Question
Given the following project (all times are in days):
please refer the pic
All activities, except for activity b , may be partially crashed.(i.e. partial crashing for activity b only, is not allowed.)
2) If the project indirect cost is $89/day, what is the optimal completion time and the corresponding total cost?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 5 steps with 6 images
Knowledge Booster
Similar questions
- Development of Version 2.0 of a particular accountingsoftware product is being considered by Jose Noguera'stechnology firm in Baton Rouge. The activities necessary for thecompletion of this project are listed in the following table: a) What is the project completion date?b) What is the total cost required for completing this project on normal time? c) If you wish to reduce the time required to complete this projectby I week, which activity should be crashed, and how much will this increase the total cost?d) What is the maximum time that can be crashed? How much would costs increase?arrow_forward#3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardbit have been awarded the project and can begin working on the project from 12th October 2020. The project should be handed over to Barstow’s (launch) no later than 2nd April 2021. If project activities extend beyond this date, Orbit will pay a project penalty of 2% of project value for each working days delay.(Note: There is an important activity constraint that has been missed from this description – What is it?). Please explain brieflyarrow_forward
- Using the information given and the project completiontime calculated in Problem 9(a), reduce the completion time ofthe project by 3 weeks in the most economical way.arrow_forwardA) What is the variance activity B? 2 decimal places B) What is the variance of activity F? 2 decimal places C) what is the probability the project can be completed? 4 decimals places only D) what is the probability the project will be 3 weeks late from the expected completion time ? 4 decimal places only.arrow_forwardThree recent college graduates have formed a partnership and have opened an advertising firm.Their first project consists of activities listed in the following table.a. Draw the precedence diagram.b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?c. Suppose it is now the end of the seventh day and that activities A and B have been completedwhile activity D is 50 percent completed. Time estimates for the completion of activity D are5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing theproject by day 24 and the probability of finishing by day 21.TIME IN DAYSActivityImmediatePredecessor Optimistic Most Likely PessimisticA — 5 6 7B — 8 8 11C A 6 8 11D — 9 12 15E C 5 6 9F D 5 6 7G F 2 3 7H B 4 4 5I H 5 7 8End E, G, Id. The partners have decided that shortening the project by two days would be beneficial, as longas it doesn’t cost more than about $20,000. They have estimated the daily crashing costs for…arrow_forward
- Given the following project (all times are in days): refer the pic please All activities, except for activity b , may be partially crashed.(i.e. partial crashing for activity b only, is not allowed.) 1. Draw the network and find the critical path, time, and total cost for an all-normal level of project activity.arrow_forwardPlease find the questions Note : The first question is in detail the question of the (LSD, LFD)arrow_forwardThe following payoff table shows profit for a decision analysis problem with two decision alternatives and three states of nature. Decision Alternative If S1 d₁ d₂ States of Nature then ? $1 240 90 90 15 The probabilities for the states of nature are P(S₁) = 0.65, P(s₂) = 0.15, and P(s3) = 0.20. (a) What is the optimal decision strategy if perfect information were available? ; If S₂ then ? 90 65 ; If S3 then ? (b) What is the expected value for the decision strategy developed in part (a)? î (c) Using the expected value approach, what is the recommended decision without perfect information? What is its expected value? The recommended decision without perfect information is ? EV = (d) What is the expected value of perfect information? EVPI = îarrow_forward
- 9. A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration of 1 day. (This is the same network as a previous problem.) What is the minimum total cost to shorten the project by 2 days? Round your answers to 2 decimals. Activity Precedent Duration Crash cost/day A - 3 $350 B A 3.8 $250 C A 6 $400 D B 6 $150 E B 4.1 $200 F C 4 $275 G D 6.2 $500 H E 8 $300 Answer:arrow_forwardDraw a network representation of the project (nodes = activities, arrows = precedence constraints). Provide early start/early finish as well as late start/late finish times for all activities. What is the duration of the project, and which tasks are on the critical path? Task Description Duration Predecessors A Project Planning 16 days - B Evaluation Existing Apps 20 days - C Define Value Proposition 12 days B D Define User Interface 18 days B E Define Technology Requirements 22 days C and D F Document Requirements 14 days E G Develop Architecture 35 days A and F H Creation Code Design 18 days G I Roadmap Feature Development 12 days G J User Interface Development 74 days H and I K Code Development 92 days H and I L Release Testing 32 days J and K M Get User Feedback 22 days L N Bug Fixing 28 days L O Marketing Plan 54 days E P Release Product 5 days M, N and Oarrow_forwardHow can we determine the probability that a project will be completed by a certain date? What assumptions are made in this computation?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.