(3) A project was planned using PERT. Its expected completion time was determined to be 85 days. The variance of 1 path is 49. What is the probability the project will be completed within 75 days (5 decimal places) Let X=the project completion time. PLX Please show how you use the Normal Curve Table to obtain your a (4) Perform a project nagement analysis for the data given below to determine ES, EF, LS, LF, and slack for each activity, the total peoyut oompletion time, and the critical puthe Activity || Time (weeks) | Predecessors A in the space below. 11 13 С 10 A 17 C.E D A 14 D.F (a) Draw a network with t, ES, EF, LS, and LF (follow the same format as Figure 11.5 on p.394) B С (b) Complete the following table (similar in format to Table 11.3 on p.396) Activity ES EF LS A D E F G H Activity | Time (weeks) | Predecessors B E F B (c) Identify the critical path(s): (4) Based on your analysis, the project completion time is: LF Slack Critical weeks and the least critical activity is

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
(3) A project was planned using PERT. Its expected completion time was determined to be 85 days. The variance of
the critical path is 49. What is the probability the project will be completed within 75 days (5 decimal places)? Let
X= the project completion time.
PIX
Please show how you use the Normal Curve Table to obtain your answer in the space below.
(4) Perform a project management analysis for the data given below to determine ES, EF, LS, LF, and slack for each
activity, the total project completion time, and the critical path.
Activity
E
12
F
B
10
G
C.E
9
H
D, F
(a) Draw a network with 1, ES, EF, LS, and LF (follow the same format as Figure 11.5 on p.394),
B
с
Activity Time (weeks) Predecessors
A
B
с
D
D
E
F
G
13
(b) Complete the following table (similar in format to Table 11.3 on p.396),
Activity Time (weds) ES
EF
LS
A
A
A
Time (weeks) Predecessors
B
(c) Identify the critical path(s):
(4) Based on your analysis, the project completion time is:
LF
11
13
17
Slack
Critical?
weeks and the least critical activity is:
Transcribed Image Text:(3) A project was planned using PERT. Its expected completion time was determined to be 85 days. The variance of the critical path is 49. What is the probability the project will be completed within 75 days (5 decimal places)? Let X= the project completion time. PIX Please show how you use the Normal Curve Table to obtain your answer in the space below. (4) Perform a project management analysis for the data given below to determine ES, EF, LS, LF, and slack for each activity, the total project completion time, and the critical path. Activity E 12 F B 10 G C.E 9 H D, F (a) Draw a network with 1, ES, EF, LS, and LF (follow the same format as Figure 11.5 on p.394), B с Activity Time (weeks) Predecessors A B с D D E F G 13 (b) Complete the following table (similar in format to Table 11.3 on p.396), Activity Time (weds) ES EF LS A A A Time (weeks) Predecessors B (c) Identify the critical path(s): (4) Based on your analysis, the project completion time is: LF 11 13 17 Slack Critical? weeks and the least critical activity is:
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.