Question
Chapter 15, Problem 1.1VC
Summary Introduction
Case summary:
The case deals about the conversion of concert to a basketball. The details about the center were given. The available crew size is given as 16. The following information is given in the case:
To draw: The Gantt chart to help Person C to organize his crew to perform the concert-to-basketball conversion.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Question Scenario:
Early one Monday morning in Jamaica, Susan, a Restaurant Manager starts getting ready for the morning’s work operations. She is particularly happy because tonight he has a date with Marvin, the new Chef that was recently hired. The problem, as Susan sees it, is that Roberta, another Restaurant employee has been just a little too friendly with Marvin lately and that really upsets Susan. Susan has redone the work schedule, assigning Roberta the clean-up shift in the night and cutting back on her hours of work. She is hoping that Roberta would simply quit and out of her way. However, that plan doesn’t seem to be working. Despite a lighter pay cheque and frequent reprimand through the disciplinary process of creating reasons to write to her about her conduct and performance. Roberta has decided to quit her studies due to her inability to fund her tuition. A few days later, Susan noticed Marvin and Roberta having lunch together in the staff dining room. Susan got furious…
А.
Instruction:
1. Construct both AOA diagram for the following data.
a)
b)
Identify the paths and the time for each path
Identify critical pathe and the due date (T) of the critical path
c)
Compute for expected time for each activity and the
expected path duration
Identify the variance for each activity and of each path
b)
c)
d)
Identify the critical path
Compute for z value, the Pz (Normal standard distribution) and plot in a graph
ACTIVITY
IMMEDIATE
TIME
PREDECESSORS
ESTIMATES
to
tm
(days)
A.
2
1
4
3
4
А, В
1
3
8
A,C
B,C
D,E
D,E
F,G
F,G
H,I
Н
J,K
KL
12
3
10
E
15
4
7
G
7
3
6
8
1
3
4
1
9.
J
12
4
6
10
K
6
7
L
1
4
M
3
2
4
7
Question: Create me an AON diagram for Production of High-Quality Organic Rice. You may assume the activities and days.
Chapter 15 Solutions
Principles Of Operations Management
Ch. 15 - Prob. 1EDCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Prob. 10DQCh. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 11PCh. 15 - Prob. 12PCh. 15 - Prob. 13PCh. 15 - Prob. 14PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Prob. 24PCh. 15 - Prob. 25PCh. 15 - Prob. 26PCh. 15 - Prob. 27PCh. 15 - Prob. 28PCh. 15 - Daniels Barber Shop at Newark Airport is open 7...Ch. 15 - Given the following demand for waiters and...Ch. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Why is seniority important in scheduling servers?Ch. 15 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 10:15 ← Assignment for chapter One.pdf Operation Research Assignment for Chapter One Instructor: Wehliye Operation Research K 7 ку 5. Operation research analysis does not: a) Predict future operation b) Collect the relative data 4G 83% 个 Part One: Multiple Choice 1. A feasible solution to an lp problem a) Must satisfy all of the problems constraints simultaneously b) Need not satisfy all of the constraints, only some of them c) Must be a corner point of the feasible region d) Must optimize the value of the objective function 2. Which of the following statements is true with respect to the optimal solution of an LP problem? ||| L a) Every LP problem has an optimal solution b) Optimal solution of an LP problem always occur at an extreme point c) At optimal solution, all resources are completely used d) If an optimal solution exists, there will always be at least one at a corner 3. While plotting constraints on a graph paper, terminal points on both the axes are connected by straight line…arrow_forwardQUESTION 6 The framing department has six jobs waiting to be processed as shown in Table 3 below. It is now time zero and all jobs are ready to begin. Each has only one operation remaining. Table 3 Jobs (In order of arrival) Processing Time Due Date A 5 12 B 7 18 C 8. 14 D 3 10 E 9 22 F 12 17 Using minimum flow time as the evaluation criterion, recommend the best rule to sequence the jobs from the list below: i. FCFS ii. SOT iii. EDD iv. STRarrow_forwardQuestion 16 An activity on a PERT network has an optimistic time of 2 hours, a most likely time of 4 hours, and a pessimistic time of 14 hours. Find its STANDARD DEVIATION. O 2.5 hours O 1 hour O 0.5 hour 2 hours O 1.5 hoursarrow_forward
- Question 3 of 19 The following table contains information concerning four jobs that are awaiting processing at a work center. Job Time Due date (days) (days) 14 10 7 6 Job A B C D Determine the average flow time using the EDD rule. Select the correct response: 20 20.5 19.75 21 20 16 15 17 ProviQUSarrow_forwardtime (hours) pH 7.00 7.30 6.99 7.00 Assignment 1 2 7.12 7.25 7.12 7.20 3 720 7.16 720 7.16 4 6.98 7.00 6.94 7.00 5 6.99 6.99 6.99 6.98 6 7.00 6.93 7.02 6.93 7 6.92 7.00 6.92 7.02 Construct the X-Bar charts and R- charts 6.88 6.82 6.94 6.99 7.10 7.00 7.00 7.00 for reporting your results 10 721 7.02 721 7.04 11 7.01 6.86 7.01 6.90 12 6.86 6.98 6.90 6.98 13 6.90 7.00 6.87 7.00 14 7.01 7.04 7.01 7.05 15 7.00 6.95 7.00 6.99 16 7.09 7.20 7.03 7.20 17 6.89 7.14 6.87 7.15 18 6.98 6.80 6.98 6.89 19 7.00 6.90 7.00 6.90 20 7.20 7.00 723 7.00 21 7.04 7.03 7.08 7.00 22 6.90 6.92 6.98 6.92 23 7.00 7.00 7.00 7.00 24 7.00 6.97 7.01 6.98arrow_forwardQuestion 2: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 28 units. Assume the shop works a 56-minute hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: (SEE PHOTO) a. What is Cycle time? (Round your answer to 1 decimal place.) In order of most following tasks. Tiebreaker: greatest positional weight. (Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and h in lowercase with no other text or symbols. Round your numerical answers to 1 decimal place.) What is Efficiency? (Use your rounded cycle time in the denominator of your efficiency calculation. Round your answer to 1 decimal place.) b. In order of greatest positional weight. Tiebreaker: most following tasks. (Use your rounded cycle time. Enter your tasks in the order they were assigned at each station as a letter between a and…arrow_forward
- Question 1 Activity Activity Description Immediate Predecessors Estimated Duration A Excavate — 2 weeks B Lay the foundation A 4 weeks C Put up the rough wall B 10 weeks D Put up the roof C 6 weeks E Install the exterior plumbing C 4 weeks F Install the interior plumbing E 5 weeks G Put up the exterior siding D 7 weeks H Do the exterior painting E, G 9 weeks I Do the electrical work C 7 weeks J Put up the wallboard F, I 8 weeks K Install the flooring J 4 weeks L Do the interior painting J 5 weeks M Install the exterior fixtures H 2 weeks N Install the interior fixtures K, L 6 weeks Using the PERT method, draw the network map. Calculate the earliest start, earliest finish, latest start, latest finish, and slack times for each activity. Display results in a table format. Calculate the critical path.…arrow_forwardQUESTION 1 Background The IT group at Fang Technology received approval to add a new entry-level systems analyst position. You will help set up the hiring timetable and create a task list to handle the interviewing logistics. After checking with several people in the IT department, you identified seven specific tasks, estimated their duration, and determined the order in which they should be performed. Now you need to create a work breakdown structure and a PERT chart that shows the task pattern and a critical path. Practice Tasks and Answers The IT group at Fang Technology has received approval to add a new entry-level systems analyst position. You will help set up the hiring timetable and tasks. After speaking to several people in the department, you identified seven tasks and the order in which they should be performed. Using your notes, you write up the following statement: First, review the applications (2 days). Then start three tasks: notify the IT team (2 days), reserve a…arrow_forwardQuestion 2: start ever Activity A Activity B Activity A Activity B Activity C Activity D Activity E Activity F Activity G Activity H Activity Activity C 20% 40% 40% Calculate CTE of the following process: Activity D Activity E 2 days 1 day 1 day 2 days 2 days 1 day 1 day 4 days Cycle Time Activity G Activity H 2 hours 2 hours 1 hour 2 hours 2 hours 3 hours 2 hours 4 hours 20% Process Time end event Larrow_forward
- Question 22: Briefly describe a project you worked on that required data gathering, importing, cleaning (i.e. merging other data, creating new variables, etc.), analysis, and output. If you have not had any experience with this please describe a project that might require these steps and how you would go about doing it.arrow_forwardMangement question Alpha Enterprises is a company manufacturing water geysers. The company has a functional structure with four main functions-Production, Marketing, Finance and Human Resource. As the demand for the product grew, the company decided to hire more employees. Identify the concept which will help the Human Resource Manager in deciding the actual number of persons required in each department.arrow_forwardQuestion 13 Jassim is a 'Team Leader' with a three month project to develop a new mobile phone app. Maryam is a member of Jassim's team and hence reports to Jassim. Maryam also reports to Faisal, the Product Development Manager. This is an example of a structure. A) functional B) product team customer D divisional E) matrix O 113 minutes remaining hparrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.