FINANCIAL ACCOUNTING
10th Edition
ISBN: 9781259964947
Author: Libby
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
On September 1, 20x1, ABC Co. enters into a contract with a customer to remodel a plant's electrical wirings and install a new generator for a total consideration of P12. The remodeling and the installation are treated as a single performance obligation satisfied over time.
The expected contracts costs are as follows:
Generator 4,000,000
Other costs 5,000,000
Expected total contract costs 9,000,000
Additional information:
ABC Co. uses the cost-to-cost method in measuring its progress towards the complete satisfaction of the performance obligation.
ABC Co. incurs total costs of P6,000,000 in 20x1, including the cost of the generator.
The customer obtains control of the generator when it is delivered to the site in December 20x1. However, the generator will not be installed until March 20x2.
ABC Co. regards the cost of the generator as significant in relation to the expected total contract costs (i.e., 4M ÷ 9M = 44.44%).
Although ABC Co. acted as a principal in procuring the generator, ABC Co. is not involved in designing or manufacturing the generator.
The profit in 20x1 is
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- please help mearrow_forwardIn 20Y5, Duncan Construction Company agreed to construct an apartment building at a price of $1,200,000. The information relating to the costs and billings for the contract is shown below. Cost incurred to date Est. cost yet to be incurred Customer billings to date Collections of billings to date 20Y5 $ 280,000 520,000 150,000 120,000 ● 20Y6 $ 600,000 200,000 500,000 320,000 20Y7 $ 785,000 0 1,200,000 940,000 • Prepare a schedule showing the profit to be recognized each year. Prepare all journal entries required for all years using the percentage of completion method. Prepare all journal entries required for all years using the completed contracts method.arrow_forwardOn January 1, 20xl, ABC Company enters into a construction contract which includes a fixed contract price of P144,000 to build a bridge. On December 31, 20x1, the contractor's estimate of the total contract cost is still P96,000. However, by the end of 20x2 the contractor's estimate of contract costs increased to P120,000, excluding the variation below. In 20x2, the customer and the contractor agree to a variation resulting in an increase in contract revenue of P2,400 and estimated additional contract costs of P1,800. Actual cumulative costs incurred to the end of 20x1, 20x2 and 20x3 (the end of the contract) including the costs of the variation are P36,480, P85,260 and P120,500, respectively. At the end of 20x1, 20x2 and 20x3, the customer paid the contractor progress billings of P60,000, P36,000 and P48,000, respectively. The contractor determines the stage of completion of the contract costs incurred for a work performed to date bear to the latest estimated total contract costs.…arrow_forward
- Venus' Venerable Construction contracts to lay marble in a new museum over a three-year period, and the project is considered to be a single performance obligation. The company's accountants record the following details relating to the project: Contract details: Contract price Year Revenue Expense Income Estimated cost Estimated profit $1,500 $1,200 $300 Spending pattern during construction: Year 1 1 [R1] [E1] [11] Year 2 Year 3 $300 Answer the following question(s) by filling in the blanks. Do not include any symbols besides decimals in your answers (do not input commas). $750 Compute the amount of revenue, expense, and income for each year assuming that its performance obligation is fulfilled over time and that the costs it incurs are reflective of the value conveyed to the customer. 2 [R2] [E2] [12] $150 3 [R3] [E3] [13] Venus' Venerable Construction contracts to lay marble in a new museum over a three-year period, and the project is considered to be a single performance obligation.…arrow_forwardOn September 1, 20x1, ABC Co. enters into a contract with a customer to remodel a plant's electrical wirings and install a new generator for a total consideration of P10M. The remodeling and the installation single performance obligation treated as a satisfied over time. The expected contract costs Generator are LOU an as follows: 2,500,000 4,000,000 6,500,000 SALL Other costs Expected total contract costs VERSITY Additional information: • ABC Co. uses the cost-to-cost method in measuring its progress towards the complete satisfaction of the performance obligation. • ABC Co. incurs total costs of P4,000,000 in 20x1, including the cost of the generator. • The customer obtains control of the generator when it is delivered to the site in December 20x1. However, the generator will not be installed until March 20x2. • ABC Co. regards the cost of the generator as significant in relation to the expected total contract costs-eating during examinations, quizzes or plagiarism in connection •…arrow_forwardUN LOUIS ABC Co. started work on an P8,000,000 fixed-price construction contract in 20x1. Information on the contract is as follows: 20x1 20x2 Costs incurred per year 2,850,000 3,670,000 Estimated costs to complete 4,275,000 1,630,000 How much profit (loss) is recognized in 20x2?arrow_forward
- Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete the project are $5,000,000. Tullis billed $5,000,000 in year 1 and collected $3,100,000 by the end of the end of the year. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of year 1 on the balance sheet assuming the use of the completed - contract method? O A. asset of $2,000,000 O B. liability of $1,900,000 O C. asset of $1,900,000 O D. liability of $2,000,000arrow_forwardOn November 1, 20x5, GVF entered into a contract to buy a P225,000 machine from JDH. The contract requires GVF to pay P225,000 in advance on November 1, 20x5. The machine costs P165,000 and was delivered on November 30, 20x5. The journal entry by GVF for the delivery of the equipment will include:arrow_forwardCompute for the net income for year 3arrow_forward
- DMCI entered into a fixed price contract for the construction of a road for Camella Corp. DMCI determines the stage of completion of construction contracts using the "cost to cost method". The estimated total contract cost is P50 million. The following were the total actual costs incurred by DMCI during the first year of the construction: Cost of negotiating the contract (charge immediately as expense) 500,000 Costs of hiring equipment 700,000 Costs of materials purchased but not yet used in construction 2,500,000 Costs of materials used in construction 15,000,000 Costs of moving plant, equipment and materials to and from the 200,000 contract site Depreciation of equipment used in construction 600,000 Depreciation of idle construction equipment 300,000 Site labor costs 5,000,000 Site supervision costs 1,000,000 How much is the cost incurred to date?arrow_forwardOn January 1, 2018, DMCI Company started the construction of a building at a fixed contract price ofP1,000,000. On the same date, the customer paid a mobilization fee equal to 5% of contract price that will be deductible from the first billing. The outcome of construction contract cannot be estimated reliably During 2018, the entity billed the customer equivalent to 30% of the contract price. During 2019, the entity billed again the customer amounting to 20% of the contract price. During 2020, the entity billed again the customer amounting to 40% of the contract price. The remaining billing was made at the year of completion of the project. The entity made collection from the customer at the end of 2018, 2019 and 2020, in the amount of P120,000, P450,000 and P180,000, respectively. The entity provided the following data concerning the direct costs related to the said project: 2018 2019 2020 Cumulative costs incurred at year-end 360,000 800,000 870,000 Remaining estimated costs to…arrow_forwardLong-term Contracts Clorad Corp. contracts with a customer to construct a building. It appropriately determines that it has one performance obligation which is satisfied over time. Using the following information for Year 1, compute Clorad's (a) total estimated costs for the contract, (b) revenue to date, and (c) gross profit recognized. Year 1 (of 4-year project): Construction costs incurred during the year $174,000 Estimated costs to complete the contract 426,000 Partial billings to customers 100,000 Collections from customers 25,000 Total contract price 1,000,000 (a) Total estimated costs for the contract $ (b) Revenue to date $ (c) Gross profit recognized $arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education