Chapter 12, Problem 12.42BE
1.
To determine
The payback period in years of the project S.
2.
To determine
Net present value of project S.
3.
To determine
Whether the company undertake the project under its own existing rule of not accepting the project with payabck period lesser than 5 years.
To conclude: That, what arguments could the energy manager make to try to obtain approval for project S.
4.
To determine
To conclude: If I approving capital investment proposals.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Happy Trails Senior Living Community is considering investing in solar panels to save on utility costs. The initial cost of the panels, including installation, is $250,000. The expected reduction in utility costs are noted below. Utility costs savings for the next five years are:
Year 1: $65,000
Year 2: $68,250
Year 3: $71,663
Year 4: $75,246
Year 5: $79,008
The current interest rate used to evaluate investment decisions is 6%. The inflation rate is expected to remain constant at 3% for the entire period.
Instructions
(a) Compute the present value of the expected cash flows (savings).
(b) Should Happy Trails move forward with the investment?
Liwayway High School is planning to install solar panels to provide some of the electricity for its groundwater desalting facilty. The project would be done in two phases. The first phase will cost P400 million in year 1 and P500 million in year 2. This investment will result in energy savings (phase 2) of P54,000,000 in year 3, P54,600,000 in year 4, and amounts increasing by P600,000 each year through year 10. Let i = 10% per year.(a) What is the future worth of the savings?(b) Is the cost of the solar project justified by the savings? (Hint: Calculate the difference between savings and cost).
Installing low thermal emissivity windows (low-e windows) on buildings can contribute to energy conservation. Installing low-e
windows on a school building is estimated to cost $10,000. The windows are expected to last 6 years and have no salvage value at that
time. The energy savings from the windows are expected to be $2,525 in the 1st year. After the 1st year, the savings are expected to
increase by $125 each year due to escalating fossil fuel costs. MARR is 15% per year and annual worth is the preferred measure of
economic worth. Which Excel® entry should you use to determine the annual worth of installing the low-e windows?
-NPV (15 %,6,10000)+NPV( 15%,6,- NPV ( 15%,2525,25252525,2525,25252525))
O-PMT( 15%,6,10000) + PMT( 15 %,6,- NPV ( 15%, 0,125,2 125,3 125,4 125,5*125))+2525
O-PMT(15,6,10000)+PMT(15,6,PMT(15,0,125,2 125,3 125,4*125,5*125))+2525
-PMT(15%.6.10000)+PMT (15% , 6 , NPV ( 15%, 2525,2 2525,2525,2525,2525))
Chapter 12 Solutions
Managerial Accounting (5th Edition)
Ch. 12 - Prob. 1QCCh. 12 - (Learning Objective 2) After identifying potential...Ch. 12 - Prob. 3QCCh. 12 - Prob. 4QCCh. 12 - Prob. 5QCCh. 12 - Prob. 6QCCh. 12 - Prob. 7QCCh. 12 - Prob. 8QCCh. 12 - Prob. 9QCCh. 12 - (Learning Objective 5) Which of the following...
Ch. 12 - Order the capital budgeting process (Learning...Ch. 12 - Prob. 12.2SECh. 12 - Prob. 12.3SECh. 12 - Prob. 12.4SECh. 12 - Prob. 12.5SECh. 12 - Prob. 12.6SECh. 12 - Prob. 12.7SECh. 12 - Prob. 12.8SECh. 12 - Prob. 12.9SECh. 12 - Prob. 12.10SECh. 12 - Prob. 12.11SECh. 12 - Prob. 12.12SECh. 12 - Prob. 12.13SECh. 12 - Prob. 12.14SECh. 12 - Prob. 12.15SECh. 12 - Identify ethical standards violated (Learning...Ch. 12 - Prob. 12.17AECh. 12 - Compute payback period and analyze changes...Ch. 12 - Prob. 12.19AECh. 12 - Prob. 12.20AECh. 12 - Prob. 12.21AECh. 12 - Prob. 12.22AECh. 12 - Calculate the payback and NPV for a sustainable...Ch. 12 - Prob. 12.24AECh. 12 - Prob. 12.25AECh. 12 - Prob. 12.26AECh. 12 - Prob. 12.27AECh. 12 - Prob. 12.28AECh. 12 - Prob. 12.29AECh. 12 - Prob. 12.30AECh. 12 - Prob. 12.31AECh. 12 - Prob. 12.32AECh. 12 - Prob. 12.33AECh. 12 - Prob. 12.34AECh. 12 - Prob. 12.35AECh. 12 - Prob. 12.36BECh. 12 - Prob. 12.37BECh. 12 - Prob. 12.38BECh. 12 - Prob. 12.39BECh. 12 - Prob. 12.40BECh. 12 - Prob. 12.41BECh. 12 - Prob. 12.42BECh. 12 - Prob. 12.43BECh. 12 - Prob. 12.44BECh. 12 - Prob. 12.45BECh. 12 - Prob. 12.46BECh. 12 - Prob. 12.47BECh. 12 - Prob. 12.48BECh. 12 - Prob. 12.49BECh. 12 - Prob. 12.50BECh. 12 - Prob. 12.51BECh. 12 - Prob. 12.52BECh. 12 - Prob. 12.53BECh. 12 - Prob. 12.54BECh. 12 - Prob. 12.55APCh. 12 - Prob. 12.56APCh. 12 - Prob. 12.57APCh. 12 - Prob. 12.58APCh. 12 - Prob. 12.59BPCh. 12 - Prob. 12.60BPCh. 12 - Evaluate an investment using all four methods...Ch. 12 - Prob. 12.62BPCh. 12 - Prob. 12.63SCCh. 12 - Discussion Questions 1. Describe the capital...Ch. 12 - Prob. 12.65ACTCh. 12 - Prob. 12.66ACTCh. 12 - Prob. 12.67ACT
