Using the following project information, calculate the variance for each of the project activities.
Activity
|
Optimistic Time
Estimate(weeks) |
Most Likely Time
Estimates (weeks) |
Pessimistic Time
Estimates (weeks) |
Immediate
Predecessor(s) |
||||
---|---|---|---|---|---|---|---|---|
A
|
2 | 3 | 5 | none | ||||
B
|
2.5 | 4 | 5 | A | ||||
C
|
5 | 7 | 8 | A | ||||
D
|
3 | 5 | 7 | B,C | ||||
E
|
4 | 7 | 14 | B,C | ||||
F
|
2 | 5 | 8 | D | ||||
G
|
4 | 5 | 6 | E | ||||
H
|
6 | 6 | 8 | F | ||||
I
|
4 | 8 | 10 | G | ||||
J
|
2 | 3 | 3 | H,I |
(Round your answers to 2 decimal places, e.g. 1.75.)
Activity
|
Variance
|
---|---|
A
|
enter a variance rounded to 2 decimal places |
B
|
enter a variance rounded to 2 decimal places |
C
|
enter a variance rounded to 2 decimal places |
D
|
enter a variance rounded to 2 decimal places |
E
|
enter a variance rounded to 2 decimal places |
F
|
enter a variance rounded to 2 decimal places |
G
|
enter a variance rounded to 2 decimal places |
H
|
enter a variance rounded to 2 decimal places |
I
|
enter a variance rounded to 2 decimal places |
J
|
enter a variance rounded to 2 decimal places |
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 3 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- please help and solve correctly..will give upvote if rightarrow_forwardA paint company has three sources for buying bright red pigment for its paints: Vietnam, Taiwan, and Thailand. Unfortunately, the pigment is made from a bush whose annual growth is heavily dependent upon the amount of rainfall during the growing season. The following tables show probabilities and prices for wet, dry, and normal growing seasons. Probabilities Wet Dry Normal Vietnam 0.5 0.2 Taiwan 0.6 0.3 Thailand 0.4 0.4 Price/Pound ($) Vietnam 0.96 1.11 Taiwan 0.86 1.25 Wet Dry Normal Thailand 0.92 1.19 0.3 What country shoul the company select? Thailand Taiwan Vietnam 0.1 0.2 1.05 0.99 1.06 What is the expected value (price) associated with it?arrow_forwardPlease help with (b) and (c) as both answers given were incorrect! Please need correct answers. Blue Lagoon is a contractor that installs residential swimming pools, projects that consist of nine major activities. The activities, their immediate predecessors, and the activity time estimates (in days) are shown. Activity Immediate Predecessor Optimistic Most Probable Pessimistic A 3 5 6 B 2 4 6 C A, B 6 7 8 D A, B 8 10 11 E B 2 4 6 F C 1 2 3 G D 6 10 12 H D, F 7 9 11 I E, G, H 3 4 5 (a) What are the critical activities? (Enter your answers as a comma-separated list.) $$A, D, G, I (b) What is the expected time (in days) to complete the project? (Round your answer to two decimal places.) (c) Based only on the critical path, what is the estimated probability that the project can be completed in 28 or fewer days? (Round your answer to four decimal places.)arrow_forward
- 1) Lucy is in charge of planning and coordinating a project. Following is the activity information for this project. Time (weeks) Activity Preceded By Optimistic Most Likely Pessimistic A -- 2 2 4 B A 8 12 16 C A 4 8 12 D B,C 2 4 6 E B 4 6 8 F A 2 4 6 G D 2 4 6 H G 2 4 6 I E,F,H 2 2 2 (a) Construct a precedence diagram. (b) Identify the Critical Path(s) and the expected completion time. (c) What is the probability that the training program can be completed in 26 weeks?arrow_forwardThe expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 31 periods? ID A B C D E F G H Description Pilot production Select channels of distribution Develop program Test market Patent Full production Ad promotion Release 55% 77% 88% 66% Predecessor None None None A A D C B,E,F,G 6 7 4 4 10 16 3 2 Variance [(b-a)/6]2 3 4 2 2 5 10 2 1arrow_forwardwhat is the total duration? answer it through excel file. thank you so mucharrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.