Textbook Question
Chapter 14, Problem 26P
M. de Koster, of Rene Enterprises, has the master production plan shown below:
Lead time = 1 period; setup cost = $200; holding cost = $10 per week; stockout cost = $10 per week. Your job is to develop an ordering plan and costs for:
a) Lot-for-lot.
b) EOQ.
c) POQ.
d) Which plan has the lowest cost?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using the gross requirements schedule below*, prepare an alternative ordering system that orders every 3 weeks for 3 weeks ahead (a periodic order quantity). What is the cost of this
ordering system?
Period
1 2 3 4 5 6 7
Gross requirements 25 20 40 0 10 50 30
The cost of this ordering system is $
Prepare a net requirements plan (enter your responses as whole numbers).
*Holding cost = $1/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 25 units.
Period
Gross requirements
On-hand at beginning of period
On-hand at end of period
Net requirements
Order receipt
Order release
(enter your response as a whole number).
25
1
25
2
20
3
40
4
5
0 10
8
0
6
50
9 10
30 65
7
30
8 9 10
0
30 65
The annual demand of Bulldogs Inc. sole product totaled 450,000 units. Due to uncertainty in supply of items, the maximum possible lead time for the orders is 2 weeks and 1 day. A safety stock of 6,250 units is determined. What is the normal lead time? (Use 360 days)
A. 10 days
B. 9 days
C. 1 week and 5 days
D. 1 week
Demand for chicken soup at a supermarket is always 25 cases a day and the lead time is always 4 days. Theshelves were just restocked with chicken soup, leaving an on-hand inventory of only 10 cases. No backorderscurrently exist, but there is one open order in the pipeline for 200 cases. What is the inventory position? Shoulda new order be placed?
Chapter 14 Solutions
Principles Of Operations Management
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Jean-Ma rie Bourjolly's restau rant has the followinginventory items that it orders on a weekly basis: a) Which is the most expensive item, using annual dollar volume?b) Which are C items?c) What is the annual dollar volume for all 20 items?arrow_forwardDennis Sport World, a chain of sporting goods stores, sells 360,000 tennis balls per year. The tennis balls cost Dennis Sport World RM15 per dozen. Annual inventory carrying costs are 20 percent of inventory price. The cost of placing and receiving an order are RM72. Assume the inventory replenishment occurs virtually instantaneously. Based on recent experience, Dennis Sport World uses 7 days delivery time for planning purposes. (Assume 360 days in a year) TASKS a) Calculate the Economic Order Quantity. b) Calculate the number of orders to be placed. c) Calculate the total annual inventory costs. d) Determine the reorder point.arrow_forwarda. If demand for the new videotape recorder is expected to be constant with a rate of 20 units per month, what is the recommended order quantity for the videotape recorder? b. What are the estimated annual inventory holding and ordering costs associated with this product? c. How many orders will be placed per year? d. With 250 working days per year, what is the cycle time for this product?arrow_forward
- Use ABC analysis to determine the items deserving mostattention and tightest inventory control.arrow_forwardFill in the blanks in the following Inventory Record using POQ inventory policy assuming: Lead Time 50, and scheduled receipts of 40 in week 1 A = 2, P=3, on hand inventory LT= Quantity= Lot Size = On hand = 2 P=3 50 = Gross requirements Scheduled receipts Projected on hand Planned-order receipts Planned-order releases B D 1 90 40 2 D 3 20 A 4 40 5 6 60 C 7 B co 8 60arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 10. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. Item Lead Time On-Hand Inventory Components Stepper 2 10 A(2), B(2), C(1) A 1 10 D(1), F(2) B 2 20 E(1), F(3) C 3 10 D(2), E(3) D 2 15 E 2 5 F 2 20 c) Develop a net material requirements plan for F (enter your responses as whole numbers). Week Lead Time Item 3 4 5 6 7 8 9 10 (weeks) F Gross req enter your response here enter your response here 2 On hand enter your response here enter your response here Net req enter your response here enter your response here Order…arrow_forward
- Using the gross requirements schedule below*, prepare an alternative ordering system that always orders 100 units the week prior to a shortage (a fixed order quantity of 100). What is the cost of this ordering system? D Period 1 2 3 Gross requirements 35 30 40 4 5 6 7 8 9 10 0 10 40 30 0 30 55 *Holding cost = $1/unit/week; setup cost = $100; lead time = 1 week; beginning inventory = 35 units. Prepare a net requirements plan (enter your responses as whole numbers). The holding cost of this ordering system is $ The setup cost of this ordering system is $ The total cost of this ordering system is $ Period Gross requirements On-hand at beginning of period 35 On-hand at end of period Net requirements Order receipt Order release (enter your response as a whole number). (enter your response as a whole number). (enter your response as a whole number). 1 35 2 3 30 40 4 0 7 8 9 10 0 30 55 5 6 10 40 30arrow_forward2.7 Which of the following help explain how the Reorder Point (ROP) works in conjunction with the Economic Order Quantity (Q), the number of orders (N) and the time between orders (T)? a) The Economic Order Quantity (Q) and the Annual Demand (D) are used to determine the number of Order (N) b) The number of orders (N) and the number of days that a firm works (W) are used to determine the time span between orders (T) c) Orders are placed every T days unless the inventory on hand fall to or below the Reorder Point d) Only a and b e) f) Only b and c All of a, b and c 2.8 The objective of Inventory Management is to balance inventory investment (cost) and customer service. a) TRUE b) False 2.9 The Economic Order Quantity (EOQ), the number of orders, the Reorder Point (ROP), the time between orders are important analytics in Inventory Management. a) TRUE b) FALSE 2.10 The number of working days for a firm is an important input in calculating the components of the Economic Order Quantity…arrow_forwardDescribe methods other than the EOQ and EPQ for evaluating order amounts.arrow_forward
- Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. Item Lead Time On-Hand Inventory Components Stepper 2 20 A(2), B(2), C(2) A 1 10 D(1), F(2) B 2 20 E(2), F(3) C 2 10 D(2), E(1) D 1 15 E 2 5 F 2 20 c) Develop a net material requirements plan for F (enter your responses as whole numbers). Week Lead Time Item 1 2 3 4 5 6 7 8 (weeks) F Gross req 2 On hand Net req enter your response here enter your response here Order receipt enter your response here enter your…arrow_forwarda) Cycle Inventory b) Total cost c) Reorder level if lead time is constant at 4 daysarrow_forwardYou work as a planner in the supply chain department for AFIA co. Given the monthly gross requirements for one of the items (Carton). Your job is to develop an ordering plan and costs for: a) Lot-for-lot. b) EOQ. c) Which plan should we select ? Calculate the total cost of each plan. Please use the following information : Holding Cost per month = $ 0.75 Set Up Cost = $ 150 Lead time = 0 Master Production Schedule : Month 1 2 4 5 6. Gross requireme 100 150 200 150 100 150 250 nts Attach your solutions (Answer the total cost of EOQ plan in field)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY