculate the cost of the issuing statements activity. 3. What if process improvements decreased the number of customer inquiries, leading to a 10 percent reduction in check processing hours and a 10,000 reduction in total resource costs? Update all the activity rates for these changes in operating conditions.arrow_forwardLong lines of patients wait for CAT scanning service in a hospital. Patients arrive for scans at a rate of 1.9 per hour. The average processing time for CAT service is 27 minutes per patient. Your summer internship is in the hospital where you are assigned to help analyze the bottleneck situation. One tool that you think can help evaluate the situation is a single server queueing model. Use the Single Server Queue Excel template to answer the following questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the system is empty? What is the probability that a customer must wait for service? What is the average number of customers waiting for service in the queue? customer(s) What is the average wait time in the queue? hour(s) What is the average time spent in the system? hour(s)arrow_forwardThese problems illustrate the application of Little’s Law. 1. Suppose that a voting facility processes an average of 57 people per hour (throughput) and that, on average, it takes 35 minutes for each person to complete the voting process (flow time). 2. Suppose that the loan department of a bank takes an average of 15 days (0.5 months) to process an application (flowtime) and that an internal audit found that about 100 applications are in various stages of processing at any one time (work-in-process). 3. Suppose that a restaurant makes 350 pizzas per week, each of which uses 1/2 pound of dough, and that it typically maintains an inventory of 60 pounds of dough. Open the spreadsheet and perform the required analysis to answer the questions below. 1. What is the work-in-process for the problem 1? Round your answer to two decimal places. ______ voters 2. What is the throughput (per month) for the problem 2? Round your answer to the nearest whole value. ____________ applications per…arrow_forward
- Valley Hospital began using standards to evaluate its Admissions Department. The standard was broken into two types of admissions as follows: Type of Admission Standard Time to CompleteAdmission Record Unscheduled 30 min. Scheduled 20 min. The unscheduled admission took longer because name, address, and insurance information needed to be determined and verified at the time of admission. Information was collected on scheduled admissions prior to admitting the patient, thus requiring less time in admissions. The Admissions Department employs four full-time people for 40 hours per week at $15 per hour. For the most recent week, the department handled 176 unscheduled and 240 scheduled admissions. a. How much was actually spent on labor for the week?$ b. What are the standard hours for the actual volume of work for the week? (Round to the nearest whole hour.) hours c. Compute the direct labor time variance, and report how well the department performed for the…arrow_forwardConsider the checkout process of a grocery store with ten identical cashiers performing the checkout process. First, assume that each cashier has her own separate checkout queue and that customers arrive at each case with an average arrival rate of 12 per hour. It takes 4.8 minutes on average to check a customer out. Assume that both the inter-arrival times and service times have a coefficient variation of 1. 1) How long on average does a customer wait from joining the queue in front of a cashier until her checkout is complete? 2) On average, how many customers are waiting in the queue in total? ( Including all queues)? 3) Now suppose the ten queues are pooled together so that there is one common queue. Repeat your calculations for part a and b, compare the results, and explain the differencearrow_forwardManagement of Mittel Company would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.4 days Wait time (from order to start of production) 16.5 days Process time 2.8 days Move time 0.7 days Queue time 3.7 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non–value-added activities? (Round your percentage answer to nearest whole percent.) 4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.) 5. If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate…arrow_forward
- A quality control activity analysis indicated the following four activity costs of a hotel. Verifying credit card information $486,000 Customer service training 364,500 Discounting room rates due to poor customer service 243,000 Correcting charges to customer invoices 121,500 Total $1,215,000 Sales are $8,100,000 for the year. Prepare a cost of quality report. Round your answers to one decimal place, if necessary. Cost of Quality Report Quality Cost Percent of Quality Cost Percent of Total Quality Cost Classification Total Sales $ Prevention Appraisal Internal failure External failure Totals % 100 % % %arrow_forwardChocolate Company is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported: Inspection Time 0.5 days Process Time 2.8 days Wait Time 16.0 days Queue Time 4.0 days Move Time 0.7 days Compute the throughput time. Answer(days)arrow_forwardOne of the operations in the Wonderland Post Office is a mechanical mail sorting operation. In this operation, letter mail is sorted at a rate of one letter per second. The letter is mechanically sorted from a three-digit code input by an operator sitting at a keyboard. The manager of the mechanical sorting operation wants to determine the number of temporary employees to hire for December. The manager estimates that there will be an additional 32,364,000 pieces of mail in December, due to the upcoming holiday season. Assume that the sorting operators are temporary employees. The union contract requires that temporary employees be hired for one month at a time. Each temporary employee is hired to work 145 hours in the month. a. How many temporary employees should the manager hire for December?fill in the blank 1 employees b. If each temporary employee earns a standard $20 per hour, what would be the labor time variance if the actual number of additional letters sorted in December was…arrow_forward
- A quality control activity analysis indicated the following four activity costs of a hotel. Line Item Description Amount Verifying credit card information $40,000 Customer service training 20,000 Discounting room rates due to poor customer service 16,000 Correcting charges to customer invoices 8,000 Total $84,000 Sales are $750,000 for the year. Prepare a cost of quality report. Round your answers to one decimal place, if necessary. Due to rounding there may be difference of 0.1 Quality CostClassification Quality Cost Percent of TotalQuality Cost Percent ofTotal Sales Prevention $fill in the blank 1 fill in the blank 2% fill in the blank 3% Appraisal fill in the blank 4 fill in the blank 5% fill in the blank 6% Internal failure fill in the blank 7 fill in the blank 8% fill in the blank 9% External failure fill in the blank 10 fill in the blank 11% fill in the blank 12% Totals $fill in the blank 13 fill in the blank 14% fill in the blank 15%…arrow_forwardManagement of Mittel Company would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time Wait time (from order to start of production) Process time Move time Queue time Required: 0.4 days 16.2 days 3.4 days 1.3 days 3.7 days 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.) 4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.) 5. If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your…arrow_forwardEnglert Hospital began using standards to evaluate its Admissions Department. The standard was broken into two types of admissions as follows: Type of Admission Standard Time to CompleteAdmission Record Unscheduled admission 30 min. Scheduled admission 15 min. The unscheduled admission took longer because name, address, and insurance information needed to be determined and verified at the time of admission. Information was collected on scheduled admissions prior to the admissions, which was less time-consuming. The Admissions Department employs four full-time people (40 productive hours per week, with no overtime) at $15 per hour. For the most recent week, the department handled 140 unscheduled and 350 scheduled admissions. a. How much was actually spent on labor for the week?$fill in the blank 1 b. What are the standard hours for the actual volume for the week (round to one decimal place)?fill in the blank 2 hours c. Calculate the time…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
- Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningAuditing: A Risk Based-Approach (MindTap Course L...AccountingISBN:9781337619455Author:Karla M Johnstone, Audrey A. Gramling, Larry E. RittenbergPublisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Auditing: A Risk Based-Approach (MindTap Course L...
Accounting
ISBN:9781337619455
Author:Karla M Johnstone, Audrey A. Gramling, Larry E. Rittenberg
Publisher:Cengage Learning