Under IFRS 15, what is the net income/(loss) to be reported by the company for the years ended December 31, 2017 and 2018?

A. 30M and (15M)

B. 50M and (10M)

C. 60M and (15M)

D. 40M and (15M)

On January 1, 2017, Build Company entered into
oil
a
construction contract with
an
owner
to
build
an
refinery.
The
contract
has
the
following
characteristics;
the
oil
refinery
is
highly
customized to
the
owner's
specifications and changes to these specifications by the owner are expected
The oil refinery does not have an alternative use to
Non-refundable, interim progress payments are required as
can cancel the contract at any
time (with a termination penalty); any work in process is the property of the
As a result, another entity would not need to re-perform the tasks
over the contract term.
the contractor.
a.
mechanism to
finance the contract.
The owner
owner.
performed
completion of the contract.
single performance obligation
evidences suggests that
to
date.
Physical
possession
and
title
do
not
pass
until
The contractor determines that the contract has
a
to build the
refinery.
The majority of
the contractor's performance creates an
is being transferred
assets
that
the
customer
controls
and control
over
time.
Build
concludes that input method (cost to cost method) instead of output method is
reasonable method for measuring the progress toward satisfying its
a more
performance obligation.
duration is 3 years with
estimated contract
cost as of December 31, 2017 is P200M.
including
represent/depict the
The
contract
total
revenue
of
P300M.
The total estimated contract
The
Cost
incurred
during
year
2017
as
120M
P20M
related
to
contractor-caused inefficiencies which do
not
transfer
of goods or
services
to
the customer.
As of December 31,
2018, the total
estimated
contract
cost
becomes
250M
due
to
increase
in
cost
of
raw
materials.
contractor-caused inefficiencies which do
The cost incurred during 2018 is P105M including P5M related to
not represent/depict the
transfer
of goods or services to the customer.
Under IFRS 15, what is
the net income/(loss)
for the years ended December 31, 2017 and 2018?
to be reported by the company
Transcribed Image Text:On January 1, 2017, Build Company entered into oil a construction contract with an owner to build an refinery. The contract has the following characteristics; the oil refinery is highly customized to the owner's specifications and changes to these specifications by the owner are expected The oil refinery does not have an alternative use to Non-refundable, interim progress payments are required as can cancel the contract at any time (with a termination penalty); any work in process is the property of the As a result, another entity would not need to re-perform the tasks over the contract term. the contractor. a. mechanism to finance the contract. The owner owner. performed completion of the contract. single performance obligation evidences suggests that to date. Physical possession and title do not pass until The contractor determines that the contract has a to build the refinery. The majority of the contractor's performance creates an is being transferred assets that the customer controls and control over time. Build concludes that input method (cost to cost method) instead of output method is reasonable method for measuring the progress toward satisfying its a more performance obligation. duration is 3 years with estimated contract cost as of December 31, 2017 is P200M. including represent/depict the The contract total revenue of P300M. The total estimated contract The Cost incurred during year 2017 as 120M P20M related to contractor-caused inefficiencies which do not transfer of goods or services to the customer. As of December 31, 2018, the total estimated contract cost becomes 250M due to increase in cost of raw materials. contractor-caused inefficiencies which do The cost incurred during 2018 is P105M including P5M related to not represent/depict the transfer of goods or services to the customer. Under IFRS 15, what is the net income/(loss) for the years ended December 31, 2017 and 2018? to be reported by the company
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Accounting Equation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education