Question
7.
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an expected project completion time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline? (select the closest answer)
Select one:
a.
about 4%
b.
over 99%
c.
about 80%
d.
about 46%
e.
about 96%
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Which of the following statements regarding PERT analysis is TRUE? Select one: O a Project variance is the sum of all activity variances. O b. Project standard deviation is the sum of all critical activity standard deviations. O c. Each activity has two estimates of its duration. O d. Only critical activities contribute to the project variancearrow_forwardUsing the information given and the project completiontime calculated in Problem 9(a), reduce the completion time ofthe project by 3 weeks in the most economical way.arrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Crash Normal Activity Time (days) Time (days) Normal Cost A 5 4 B 9 7 C 6 5 D 7 5 E 7 4 Total Cost with Crashing Immediate Predecessor(s) $800 $300 $600 $750 $1,200 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $400 $650 $1,500 $1,650 | | | < 0arrow_forward
- You have determined the following for a given project: Expected completion time of the project = 26 weeks Standard deviation of project completion time = 8 What is the probability of completing the project in more than 32 weeks? answer as a decimal and take it to four places.arrow_forwardConsider the office renovation project data in Table 7.16. A“zero” time estimate means that the activity could take a verysmall amount of time and should be treated as a numericzero in the analysis.a. Based on the critical path, find the probability ofcompleting the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure ofcompleting the project.arrow_forwardgiven the following information for a 1-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the plan value, Evie is the earned value, AC is the actual cost, and BAC is the budget at completion.pv =$ 23,000ev = 20,000ac= 25,000bac = 130,000a. what is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI for the project?B. how is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?C. use the CPI to calculate the estimate at completion EAC for this project.d. use the SPI to estimate how long it will take to finish this project.e. sketch the earned value chart for this project, use the figure below as a guide. Assume the data for month one is half of the values given for Pv, Ev and ac at the end of month 2arrow_forward
- Gmarrow_forward4. Using a discounted rate of 12 percent, INITIAL COST NET CASH FLOW YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 PROJECT A (BROILER) K100,000 (20,000) 10,000 40.000 40.000 150.000 PROJECT B (LAYERS) K100,000 33,000 33,000 33,000 33,000 33,000 a. Determine the net present value of project A and B b. Calculate the IRR on mutually exclusive investment of project A and B. C. Which project must the farm undertake and why?arrow_forward#9arrow_forward
- Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis. a. Based on the critical path, find the probability of completing the office renovation project by 39 days. Refer to the standard normal table (Make sure to round all intermediate calculations for te and variance to two decimal places.) The probability isarrow_forwardThe following information relates to a project (task times are in weeks). Use the information to solve for the critical path and then to determine the probability that the project could be completed within 36 weeks. Task A B C D E F Preceding Tasks to 4 4 2 None A B D, E tm 6 7 7 8 13 9 8 0 W CON 6 tp 8 10 12 18 15 10 Click the icon to view the table of standard normal probabilities. The probability that the project is completed within 36 weeks is. (Enter your response rounded to four decimal places.)arrow_forwardCan you detect the risk management of the project “Organising a Fan Convention at Birkbeck. This could be to organise an event/concert that could connect students/staff with a celebrity of their liking. Identify – minimum 15 different risks • Analyse Use the probability/impact matrix and place all risks there For 5 risks, from different boxes, explain in detail why you think they have that level of probability and impact on the project. (use 1-2 slides) • Response strategies and specific response actions• Use the simplified risk register provided in the lecture and seminar• For 5 risks, propose a response strategy AND specific response actions for each of these. • At least one of these 5 risks should be a positive riskarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.