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- An electric utility is considering a photovoltaic (PV) solar panel system to provide power to water conditioning pumps within the power plant. The project will be done in two phases. Phase 1 has an initial cost of $3 million. Phase 2 will cost $2.2 million at the beginning of year 3. The system will be put into service at the beginning of year 4. The annual savings using the PV panels is estimated to be $900,000, increasing by $120,000 per year through year 10. The utility’s Minimum Attractive Rate of Return (MARR) is 10%. 1. Determine if the cost of the PV system is justified. (Hint: Consider comparing the present worth of the costs and present worth of the savings.) 2. What is the actual rate of return for this project?arrow_forwardThe Culinary Institute is considering a classroom remodeling project. The cost of the remodel would be $350,000 and will be depreciated over six years using the straight- line method. The model will acoomoodate five extra student per year. Additional information related to the project follows:Cost of the remodel project: $350,000 Useful life of project in years: 6 Annual number of extra students: 5 Annual tuition per student: $22,000 Before- tax incremental cost of a student: $2,000 Company's income tax rate: 20% Required rate of return: 12% Assuming a six- year time horizon, what is the internal rate of return of the remodeling project? Calculate using both present value factors and separately using Excel's IRR function. Please include formulas to show how you arrive at each solution! A) Annual cash flow: Revenue ? Less costs:Other than depreciation ? Depreciation ? Income before taxes ? Income tax expense ?…arrow_forward. Austin Utilities is planning to install solar panels to provide some of the electricity for its groundwater desalting plant. The project would be done in two phases. The first phase will cost $4 million in year 1 and $5 million in year 2. This investment will result in energy savings (phase 2) of $540,000 in year 3, $546,000 in year 4, and amounts increasing by $6000 each year through year 10. Let i= 10% per year. (b) Is the cost of the solar project justified by the savings?arrow_forward
- "A university wants to utilize a solar energy system to reduce its energy bill. The investment cost 500000$ and the system will have a market value of 10000$ at the end of the estimated lifetime which 25 years. The saving amount in the energy bill will be 105000$ per year. If the university's MARR is 15% per year, what is the Present worth of this investment?" 179035 267432 249753 232073 214394 196714 161355 143676 None of themarrow_forwardA university spent $1.7 million to install solar panels atop a parking garage. These panels will have a capacity of 600 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 10%, that electricity can be purchased at $0.30 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the solar panels for 1 hour per year first. Approximately how many hours per year will the solar panels need to operate to enable this project to break even? 776.54 1,109.34 1,774.94 1,331.21 If the solar panels can operate only for 998 hours a year at maximum, the project Continue to assume that the solar panels can operate only for 998 hours a year at maximum. In order for the project to be worthwhile (i.e., at least break even), the university would need a grant of at least break even.arrow_forwardA university spent $1.3 million to install solar panels atop a parking garage. These panels will have a capacity of 400 kilowatts (kW) and have a life expectancy of 20 years. Suppose that the discount rate is 20%, that electricity can be purchased at $0.30 per kilowatt-hour (kWh), and that the marginal cost of electricity production using the solar panels is zero. Hint: It may be easier to think of the present value of operating the solar panels for 1 hour per year first. Approximately how many hours per year will the solar panels need to operate to enable this project to break even? a. 2,224.69 b. 1,112.35 c. 2,892.10 d. 2,447.16 If the solar panels can operate only for 2,002 hours a year at maximum, the project __________ break even. Continue to assume that the solar panels can operate only for 2,002 hours a year at maximum. In order for the project to be worthwhile (i.e., at least break even), the university would need a grant of…arrow_forward
