(Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.
2017 | 2018 | 2019 | |
Costs to date | $270,000 | $450,000 | $610,000 |
Estimated costs to complete | 330,000 | 150,000 | –0– |
Progress billings to date | 270,000 | 550,000 | 900,000 |
Cash collected to date | 240,000 | 500,000 | 900,000 |
Instructions
(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 4 images
- Please walk through problemarrow_forward1. At the Poly Novo 2023 Annual General Meeting (" AGM) heid on 3 November, 2023 they revealed plans to construct a new manufacturing facility adjacent to its existing facility, PolyNovo has already performed a substantial amount of design analysis related to the new facility at a cost of $70, 000. The capital expenditure of $845, 000 associated with the construction of the new facility and the annual operating expenses are substantial. 2. The capital cost of the new facility is expected to be $845, 000 today. PolyNovo must also purchase $300, 000 of plant and equipment ("P&E"). At the end of FY23 PolyNovo had" $46.8m of cash on hand and it plans to use S0.3 million of their cash balance to pay for the building which will reduce the capital cost to just $545,000. If the new facility is built, a piece of obsolete manufacturing equipment must be sold. The equipment had a total capital cost in 2020 of $220,000 and is being depreciated at 511,000 per annum for the years 2021 to 2030…arrow_forwardBeavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,850,000. The project was begun in 2023 and completed in 2024. Cost and other data are presented below: 2023 2024 Costs incurred during the year $ 435,000 $ 1,150,000 Estimated costs to complete 1,015,000 0 Billings during the year 425,000 1,425,000 Cash collections during the year 325,000 1,525,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross profit recognized during 2023 and 2024.arrow_forward
- Sodlnoarrow_forwardCurrent Attempt in Progress Flounder, Inc. began work on a $6,504,000 contract in 2020 construct an office building. During 2020, Flounder, Inc. incurred costs of $1,639,900, billed its customers for $1,300,000, and collected $1,055,000. At December 31, 2020, the estimated additional costs to complete the project total $3,650,100. Prepare Flounder's 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is required, select "No entry" for the account titles and enter O for the amounts.) Account Titles and Explanation (To record costs incurred.) (To record billings.) (To record collections.) (To recognize revenue.) eTextbook and Media List of Accounts Save for Later Debit Credit Attempts: 0 of 3 used Submit Answerarrow_forwardHi can someone help me with this question please?arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education