The 15km Atta Mills road connecting Old Barrier to Kokrobite operates with a capacity of 2250 pcu/hr and can be traversed within 15 minutes under free flow conditions. If a  flow of 3100 pcu/hr is assigned to the road based on the capacity-restrained approach,  what would be the resultant travel time after the traffic assignment proce ss.

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter9: Capacity And Level Of Service For Highway Segments
Section: Chapter Questions
Problem 21P
icon
Related questions
Question

Q3b. The 15km Atta Mills road connecting Old Barrier to Kokrobite operates with a capacity of 2250 pcu/hr and can be traversed within 15 minutes under free flow conditions. If a  flow of 3100 pcu/hr is assigned to the road based on the capacity-restrained approach,  what would be the resultant travel time after the traffic assignment proce ss.

Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning