Chapter 12, Problem 1E

LO 4-1    Exercise 4-1A Direct versus indirect costs

Ludmilla Construction Company is composed of two divisions: (1) Home Construction and (2) Commercial Construction. The Home Construction Division is in the process of building 12 houses and the Commercial Construction Division is working on three projects. Cost items of the company follow:

Wages of workers assigned to a specific construction project

Supplies used by the Commercial Construction Division

Labor on a particular house

Salary of the supervisor of commercial construction projects

Supplies, such as glue and nails, used by the Home Construction Division

Cost of building permits

Materials used in commercial construction projects

Depreciation on home building equipment (small tools such as hammers or saws)

Company president’s salary

Depreciation on crane used in commercial construction

Depreciation on home office building

Salary of corporate office manager

Required

  1. a. Identify each cost as being a direct or indirect cost assuming the cost objects are the individual products (houses or projects).
  2. b. Identify each cost as being a direct or indirect cost, assuming the cost objects are the two divisions.
  3. c. Identify each cost as being a direct or indirect cost assuming the cost object is Ludmilla Construction Company as a whole.
Blurred answer
Students have asked these similar questions
Problem 2 ASD Company consists of two producing departments and two servicing Departments. The following are the cost incurred in each department. The Company use the direct labor hours as the basis for the overhead rate in the assembly department while units produced for the Packaging Department Producing Departments Assembly Department Packaging Department Servicing Department Maintenance Department Quality Inspection Department Cost 1,200,000 800,000 250,000 400,000 Units Produced 25,000 16,000 Direct Labor Hours 90,000 80,000 15,000 15,000 Floor Area 4,500 6,000 1,500 3,000 Additional information The Maintenance Department is allocated based from the space used by the departments while the Quality Inspection Department is based on units produced Required Compute for the predetermined overhead rate of cutting and assembling department using the following: (show your solutions)
Question 1 Fair Manufacturing Company is a factory in Hong Kong. It has two support departments- Maintenance and Accounting and two operating departments – Production 1 and Production 2 Departments. You are given the following information related to the overhead costs of the four departments: Maintenance Accounting Production 1 Production 2 Budgeted overhead costs before any interdepartment cost allocations Support work furnished: For Maintenance department $300,000 $120,000 $300,000 $500,000 Machine hours 50 5,750 500 For Accounting department Number of employees 5 20 10 Support costs in Maintenance department are allocated based on the machine hours used and that for the Accounting department are allocated by number of employees. Required What are the total costs for each of the operating departments (Production 1 and Production 2) after the support department costs of Maintenance and Accounting have been allocated using а. the direct method, b. the step-down method (allocate…
al 15 Chapter Four Activity Cost Pool Machining Machine setups Production design. General factory Activity Measure Machining Required information Greenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity- based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Number of setups Number of products. Direct labor-hours Activity Measure. Machine-hours Number of setups Number of products Direct labor-hours. Activity rate Saved per setup Estimated Overhead Cost $ 249,600 $ 162,400 $ 92,000 $ 309,600 4. What is the activity rate for the Machine Setups activity cost pool? Product Y Product Z 8,800 3,200 40 240 1 1 8,800 3,200 S 15 Expected Activity 12,000 MHS 280 setups of 15 2 products 12,000 DLHS…

Chapter 12 Solutions

Survey Of Accounting

Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Fixed Asset Replacement Decision 1235; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=LJRzn9K8Nwk;License: Standard Youtube License