On January 1, Miller Construction Company contracted to build a parking lot for the city of St. Louis for $1,125,000. The following transactions and estimates relate to this contract. Construction costs incurred during 2020 $600,000 Progress billings $285,000 Cash collections $262,500 Estimated costs to complete $600,000 Required a. Prepare the journal entry to record profit or loss assuming revenue is recognized over time. •Note: If a journal entry isn't required on any of the dates shown, select "N/A-debit" and "N/A-credit" as the account names and leave the Dr. and Cr. answers blank (zero). Account Name Cost of Construction Revenues from Long-Term Contracts Construction in Process To recognize revenues and expenses N/A-Debit Account Name Dr. 600,000 N/A Credit To recognize revenues and expenses b. Prepare the journal entry to record profit or loss assuming revenue is recognized at a point in time. •Note: If a journal entry isn't required on any of the dates shown, select "N/A-debit" and "N/A-credit" as the account names and leave the Dr. and Cr. answers blank (zero). 0 0 Dr. Cr. 0 0 0 x 562,500 ✓ 37,500 * Cr. 0 x 0 x

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter6: Cash And Receivables
Section: Chapter Questions
Problem 9RE: Refer to RE6-8. On April 23, 2020, McKinncy Co. receives a check, from Mangold Corporation for...
icon
Related questions
Question
On January 1, Miller Construction Company contracted to build a parking lot for the city of St. Louis for $1,125,000. The following transactions and estimates relate to this contract. Required a. Prepare the journal entry to record
profit or loss assuming revenue is recognized over time. - Note: If a journal entry isn't required on any of the dates shown, select "N/A-debit" and "N/A-credit" as the account names and leave the Dr. and Cr. answers blank (
zero). b. Prepare the journal entry to record profit or loss assuming revenue is recognized at a point in time. -Note: If a journal entry isn't required on any of the dates shown, select "N/A-debit" and "N/A-credit" as the account
names and leave the Dr. and Cr. answers blank (zero).
Transcribed Image Text:On January 1, Miller Construction Company contracted to build a parking lot for the city of St. Louis for $1,125,000. The following transactions and estimates relate to this contract. Required a. Prepare the journal entry to record profit or loss assuming revenue is recognized over time. - Note: If a journal entry isn't required on any of the dates shown, select "N/A-debit" and "N/A-credit" as the account names and leave the Dr. and Cr. answers blank ( zero). b. Prepare the journal entry to record profit or loss assuming revenue is recognized at a point in time. -Note: If a journal entry isn't required on any of the dates shown, select "N/A-debit" and "N/A-credit" as the account names and leave the Dr. and Cr. answers blank (zero).
On January 1, Miller Construction Company contracted to build a parking lot for the city of St. Louis for $1,125,000. The following transactions and estimates relate to this contract.
Construction costs incurred during 2020 $600,000
$285,000
$262,500
$600,000
Progress billings
Cash collections
Estimated costs to complete
Required
a. Prepare the journal entry to record profit or loss assuming revenue is recognized over time.
●Note: If a journal entry isn't required on any of the dates shown, select "N/A—debit" and "N/A—credit" as the account names and leave the Dr. and Cr. answers blank (zero).
Account Name
Cost of Construction
Revenues from Long-Term Contracts
Construction in Process
To recognize revenues and expenses
N/A-Debit
Account Name
Dr.
600,000
N/A-Credit
To recognize revenues and expenses
b. Prepare the journal entry to record profit or loss assuming revenue is recognized at a point in time.
•Note: If a journal entry isn't required on any of the dates shown, select "N/A-debit" and "N/A-credit" as the account names and leave the Dr. and Cr. answers blank (zero).
0
0
Dr.
Cr.
0
0
0 x
562,500✔
37,500 *
Cr.
0x
0 x
Transcribed Image Text:On January 1, Miller Construction Company contracted to build a parking lot for the city of St. Louis for $1,125,000. The following transactions and estimates relate to this contract. Construction costs incurred during 2020 $600,000 $285,000 $262,500 $600,000 Progress billings Cash collections Estimated costs to complete Required a. Prepare the journal entry to record profit or loss assuming revenue is recognized over time. ●Note: If a journal entry isn't required on any of the dates shown, select "N/A—debit" and "N/A—credit" as the account names and leave the Dr. and Cr. answers blank (zero). Account Name Cost of Construction Revenues from Long-Term Contracts Construction in Process To recognize revenues and expenses N/A-Debit Account Name Dr. 600,000 N/A-Credit To recognize revenues and expenses b. Prepare the journal entry to record profit or loss assuming revenue is recognized at a point in time. •Note: If a journal entry isn't required on any of the dates shown, select "N/A-debit" and "N/A-credit" as the account names and leave the Dr. and Cr. answers blank (zero). 0 0 Dr. Cr. 0 0 0 x 562,500✔ 37,500 * Cr. 0x 0 x
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning