Business Driven Technology
7th Edition
ISBN: 9781259567322
Author: Paige Baltzan Instructor
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Expert Solution & Answer
Chapter 19, Problem 6MBD
Explanation of Solution
- 1. Analysing the project:
Project is categorized based on the hard work and chances to success. It is categorized as four
-
- Mission impossible project refers the need of hard work and more chances available for the success.
- Battery charging controller automation code development for fuel and solar based hybrid vehicle project suits for this category.
- It requires a lot of work and a chance to win this one is high.
- Ugly project refers the high chances of the success and more need or hard work.
- Developing a website for weather forecast information display using new technology suits for this category.
- Weather forecast information display is a good one for locals to plan their activities, it helps to them a lot but without knowing about new technology involved in the development is painful.
- Need to collect the requirements and suitability of the new technology.
- Need to learn lot about new technology to create a project and it also requires a lot of work.
- Kamikaze project refers the more interesting one to work but winning chances are low.
- Website development for Orphanage home fund collection project suits this category.
- Working on this project is the happiest one but don’t have enough financial support so need to make arrangements by own.
- Suicide project refers very less chance of the success and offer more trouble to work on that.
- Developing an application to book moon tour which does not have any defined structure...
Project is categorized based on the hard work and chances to success. It is categorized as four
- Mission impossible project refers the need of hard work and more chances available for the success.
- Battery charging controller automation code development for fuel and solar based hybrid vehicle project suits for this category.
- It requires a lot of work and a chance to win this one is high.
- Developing a website for weather forecast information display using new technology suits for this category.
- Weather forecast information display is a good one for locals to plan their activities, it helps to them a lot but without knowing about new technology involved in the development is painful.
- Need to collect the requirements and suitability of the new technology.
- Need to learn lot about new technology to create a project and it also requires a lot of work.
- Website development for Orphanage home fund collection project suits this category.
- Working on this project is the happiest one but don’t have enough financial support so need to make arrangements by own.
- Developing an application to book moon tour which does not have any defined structure...
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
17 The entical path method (CPM) calculates the theoretical early start and fish
dates, and late start and finish dates. The difference between the late and early
start of a task is called
A Free float
B. Feeding buffer
C Danger zone
D Total float
18 Which of the following is NOT a characteristic of a project?
A Ongoing nature
B Uniqueness
C Clear objectives
D Integration of interrelated tasks and resources
19. Which of the following is NOT managed by the project manager?
A. Time, cost and scope
B. The project team
C. The project sponsor
D Expectations of the stakeholders
20 When writing the roles and responsibilities for team members, you should
document the role, authority, responsibility and competency for each team
member. Where must this information be documented?
-A Human resource management plan
B RACI chart
C Resource calendar
D Resource Breakdown Structure (RBS)
21. Which of these is not a component of the scope baseline that is contained in
the project management plan?
A Work…
133.
Model suitable for project requiring shorter development times is
a.
Waterfall model
b.
RAD model
c.
Incremental model
d.
Decremented model
A project estimator is working on estimates for a project that is very similar to a previous project, in that it has many of the same features and those features have similar costs. Each feature or deliverable will represent the same percentage of the total cost as it did for the previous project. He is using the _________ method of top-down estimating.
a. ratio
b. consensus
c. apportion
d. function point
e. learning curves
Chapter 19 Solutions
Business Driven Technology
Ch. 19 - What are the three interdependent variables...Ch. 19 - Prob. 2OCCh. 19 - Prob. 3OCCh. 19 - Prob. 1CQCh. 19 - Prob. 2CQCh. 19 - How could more time spent in the analysis and...Ch. 19 - Prob. 4CQCh. 19 - Prob. 1RQCh. 19 - Prob. 2RQCh. 19 - Prob. 3RQ
Ch. 19 - Prob. 4RQCh. 19 - Prob. 5RQCh. 19 - Prob. 6RQCh. 19 - Prob. 7RQCh. 19 - Prob. 8RQCh. 19 - Prob. 9RQCh. 19 - Prob. 1MBDCh. 19 - Prob. 2MBDCh. 19 - Prob. 3MBDCh. 19 - Prob. 4MBDCh. 19 - Prob. 5MBDCh. 19 - Prob. 6MBDCh. 19 - Prob. 1CCOCh. 19 - Prob. 2CCOCh. 19 - Prob. 3CCOCh. 19 - Prob. 4CCOCh. 19 - Prob. 5CCOCh. 19 - Prob. 1CCTCh. 19 - Prob. 2CCTCh. 19 - Prob. 3CCTCh. 19 - Prob. 4CCTCh. 19 - Prob. 5CCTCh. 19 - Prob. 1AYKCh. 19 - Prob. 2AYKCh. 19 - Prob. 3AYKCh. 19 - Prob. 4AYKCh. 19 - Prob. 5AYKCh. 19 - Prob. 6AYKCh. 19 - Prob. 7AYK
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- Can you please assist with answers from question 6 to 10, Now that you have selected a project (a case), develop an analytical report of the project with specific focus on the components and questions/statements listed below: (1) State the name of the project and give a brief description of the project. (2) Outline the problem(s) that the project was initiated to solve or the opportunity it exploited. (3) Describe the technique or method used to select the project. (4) Identify and describe at least five (5) characteristics that make this endeavour a project. (5) Identify the project developmental approach used for the project. Give reasons or justification for your conclusion(s). Hint: (Agile, Waterfall/Traditional, or Hybrid approach?) (6) Using your knowledge of the project life cycle and information gathered from the examination of the project documents, describe the phases of the project and the key activities/tasks associated with each phase of the project. (7) List and…arrow_forwardHow to solved below problem based on software engineer knowledge? See the explanation of the planning case as below, when should this project start? Identify the Critical Path of planning this project. Is it possible to reduce the number of people dedicated to the project? "Software developers have identified the work breakdown structure (WBS) as shown in the table. The company applies the Modified Water Fall approach at WBS Level 1 (x.) and Level 2 (x.x), while the iteration approach at a lower level is planned to be handed over to the customer on 17 August 2023. Note that the effective time for one day is 8 (eight) hours, and working days in a week are 5 (five) days. Specifically to support this project, there are 2 Business Analysts (part timer), 2 Senior Programmers (full timer), 4 Junior Programmers (full timer), and two Testers (full timer)". Please add other assumptions if necessary. No. Work Breakdown Structure Estimated man hour 1. Requirements Definition 2…arrow_forwardAs a project manager of a Software project, you have received given data about the different type of Issues identified in the project: – Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences. Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forward
- Detailed answer please...arrow_forwardPlz send solution for this questionarrow_forwardThe CHAOS report is a study based on the CHAOS research project on IT project success rates and project management methods conducted by the "Standish Group." Explain in detail the CHAOS study from 1994 and how it may help software projects succeed. How can we ensure the success of our projects? What is a software product's configuration? Is it possible to talk about the configuration management activities?arrow_forward
- Please provide an example of a project that you would manage utilizing the Spiral Model or the V Model, together with a short description of the project's nature and a justification for your decision.arrow_forwardExplain on each detail:arrow_forwardRead the following description and select the most appropriate class diagram: A company realizes projects; each project is executed by a team of employees. For the sake of simplicity, multiplicities and attributes are not indicated.arrow_forward
- the answers should be based on a case study of project no customer escape from the Petrie electric case. for this cases, you may take refrence from modern system design and analysis.arrow_forwardChoose the correct answer for all of the following questions. Al. Mohammed has joined a project for building a new payroll system for an organization. He started his task by identifying the scope of the system and determining the feasibility of the system. From the given scenario, Mohammed is in the phase of SDLC. A. Planning B. Analysis C. Design D. Implementation A2. Which one of the following are characteristics of decent requirement? A. Ambiguous B. Incorrect C. Concise D Inconsistent The customer can give their feedback when they visualize the A. System interface B. User interface C. Architecture A3.arrow_forwardRisk identification is one of the mechanisms of risk management that can be the work of a team or based on the expertise of the individual project manager. Assume that you are the project manager of a software team working for a manufacturing company on a project to build an inventory management system. Suppose you are working on the method of identification of risk now. Describe 2 of the common risk types and possible risks based on the system that your team is developingarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781285452340Author:Kathy SchwalbePublisher:Cengage LearningInformation Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningFundamentals of Information SystemsComputer ScienceISBN:9781305082168Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
- Systems Analysis and Design (Shelly Cashman Serie...Computer ScienceISBN:9781305494602Author:Scott Tilley, Harry J. RosenblattPublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Systems Analysis and Design (Shelly Cashman Serie...
Computer Science
ISBN:9781305494602
Author:Scott Tilley, Harry J. Rosenblatt
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
9.1.2 Software Development Approaches; Author: EIToppo;https://www.youtube.com/watch?v=Z9znuSQ7Sz8;License: Standard YouTube License, CC-BY