1.)
You have determined the following for a given project:
Expected completion time of the project = 40 weeks
Standard deviation of project completion time = 8
What is the probability of completing the project in more than 44 weeks?
answer as a decimal and take it to four places.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 1 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Create a weighted scoring model to determine grades for a course. Final grades are based on three exams worth 20 percent, 15 percent, and 25 percent, respectively; homework is worth 15 percent; and a group project is worth 25 percent. Enter scores for three students. Assume that Student 1 earns 90 percent (or 90) on every item. Assume that Student 2 earns 70 percent on each of the exams, 80 percent on the homework, and 95 percent on the group project. Assume that Student 3 earns 90 percent on Exam 1, 80 percent on Exam 2, 75 percent on Exam 3, 80 percent on the homework, and 70 percent on the group project.arrow_forwardThis is the same payoff table used in questions 2 and 3. Below is a payoff table that lists four mortgage options: Decision 1-year ARM 3-year ARM 5-year Arm 30-year fixed Rates Rise $66,645 $62,857 $55,895 $52,276 Outcomes Rates Stable $43,650 $47,698 $50,894 $52,276 4) Which of the following decisions has the best average payoff? CA. 3-year ARM B. 1-year ARM CC. 5-year ARM CD. 30-year Fixed Rates Fall $38,560 $42,726 $48,134 $52,276arrow_forward(3) A project was planned using PERT. Its expected completion time was determined to be 85 days. The variance of the critical path is 49. What is the probability the project will be completed within 75 days (5 decimal places)? Let X = the project completion time. P(X Please show how you use the Normal Curve Table to obtain your answer in the space below. (4) Perform a project management analysis for the data given below to determine ES, EF, LS, LF, and slack for each activity, the total project completion time, and the critical path. Predecessors Activity A B с D D Time (weeks) 13 12 10 9 E F G H - A A Activity E C, E D, F (a) Draw a network with 1, ES, EF, LS, and LF (follow the same format as Figure 11.5 on p.394). F G H (b) Complete the following table (similar in format to Table 11.3 on p.396). Activity Time (weeks) ES EF LS A B с (c) Identify the critical path(s): (d) Based on your analysis, the project completion time is: Time (weeks) Predecessors B B 11 13 17 14 LF Slack…arrow_forward
- You are the project manager of the NHQ Project, which is part of the HQQ Program to construct a condominium building. Samuel, the program manager, has required that you document any variances to costs, schedule, scope, and quality expectations as part of the program governance. You believe that your project team now has an internal failure cost that needs to be documented for Samuel. Which of the following is an example of internal failure cost? Group of answer choices Project team training Rework Random quality audits Quality auditsarrow_forwardAn interval estimate is typically preferred to a point estimate becausearrow_forwardThe chart below shows the initial investment and expected yearly payback for Project A and Project B Project A Project B Initial Investment $ 300,000 $ 450,000 Expected Yearly PayBack $ 45,000 $ 90,000 For Project A, There has been a change in the expected yearly payback. Years 1 and 2 – you are expecting $45,000 each year. For the next three years, you are expecting $70,000 each year. What would be the average ROI for this alternative?arrow_forward
- Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis. Click the icon to view the table. a. Based on the critical path, find the probability of completing the office renovation project by 40 days. Refer to the standard normal table. (Make sure to round all intermediate calculations for to and variance to two decimal places.) The probability is . (Enter your response rounded to four decimal places.)arrow_forward(g) Using the IF function, write a formula in J38 to display "Yes" if the activity is critical and display "No" if the activity is not critical. Copy the formula to cells J39:J44.To calculate the entire project's variance, we simply add variance for activities on the critical path. Screenshot attached tahnks!!!arrow_forwardA project costs $360,000 initially and will generate project cash flows of $50,000 every year for 8 years. The required return for the project is 9%. What is the NPV of the project (in $)? p+ decimals Submitarrow_forward
- Text: We can develop the CSR activities for Nestle company of planting trees and cleaning the lakes. This can be done by partnering with NGOs who are already working in these areas. The company can target several trees to be planted, for example, 100,000 in a quarter and take care of them till growth. To clean the lake, it can take the help of the National scientist of environmental science and fund the project to clean some of the lakes with the target number of again 50. A long-term solution must be used by them in cleaning the lakes, like stopping the sewage inflow and creating a small recycling plant before throwing water into the water bodies. The government, municipality, NGO, and environmental scientists are the main stakeholders involved. Here, the competition must not be created, but collaboration was be done between the competitors to help the society. The competitors will be other brands like Unilever and P&G. Progress indicators can be used as the number of trees…arrow_forwardSuppose you have a choice of three projects to choose from. Here the expected profits from these projects under the following economic scenarios: Project Poor/Fair Moderate/Stable Strong/Booming A -200 $400 $700 B -700 600 1200 C 100 500 900 Now suppose the probability of a Poor/Fair economy is 25%, a Moderate/Stableeconomy is 45% and there is a 30% chance for a Strong/Booming economy.A) Setup a decision tree.B) Determine the expected value (EV) for each project. What project shouldbe selected based on the expected value approach? Why?C) Determine the expected value with perfect information about the states ofnature?D) Determine the expected value without perfect information about the states ofnature?E) Determine the expected value of perfect information.arrow_forwardYou are the Project Analyst for Nairobi Project Advisors who have been asked by a client to advise on which of the following two projects should be accepted. Each project costs US$ 10,000 and each entails a 12% cost of capital: Year Expected Net Cash flows Project X Project Y 0 ($ 10,000) ($ 10,000) 1 6,500 3,500 2 3,000 3,500 3 3,000 3,500 4 1,000 3,500 a) Advise on which project should be undertaken using the Pay Back Period (PBP), Net Present Value (NPV), Internal Rate of Return (IRR), and Modified Internal Rate of Return (MIRR) assuming: i. The projects are independent ii. The projects are mutually exclusivearrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.