Question
The times are written to indicate weeks!!!!
Let the start date of the project shown in Activity 3 be January 1, 2020. Determine start dates of all the activities. Draw a Gantt chart. You may use Microsoft Excel, Gantt project, or some other software.
Note:-
- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
- Answer completely.
- You will get up vote for sure.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 4 steps with 8 images
Knowledge Booster
Similar questions
- You are a project manager for a project in the execution phase that is on schedule and on budget. Your sponsor asks you for a project status update. What information about your project would you want to include in an update and explain why you picked each.arrow_forwardBy how many weeks should activity C be crashed? Number By how many weeks should activity D be crashed? Number By how many weeks should activity E be crashed? Number By how many weeks should activity F be crashed? Number What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.) Numberarrow_forwardProject scope (Per Chapter 4, this should be more detailed than the proposal scope)a. Project Objectivesb. Customer Requirementsc. Project Statement of Work (Tasks)d. Project Deliverablese. Project Acceptance/Success Criteria2. Provide Estimated Number of Workers Needed to Complete Project and their responsibilitiesa. Develop fictional people with professions needed to complete the project3. Provide a Task List/Work Breakdown Structure to divide the project into piecesa. Use graphical structure from pages 114-115 in text 4. Provide a Network Diagram for your project with estimated activity durations for each step. 5. Using a Project Schedule similar to page 161 in the text, provide a schedule for the project if wewere to start on June 1st, i.e. estimated time to completion and time to complete various tasksa. Need Earliest Start/Finish and Latest Start/Finish Calculations, and Slackb. Identify the Critical Path in your project6. Provide any risks that your team believes the…arrow_forward
- Issues in project management include a. level of effort. b. period of performance. c. budget. d. all of the above. e. a and c only.arrow_forwardA company accepts a proposal from a third-party vendor to provide staffing. Which of the following documentsshould the project manager create NEXT? A. SLAB. SOWC. LOID. RFQarrow_forwardWhich of the following is NOT found in a project charter?A. Procedures to managing changes to contractsB. The business case for the projectC. Constraints and limitations on the project workD. Assumptions that have been made about the project Which of the following best describes the triple constraint?A. Cost, schedule, and qualityB. Cost, schedule and scopeC. Cost, resources, and scheduleD. Cost, schedule, and product What is a risk owner?A. The person who is responsible for the response plan for the risk.B. The person who monitors the watch list that contains the risk.C. The person who meets with stakeholders to explain the risk.D. The person who makes a risk happen.arrow_forward
- must be measured regularly to identify variances from the plan. O A. Schedule progress O B. Project performance O C. Cost O D. Stakeholder requirementsarrow_forwardNote:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardOne of Mary's employees, Shira, has obtained a new job and given her two weeks' notice. Shira was responsible for updating the company website with information on the new bag policy. Mary gave Shira's responsibilities to another employee in the Marketing department who has similar knowledge and skills.What is the probability of this risk occurring and what is the impact on the project? a.) Low probability and medium impact b.) High probability and high impact c.) Medium probability and low impact d.) High probability and low impactarrow_forward
- include the elements related to project planning requested below. An employee has been appointed by the company he works for to make a plan for the creation of a new customer service department. To carry it out, he will apply project management concepts. The following is required: Establish what the initial requirements are for said project through a project constitution with all the required parts. You must use the terminology associated with project management.The articles of incorporation must include: a) Project overviewb) The components of the project teamc) A list of the project's stakeholdersd) Two (2) project objectives using the SMART guidee) The scope of the projectf) An approximate budget of the project costsg) Two (2) risks associated with the projectarrow_forwardA potential conflict on projects is work scope; conflict can arise from differences of opinion on all the following except A. how much work should be done. B. how the work should be done. C. at what level of quality the work should be done. D. the cost of the work to be done.arrow_forwardPlease provide feedback and reaction to discussion below. A project is a “temporary activity launched for a specific purpose, to carry out a particular objective” (Wallace, 2020, p. 354). Projects are generally special and specific to a certain task. They also can contain many complicated or long-term steps that are needed to complete the project. In a project, steps and tasks are not always straight to the point. Because projects are unique, there are constraints to be followed. These constraints are forces that consists of time consumption, costs and budgets, and scope (Wallace, 2020). These forces work hand in hand and affect each other differently. A process is different from a project and generally less complicated. While projects contain complicated and elongated steps, processes are usually shorter and straight to the point. A process “is a series of events designed to deliver a product or service that is repeated over and over” (Wallace, 2020, p. 354). In order to keep the…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.