Question
Indirect cost for a project are $12,000.00 per week as long as the project lasts. The project manager has supplied the cost and time information shown. Use the information to:
A. Determine an optimum crashing plan.
B. Graph the total costs for the plan.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Can you detect the risk management of the project “Organising a Fan Convention at Birkbeck. This could be to organise an event/concert that could connect students/staff with a celebrity of their liking. Identify – minimum 15 different risks • Analyse Use the probability/impact matrix and place all risks there For 5 risks, from different boxes, explain in detail why you think they have that level of probability and impact on the project. (use 1-2 slides) • Response strategies and specific response actions• Use the simplified risk register provided in the lecture and seminar• For 5 risks, propose a response strategy AND specific response actions for each of these. • At least one of these 5 risks should be a positive riskarrow_forwardIf the pessimistic duration of an activity is 205, the most likely duration is 160 days and the optimistic duration is 115 days, what is the expected time of the activity for PERT/CPM analysis ? What is the variance for the activity time for PERT/CPM analysis ?arrow_forwardShrink the occurrence time of the following project and find: a) The critical path and the expected project completion time. b) Find the optimal duration and optimal cost. Normal Crash Activities Time Cost Time Cost 1-2 100 1-3 150 2-4 50 2-5 100 3-4 100 4-5 80. 843324 722213 200 230 90 150 200 100arrow_forward
- Problem 3: Kelly Melford Kelly Melford and her team are working on redesigning a client's home. The client requested Kelly for the project to be completed sooner. Kelly asked her assistant to collect information from her team on the project. Her assistant organized the information she got into a table. The information is given in weeks. Based on the information below, prepare a comprehensive report that includes the following: 3. Your insights on the cost-time trade-off for this project. 4. Your recommended strategy for crashing the project.arrow_forwardThe expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 31 periods? ID A B C D E F G H Description Pilot production Select channels of distribution Develop program Test market Patent Full production Ad promotion Release 55% 77% 88% 66% Predecessor None None None A A D C B,E,F,G 6 7 4 4 10 16 3 2 Variance [(b-a)/6]2 3 4 2 2 5 10 2 1arrow_forwardI need solve this in project managementarrow_forward
- A project has three critical paths: A-B-C-D-E, A-G-H-E, and A-F-I-E. Crashing costs (in thousands, per week) for each activity is listed below: Activity Crashing Crashing Crashing 1st time 2nd time 3rd time 37 1 27 4. C 26 2 8 39 4. F 28 29 2 G 27 25 H. 8. 3 What is the total cost of reducing this project by two weeks? а. 44 b. 76 C. 48 d. 50 e. 34 2] 4, O'Oarrow_forwardDevelop a project network. Determine the expected project completion time. What is the probability that the project completion time will be completed? With in 2 weeks earlier than the expected project completion time? With in 1.5 week more than the expected project completion time ?arrow_forwardDiscuss the value of the business case, benefits management plan and the feasibility study to the project manager.arrow_forward
- Your hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table that is attached as an image. a) Draw the network diagram.b) Identify all project paths. Which path is the critical path and why?c) What is the project completion time and total project costs if only normal times are used? Activityarrow_forwardNow as per the project brief: Need the below help Feasibility/Risk Assessment: • Calculate individual scores for TELOS feasibility factors. Calculate an overall score. Important: providejustification/explanation for the scores, including the overall score. For example, if you assign theTechnical feasibility a score of 9, then please explain why.• Technical–Is it likely that our staff can build it?• Economic–Is the projected return worth the investment?• Legal–Will doing this project violate laws or contractual agreements?• Operational–If built, is it likely that the system will really address or solve the business problem?• Schedule–Is it likely to be built in time to realize benefits and/or meet constraints?arrow_forward3.1 Use the generated information to calculate the NPV of the project, to decide whether to go ahead with the project. Investment required Expected economic lifetime R200 000 5 years. Minimum required rate of return 10% Net annual cash inflows 1st year 2nd year R40 000 R100 000 R90 000 3rd year R40 000 4th year R30 000 5th yeararrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.