- Your company is environmentally conscious and is looking at two heating options for a new research building. What you know about each option is below, and your company will use an annual interest rate of 8% for this decision: Gas Heating Option: The initial equipment and installment of the natural gas system would cost $225,000 right now. The maintenance costs of the equipment are expected to be $2,000 per year, starting next year, for each of the next 20 years. The energy cost is expected to be $5,000,starting next year, and is expected to rise by 5% per year for each of the next 20 years due to the price of natural gas increasing. Geothermal Heating Option: Because of green energy incentives provided by the government, the geothermal equipment and installation is expected to cost only $200,000 right now, which is cheaper than the gas lines. There would be no energy cost with geothermal, but because this is a relatively newer technology, the maintenance costs are expected to be…arrow_forwardA university's college of engineering would like to determine how much it will cost to keep its computing equipment current. In today's dollars, the college estimates that it will cost $100,000 to replace old computing equipment. Due to decreasing prices on computers, it estimates that this cost will decrease each of the following years by 2%. What would the present worth of computing updates for years 1-5 be, assuming a required 10% real return on its investments? Click here to access the TVM Factor Table calculator. $ Carry all interim calculations to 5 decimal places and then round your final answer to a whole number. The tolerance is ± $10. eTextbook and Media Hint Save for Later Attempts: 0 of 1 used Submit Answerarrow_forwardA major equipment purchase is being considered by Metro Atlanta. The initial cost is determined to be $1,000,000. It is estimated that this new equipment will save $100,000 the first year and increase gradually by $50,000 every year for the next 6 years. MARR=10% a. Using Benefit- Cost analysis, what is the Benefit/Cost ratio for this equipment purchase? b. Based on the Benefit/Cost analysis should Metro Atlanta purchase the equipment?arrow_forward
- Gina Ripley, president of Dearing Company, is considering the purchase of a computer-aided manufacturing system. The annual net cash benefits and savings associated with the system are described as follows: The system will cost 9,000,000 and last 10 years. The companys cost of capital is 12 percent. Required: 1. Calculate the payback period for the system. Assume that the company has a policy of only accepting projects with a payback of five years or less. Would the system be acquired? 2. Calculate the NPV and IRR for the project. Should the system be purchasedeven if it does not meet the payback criterion? 3. The project manager reviewed the projected cash flows and pointed out that two items had been missed. First, the system would have a salvage value, net of any tax effects, of 1,000,000 at the end of 10 years. Second, the increased quality and delivery performance would allow the company to increase its market share by 20 percent. This would produce an additional annual net benefit of 300,000. Recalculate the payback period, NPV, and IRR given this new information. (For the IRR computation, initially ignore salvage value.) Does the decision change? Suppose that the salvage value is only half what is projected. Does this make a difference in the outcome? Does salvage value have any real bearing on the companys decision?arrow_forwardFriedman Company is considering installing a new IT system. The cost of the new system is estimated to be 2,250,000, but it would produce after-tax savings of 450,000 per year in labor costs. The estimated life of the new system is 10 years, with no salvage value expected. Intrigued by the possibility of saving 450,000 per year and having a more reliable information system, the president of Friedman has asked for an analysis of the projects economic viability. All capital projects are required to earn at least the firms cost of capital, which is 12 percent. Required: 1. Calculate the projects internal rate of return. Should the company acquire the new IT system? 2. Suppose that savings are less than claimed. Calculate the minimum annual cash savings that must be realized for the project to earn a rate equal to the firms cost of capital. Comment on the safety margin that exists, if any. 3. Suppose that the life of the IT system is overestimated by two years. Repeat Requirements 1 and 2 under this assumption. Comment on the usefulness of this information.arrow_forwardThe city of Oak Ridge is evaluating three mutually exclusive landscaping plans for refurbishing a public greenway. Benefits to the community have been estimated by a landscaping committee, and the costs of planting trees and shrubbery, as well as maintaining the greenway, are summarized below. The city’s cost of capital is 8% per year, and the planning horizon is 10 years. Which landscaping plan will you recommend based on B/C ratio analysis? Landscaping plan A B C Initial planning cost $75,000 $50,000 $65,000 Annual maintenance expense 4,000 5,000 4,700 Annual community benefits 20,000 18,000 20,000arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Relevant Costing Explained; Author: Kaplan UK;https://www.youtube.com/watch?v=hnsh3hlJAkI;License: Standard Youtube License