To determine

Compute the cost of inputs for the profile 2015, if there is no change from productivity profile 2014 to 2015.

1.

Expert Solution
Check Mark

Explanation of Solution

Productivity measurement: The productivity measurement refers to the quantitative assessment of the changes in the productivity.

Profile measurement and analysis: The profile measurement and analysis refers to the computation of a set of operational partial productivity measures and their comparison to the corresponding set of base period, for the assessment of the nature of changes in productivity.

Calculate the cost of inputs for the profile 2015:

ParticularsAmount ($)
Cost of labor (3)$1,260,000
Cost of materials (4)$6,300,000
Total PQ Cost$7,560,000

Table (1)

Working Notes (1):

Compute the base period productivity ratios for profile 2014:

Compute the Labor Productivity Profile for 2014:

Labor Productivity Profile = Number of Units producedLabor hours used=$540,000108,000 hours5.00

Working Notes (2):

Compute the Material Productivity Profile for 2014:

Material Productivity Profile = Number of Units producedMaterials used=$540,0002,160,000 lbs0.25

The Labor Productivity Profile is 5.00 and Material Productivity Profile is 0.25 for 2014.

Working Notes (3):

Calculate the cost of labor:

Labor cost  = Number of units producedLabor Productivity Profile  × Wages per labor hour450,0005 (1)×$14= 90,000×$14=$1,260,000

Working Notes 4):

Calculate the cost of materials:

Material cost  = Number of units producedMaterial Productivity Profile  × Cost per pound of material450,0000.25 (2)×$3.50= 1,800,000×$3.50 = $6,300,000

2.

To determine

Compute the actual cost of inputs for the profile 2015. Indicate the net value of productivity changes and identify the profit change attributable to productivity change of each unit.

2.

Expert Solution
Check Mark

Explanation of Solution

Profit-linked productivity measurement and analysis: The profit-linked productivity measurement and analysis is the ascertainment of the amount of change in profit, from the base period to the current period, due to the various changes in the productivity.

Calculate the current cost of inputs for the profile 2015:

ParticularsAmount ($)
Cost of labor (5)$1,575,000
Cost of materials (6)$5,250,000
Total Current Cost$6,825,000

Table (2)

Working Notes (5):

Calculate the cost of labor:

Labor cost  = Number of units producedLabor Productivity Profile  × Wages per labor hour450,0005 (1)×$14= 90,000×$14=$1,260,000

Working Notes (6):

Calculate the cost of materials:

Material cost  = Number of units producedMaterial Productivity Profile  × Cost per pound of material450,0000.25 (2)×$3.50= 1,800,000×$3.50 = $6,300,000

Compute the profit linked productivity measure:

InputAB=450,000ACD=(B×C)EF=(E×C)G=(DF)
Labor590,000 $14 $1,260,000 112,500 $1,575,000 ($315,000)
Materials0.251,800,000 $3.50 $6,300,000 1,500,000 $5,250,000 $1,050,000
Total   $7,560,000 $6,825,000$735,000

Table (3)

The Net productivity change is $735,000.

The Labor productivity change is ($315,000).

The materials productivity change is $1,050,000.

3.

To determine

Compute and describe the price recovery component.

3.

Expert Solution
Check Mark

Explanation of Solution

Price-recovery component: The price-recovery component refers to the differences amongst the changes in the total profit with the changed in the productivity effects.

Compute the profit linked productivity measure:

ParticularsProfile 2014Profile 2015Changes Amount ($)
Revenues(7) $10,800,000 (8) $9,900,000 (9) ($900,000)
Costs(10) $8,640,000 $6,825,000 (11) $1,815,000
Total Profit$2,160,000$3,075,000(12) $915,000

Table (4)

Working Notes (7):

Calculate the Revenues for Profile for 2014:

Revenues = Number of units produced × Selling price= 540,000×$20=$10,800,000

Working Notes (8):

Calculate the Revenues for Profile for 2015:

Revenues = Number of units produced × Selling price= 450,000×$22=$9,900,000

Working Notes (9):

Calculate the changes in revenues:

Revenues = Revenues for Profile 2015 Revenues for Profile 2014= $9,900,000$10,800,000=($900,000)

Working Notes (10):

Calculate the cost of inputs for Profile 2014:

Cost of inputs = Labor hours usedWages per labor hour+(Materials used (lbs.)×Cost per pound of material)108,000$12+(2,160,000×$3.50)=$8,640,000

Working Notes (11):

Calculate the changes in cost of inputs:

Costs = Costs for Profile 2015Costs for Profile 2014= $6,825,000$8,640,000=$1,815,000

Working Notes (12):

Calculate the changes in total profit:

Changes in Total profit =  Profile of 2015 Profile of 2014= $3,075,000$2,160,000=$915,000

Compute the Price-recovery component:

Price-recovery component = (Total profit changeProfit-linked productivity change)= $915,000$735,000=$180,000

The Price-recovery component is $180,000.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Assume you are the department B manager for Marley's Manufacturing. Marley's operates under a cost-based transfer structure. Assume you receive the majority of your raw materials from department A, which sells only to department B (they have no outside sales). After calculating the operating income in dollars and operating income in percentage, analyze the following financial information to determine costs that may need further investigation. Marley's ManufacturingIncome StatementMonth Ending August 31, 2018
Techno Instruments uses a manufacturing costing system with one​ direct-cost category​ (direct materials) and three​ indirect-cost categories: a. ​Setup, production-order, and​ materials-handling costs that vary with the number of batches b. ​Manufacturing-operations costs that vary with​ machine-hours c. Costs of engineering changes that vary with the number of engineering changes made In response to competitive pressures at the end of 2016​, Techno Instruments used​ value-engineering techniques to reduce manufacturing costs. Actual information for 2016 and 2017 is as​ follows:     2016 2017 Setup, production-order, and materials-handling costs per batch $8,600 $7,800 Total manufacturing-operations cost per machine-hour $59 $53 Cost per engineering change $18,750 $14,000   The management of Techno Instruments wants to evaluate whether value engineering has succeeded in reducing the target manufacturing cost per unit of one…
The Western Company presents the production and cost data for the first six months of the 2015.Determine the following using High-low methoda.     estimated variable cost rate b.     fixed cost c. Also determine the cost function on the basis of data given above.

Chapter 15 Solutions

EBK CORNERSTONES OF COST MANAGEMENT

Ch. 15 - When will the average unit cost be useful for...Ch. 15 - Explain why changes in value-stream profitability...Ch. 15 - Prob. 13DQCh. 15 - Prob. 14DQCh. 15 - What is productivity measurement?Ch. 15 - Prob. 16DQCh. 15 - Prob. 17DQCh. 15 - Discuss the advantages and disadvantages of...Ch. 15 - Prob. 19DQCh. 15 - Prob. 20DQCh. 15 - What is profit-linked productivity measurement and...Ch. 15 - Prob. 22DQCh. 15 - What is the price-recovery component?Ch. 15 - Anderson Company has the following departmental...Ch. 15 - During the week of June 12, Harrison Manufacturing...Ch. 15 - Prob. 3CECh. 15 - Prob. 4CECh. 15 - Prob. 5ECh. 15 - Bienestar Inc., has the following departmental...Ch. 15 - Bienestar, Inc., implemented cellular...Ch. 15 - Henderson, Inc., has just created five order...Ch. 15 - Prob. 9ECh. 15 - Shorts Manufacturing, Inc., has implemented lean...Ch. 15 - Prob. 11ECh. 15 - Prob. 12ECh. 15 - Carsen Company produces handcrafted pottery that...Ch. 15 - Prob. 14ECh. 15 - Prob. 15ECh. 15 - Prob. 16ECh. 15 - Lean manufacturing is characterized by all but one...Ch. 15 - Lean manufacturing uses value streams to produce a...Ch. 15 - A manufacturing cell within a value stream is...Ch. 15 - Total productive efficiency is achieved when both...Ch. 15 - The following information is given for a...Ch. 15 - Sixty employees (all CPAs) of a local public...Ch. 15 - Sixty employees (all CPAs) of a local public...Ch. 15 - Prob. 24PCh. 15 - Continuous improvement is the governing principle...Ch. 15 - Prob. 26PCh. 15 - Prob. 27PCh. 15 - Prob. 28P
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Text book image
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license