a)
To determine: Thesequence of jobs based on the decision rule, i.e, First Come First Served (FCFS).
Introduction: The First Come First Served is the
a)
Answer to Problem 15P
The sequence is A-B-C-D-E.
Explanation of Solution
Given information:
The following information has been given below:
Job | Due date | Duration (days) |
A | 313 | 8 |
B | 312 | 16 |
C | 325 | 40 |
D | 314 | 5 |
E | 314 | 3 |
All the jobs have arrived on day 275.
Determine the sequence of the job by using FCFS:
Job | Due date | Duration (days) | Flow time | Start | End | Lateness |
A | 313 | 8 | 8 | 275 | 282 | |
B | 312 | 16 | 24 | 283 | 298 | |
C | 325 | 40 | 64 | 299 | 338 | 13 |
D | 314 | 5 | 69 | 339 | 343 | 29 |
E | 314 | 3 | 72 | 344 | 346 | 32 |
Total | 72 | 237 | 74 |
Working note:
The duration and due date for the jobs has been given. The flow time is the cumulative value of the duration. The jobs arrival rate is given as 275.
End day of Job A:
The jobs arrival rate is given as 275. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 282.
End day of Job B:
The start day of Job B is the next day of the end day of Job A. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 298.
End day of Job C:
The start day of Job C is the next day of the end day of Job B. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 338.
End day of Job D:
The start day of Job D is the next day of the end day of Job C. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 343.
End day of Job E:
The start day of Job E is the next day of the end day of Job D. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 346.
Lateness of Job A and Job B:
The end day of Job A and Job B is less than its respective due date. Hence, there is no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 13.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 29.
Lateness of Job E:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job E is 32.
b)
To determine: The sequence of jobs based on the decision rule, i.e, Earliest Due Date (EDD).
Introduction: The Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the earliest due date would be served first. Then, the process would be go on from the earliest due date to the latest due date.
b)
Answer to Problem 15P
The sequence is B-A-D-E-C.
Explanation of Solution
Given information:
The following information has been given below:
Job | Due date | Duration (days) |
A | 313 | 8 |
B | 312 | 16 |
C | 325 | 40 |
D | 314 | 5 |
E | 314 | 3 |
All the jobs have arrived on day 275.
Determine the sequence of the job by using EDD:
Job | Due date | Duration (days) | Flow time | Start | End | Lateness |
B | 312 | 16 | 16 | 275 | 290 | |
A | 313 | 8 | 24 | 291 | 298 | |
D | 314 | 5 | 29 | 299 | 303 | |
E | 314 | 3 | 32 | 304 | 306 | |
C | 325 | 40 | 72 | 307 | 346 | 21 |
Total | 72 | 173 | 21 |
Working note:
The duration and due date for the jobs have been given. The flow time is the cumulative value of the duration. The jobs arrival rate is given as 275. The job should be arranged based on the due date. The due date should be assembled in the ascending order.
End day of Job A:
The jobs arrival rate is given as 275. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 290.
End day of Job B:
The start day of Job B is the next day of the end day of Job A. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 298.
End day of Job C:
The start day of Job C is the next day of the end day of Job B. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 303.
End day of Job D:
The start day of Job D is the next day of the end day of Job C. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 306.
End day of Job E:
The start day of Job E is the next day of the end day of Job D. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 346.
Lateness of Job A, Job B, Job C, and Job D is given below:
The end day of Job A, Job B, Job C, and Job dare less than its respective due date. Hence, there is no lateness.
Lateness of Job E:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job E is 21.
c)
To determine: The sequence of jobs based on the decision rule, i.e, Shortest Processing Time (SPT).
Introduction: The Shortest Processing Time is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the shortest duration is served first. Then, the process would be go on from the shortest to the largest duration.
c)
Answer to Problem 15P
The sequence is E-D-A-B-C.
Explanation of Solution
Given information:
The following information has been given below:
Job | Due date | Duration (days) |
A | 313 | 8 |
B | 312 | 16 |
C | 325 | 40 |
D | 314 | 5 |
E | 314 | 3 |
All the jobs are arrived on day 275.
Determine the sequence of the job by using SPT:
Job | Due date | Duration (days) | Flow time | Start | End | Lateness |
E | 314 | 3 | 3 | 275 | 277 | |
D | 314 | 5 | 8 | 278 | 282 | |
A | 313 | 8 | 16 | 283 | 290 | |
B | 312 | 16 | 32 | 291 | 306 | |
C | 325 | 40 | 72 | 307 | 346 | 21 |
Total | 72 | 131 | 21 |
Working note:
The duration and due date for the jobs have been given. The flow time is the cumulative value of the duration. The jobs arrival rate is given as 275. The job should be arranged based on the duration (processing time). The duration should be assembled in the ascending order.
End day of Job A:
The jobs arrival rate is given as 275. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 277.
End day of Job B:
The start day of Job B is the next day of the end day of Job A. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 282.
End day of Job C:
The start day of Job C is the next day of the end day of Job B. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 290.
End day of Job D:
The start day of Job D is the next day of the end day of Job C. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 306.
End day of Job E:
The start day of Job E is the next day of the end day of Job D. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 346.
Lateness of Job A, Job B, Job C, and Job D is as follows:
The end day of Job A, Job B, Job C, and Job D are less than its respective due date. Hence, there is no lateness.
Lateness of Job E:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job E is 21.
d)
To determine: The sequence of jobs based on the decision rule, i.e, Longest Processing Time (LPT).
Introduction: The Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the largest duration is served first. Then, the process would go on from the largest to the shortest duration.
d)
Answer to Problem 15P
The sequence is C-B-A-D-E.
Explanation of Solution
Given information:
The following information has been given below:
Job | Due date | Duration (days) |
A | 313 | 8 |
B | 312 | 16 |
C | 325 | 40 |
D | 314 | 5 |
E | 314 | 3 |
All the jobs have arrived on day 275.
Determine the sequence of the job by using LPT:
Job | Due date | Duration (days) | Flow time | Start | End | Lateness |
C | 325 | 40 | 40 | 275 | 314 | |
B | 312 | 16 | 56 | 315 | 330 | 18 |
A | 313 | 8 | 64 | 331 | 338 | 25 |
D | 314 | 5 | 69 | 339 | 343 | 29 |
E | 314 | 3 | 72 | 344 | 346 | 32 |
Total | 72 | 301 | 104 |
Working note:
The duration and due date for the jobs have been given. The flow time is the cumulative value of the duration. The jobs arrival rate is given as 275. The job is arranged based on the duration (processing time). The duration should be assembled in the descending order
End day of Job A:
The jobs arrival rate is given as 275. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 314.
End day of Job B:
The start day of Job B is the next day of the end day of Job A. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 330.
End day of Job C:
The start day of Job C is the next day of the end day of Job B. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 338.
End day of Job D:
The start day of Job D is the next day of the end day of Job C. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 343.
End day of Job E:
The start day of Job E is the next day of the end day of Job D. The end day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 346.
Lateness of Job A:
The end day of Job A is less than its respective due date. Hence, there is no lateness.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 18.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 25.
Lateness of Job D:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job D is 29.
Lateness of Job E:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job E is 32.
Summary:
Decision rule | Average tardiness | Average flow time | Average number of jobs in system |
FCFS | 14.8 | 47.4 | 3.3 |
EDD | 4.2 | 34.6 | 2.4 |
SPT | 4.2 | 26.2 | 1.8 |
LPT | 20.8 | 60.2 | 4.2 |
First Come First Served (FCFS):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 14.8.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 47.4.
Average number of jobs in the system:
It is calculated by dividing the total flow time with the total duration of all the jobs. Hence, the average number of jobs in the system is 3.3.
Earliest Due Date (EDD):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 4.2.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 34.6.
Average number of jobs in the system:
It is calculated by dividing the total flow time with the total duration of all the jobs. Hence, the average number of jobs in the system is 2.4.
Shortest processing time (SPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 4.2.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 26.2.
Average number of jobs in the system:
It is calculated by dividing the total flow time with the total duration of all the jobs. Hence, the average number of jobs in the system is 1.8.
Largest processing time (LPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 20.8.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 60.2.
Average number of jobs in the system:
It is calculated by dividing the total flow time with the total duration of all the jobs. Hence, the average number of jobs in the system is 4.2.
Shortest processing time has the minimum average tardiness, average flow time, and the average number of jobs in systems. Hence, SPT is the best decision rule.
Want to see more full solutions like this?
Chapter 15 Solutions
Principles Of Operations Management
- Question Three Processing times (including setup times), and due dates for five jobs waiting to be processed at a work center are given in the following table. By Using the SPT rule determine the following: The sequence of jobs The average flow time The average job tardiness The average number of jobs at the work center Job Processing Time (hours) Hour Due A 17 15 B 10 25 C 5 20 D 7 32 E 11 38arrow_forwardQuestion 35 Consider the processing times and due dates of the following jobs: Job Processing time (days) Due date (days) 1 3 29 2 19 25 3 24 40 4 8 20 What is the average lateness if the earliest due date (EDD) is used to sequence the jobs? Group of answer choices 0.75 1.25 4.25 5.67arrow_forwardQuestion 1 Four floral arranging jobs are to be carried out across three stations: A (Arrange), B (Bag), C (crop) shown. The station sequences and job times in minutes are shown below, along with the due dates for each job. Using an "earliest due date" job dispatching priority rule, which, if any, of the jobs in will be late? Tip: create a Gantt chart schedule before answering Questions 4 & 5. a. Jobs 2 & 3 b. Jobs 3 & 4 c. Job 3 d. Job 4 e. None of the jobs will be latearrow_forward
- Question3: Two processes are applied in the same order to the jobs coming to a workstation. The durations of both processes for the six jobs coming to the workstation are as seen in the table. In order to minimize the total time to be spent on the jobs, the order in which the jobs should be done will be determined by the "johnson" rule. Accordingly, in the table below, write the order in which the business should do the work, in order, with the first things to be done on the far left, and one action to be written in each blank.1-) When the jobs are done in this order, how many minutes will it take to complete all the jobs?2-)1. How many minutes of space will there be in total in the process and the 2nd process?arrow_forwardQuestion:-M Full explain this question and text typing work only.arrow_forwardQuestion fourThree jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the sequence A-B (A has to finish the job before B can continue the job). The processing times are: Job A B1 5 42 7 73 3 5Draw a Gantt chart that shows the schedule corresponding to the sequence 1-2-3 of the jobs.arrow_forward
- Question Scenario: Early one Monday morning in Jamaica, Susan, a Restaurant Manager starts getting ready for the morning’s work operations. She is particularly happy because tonight he has a date with Marvin, the new Chef that was recently hired. The problem, as Susan sees it, is that Roberta, another Restaurant employee has been just a little too friendly with Marvin lately and that really upsets Susan. Susan has redone the work schedule, assigning Roberta the clean-up shift in the night and cutting back on her hours of work. She is hoping that Roberta would simply quit and out of her way. However, that plan doesn’t seem to be working. Despite a lighter pay cheque and frequent reprimand through the disciplinary process of creating reasons to write to her about her conduct and performance. Roberta has decided to quit her studies due to her inability to fund her tuition. A few days later, Susan noticed Marvin and Roberta having lunch together in the staff dining room. Susan got furious…arrow_forwardQuestion 32 The processing times of four jobs are given as follows: Job Processing time (minutes) A 10 B 30 C 16 D 24 Assume the jobs arrived in alphabetical order of the job name and no other job arrives in the next 70 minutes. What is the average flow time in minutes if the jobs are processed in shortest processing time (SOP) order? Group of answer choices 166 41.5 38 20.5arrow_forwardQuestion p .Full explain this question and text typing work only We should answer our question within 2 hours takes more time then we will reduce Rating Dont ignore this linearrow_forward
- Question 2 b Full explain this question and text typing work onlyarrow_forwardQuestion 1) Scheduling If the following jobs are sequenced according to the FCFS rule Job Processing Time (days) Due Date A 8 12 B 6 15 C 11 17 D 5 10 E 3 8 What is the mean tardiness (in days) for all jobs? What is the mean completion time in days for all jobs? What is the maximum job tardiness (in days)arrow_forwardQuestion 33 The processing times of five jobs are given as follows: Job Processing time (minutes) A 20 B 60 C 30 D 75 E 15 Assume the jobs arrived in alphabetical order of the job name and no other job arrives in the next 200 minutes. What is the average inventory if the jobs are processed in shortest processing time (SPT) order? Group of answer choices 3.00 2.92 1.97 2.20arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.