Question
I need help with the critical path method. I want to do the critical path, slack times, and all earliest and latest start and finish times for each of the activities.
Activity |
Immediate Predecessor(s) |
Time (Days) |
A |
__ |
5 |
B |
A |
4 |
C |
A |
6 |
D |
B |
6 |
E |
B |
4 |
F |
C |
4 |
G |
D |
6 |
H |
E, F |
8 |
I |
G, H |
5 |
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 1 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Work Breakdown Structure (WBS) for A millionares mansion with four to five (4-5) high level tasks and an average of four to five (4-5) sub-tasks for each high level task. Under these 4 phases Planning - Interior Design - Landscape/Outdoor Entertainment - Project Closeoutarrow_forwardwhat is the difference between work package and wbs?arrow_forwardPlease don't provide handwritten solution ...arrow_forward
- SOS pls help i will thumbs up :)arrow_forwardConsider a project that has the following tasks (with the duration measured in days): Task ID Duration Dependency A 3 14 C,F a) Draw the PERT chart for the above table. Be sure to include sequencing and identification for all tasks and events along with their time estimates. b) What is the critical path. c) What is the total expected duration time represented by the critical path. earrow_forwardQ. Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resource Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. What is the project duration now? Could something like this happen in real projects? Do it in Excel Spreadsheet. Please calculate/draw the network plan with unconstrained resources. Draw the constrained resource loading schedule, then the constrained resource activity schedule (or new constrained network diagram) Explain it in detail.arrow_forward
- a) Prepare the Activity Node Diagram and identify the Critical Path b) Prepare Gantt ChartThanksarrow_forwardACTIVITY Immediate Predecessor Normal Duration (wks) Minimum Duration (wks) Crash Costs ($/wk) A --- 4 4 --- B --- 3 2 100 C A, B 5 3 200 D C 4 4 --- E C 2 1 300 F C 1 1 --- G D 3 2 200 H E 1 1 --- I F 1 1 --- J H, I 3 1 100 What is the slack time for Activity F and the late start for Activity H? Group of answer choices 2 weeks, 11 weeks 1 weeks, 11 weeks 3 weeks, 10 weeks 2 weeks, 12 weeks None of the above are correct.arrow_forwardQuestion 3 Answer the following questions based on the table below. Activity Precedence Duration (day) 30 Y U 8 R,Y 4 S U,Y 24 V S 10 V 28 W V.Z 14 U 22 X S,Z 12 а) Using information provided to draw a Project Network. Nodes in your Project Network must organize largely "from left to right", as discussed in class. It is normal for the precedence lines/arrows to cross each other. Then perform Forward Pass and perform Backward Pass calculation, on top of the Project Network, which you have drawn. Please ensure, you only draw one Project Network and one set of calculation, "duplication" of work, will not be graded. b) Identify all critical path in this project Identify the activity which you can delay the most days, while the project is still expected to be completed on-time. Determine the maximum number of days you can delay the activity which you have identified. c) List THREE (3) Project Path, where duration of each project path you have listed, has to be the top three lowest. Show the…arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.