A network consists of the following list. Times are given in weeks.
Activity Preceding. Optimistic. Most likely Pessimistic
A -- 5 11. 14
B - 3 3 9
C -- 6 10 14
D A, B 3 5 7
E B 4 6 11
F C 6 8 13
G D, E 2 4 6
H F 3 3 9
A. Draw the activity network for this problem .
B. Determine the Expected Time and Variance for each activit
C. Show the activity
D. Determine and state the critical path for this project. This must be based on your work in
E. What are the expected time and the variance of the project?
F. Calculate the probability that the project will be completed in less than 28 weeks
Step by stepSolved in 2 steps with 2 images
- States) B E- Text Predictions: On Activity A I U 2. Given below are additional details for the Evergreen Company's construction project, i.e. three time estimates. B C D ALL E F Optimistic 0.5 ARDCCDGEe Normal 2.5 1 0.9 0.5 Most Likely 1 2 3 2 1 AaBb CcDdEe No Spacing 1 AaBbCcL AaBbCcDd. Heading 1 Heading 2 Pessimistic 2 2.5 3.5 3 1.1 1.5 a) Calculate the expected completion times and completion variances for each activity. b) What are the expected days to completion now for Evergreen? c) Compute the variance and standard deviation of the Evergreen project's completion time. d) What is the probability that the Evergreen Company's project can be completed in 6.5 days? e) What would be Evergreen Company's completion days if we needed a 95% confidence level? f) Which noncritical activities should Evergreen Company monitor closely? Why? Focus Earrow_forwardAABCDE Activity J К Predecessor None PZABUD FGHL-KL EOFICI LA C H с H J.I,K Draft PDS Identify team Kickoff team meeting Source previous rocket Identify & order missing or new materials/parts Assembly Simulation Alpha Test Beta Test Training of key people Buy food to bring Launch DITONT Duration (wks) 1 1 0 2 4 8722860 1. Show the Critical Path. Give reasons for your answer. 2. If you needed to shorten the duration of the project, which activity or activities would you shorten and why?arrow_forwardDevelop a spreadsheet for question. What would your recommendation be if the weight for the safety went down to 10 and the weight of profitability went up to 25?arrow_forward
- Quantitative Methods II - Question 1B. Please answer 1, ii, iii. Thank youarrow_forwardCorporate triple-A bond interest rates for 12 consecutive months follow. (a) Construct a time series plot. 11.01 10.5 10.0 9.5- FEFE 9.0- 8.5 8.0 7.5- 2 1 4 11.01 5 10.5 3 6 10.0 7 9.6 9.3 9.4 9.6 9.9 9.8 9.8 10.6 10.0 9.7 9.7 9.6 What type of pattern exists in the data? O The data appear to follow a seasonal pattern. O The data appear to follow a cyclical pattern. O The data appear to follow a horizontal pattern. O The data appear to follow a trend pattern. 8 Month 9 10 9.5 11 9.0 12 8.5 8.0 7.5 7.0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Month (b) Develop three-month and four-month moving averages for this time series. (Round your answers to two decimal places.) Time Series Value 3-Month Moving Average Forecast 4-Month Moving Average Forecast 9.6 9.3 9.4 9.6 9.9 9.8 9.8 10.6 10.0 9.7 9.7 9.6 | | [ | Ⓒ L 11.0 T T 들 10.5 10.0- 9.5 9.0 8.5 8.0 7.5 7.0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Month 0° 7.0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Month Does the three-month or four-month moving average provide more…arrow_forwardQuantitative Methods II - Question 1A. Please answer 1, ii, iii, iv. Thank youarrow_forward
- Project Implementation Plan for Culinary Tourism. • You will be creating a Project Implementation Plan for the new service to be offered by your team/group • Step 4 - Outline of Deliverables - Deliverables are the tangibles of your company. Outlining the deliverables, you hope to create can serve as a resource. This will include time frames/ due dates for ensuring the product/ service is brought to the market. For example - you can use the GANTT CHART for this part (GANTT chart helps teams to plan work around deadlines and properly allocate resources). You are also required to assign tasks for team members for which they would be accountable, and allocate resources for each input required. Kindly prepare a Conclusion for Culinary Tourism State main points and way forward in the future. Synthesize the entire paper with specific details as included in the paper No new information is included in the conclusionarrow_forward1. Identify three negative impacts of pandemic in the production of events and explain each challenge.2. What do you think are the challenges on turning projects into virtual? Cite three challengesarrow_forwardPOLITICAL ECONOMIC Starbucks Coffee SOCIAL TECHNOLOGICAL v. (A) Assimilation: Activity 4 for Week 4 Direction: Draw your answer on a piece of bond paper and take a picture of it and upload the picture on the Google Classroom. 1. Construct a PEST analysis of 1 small business that you see around you. Rubric for PEST analysis Grading VACTORS HIGH PROFICIENCY LACKS SOME PROFICIENCY Gave at least 4 Political factors but did not explain factors and did not PROFICIENCY PROFICIENCY Did not include any Political POLITICAL Included at least 4 Included Political Political factors and emphasized how each element factors but only emphasized how 2-3 of the elements each one or the affect the business impact they have environment of the on doing business community. understand how affects conducting business in the community they affect the business environment in the in the community. community, Included at least 4 Included Economic Gave at least 4 Economic factors ECONOMIC Did not include factors…arrow_forward
- Clean handwriting answer it okkk must handwriting thanks. Don't use chat gpt answers okk I use chat gpt there all answers wrong .pre calculusarrow_forwardMangement question "Planning is doing the work to obtain goals." Do you approve in full? Justify your response in detail.arrow_forwardQ1 (b). You are directed to design a Hierarchical Task Analysis (HTA) for the following scenario, Plans and types of Plan should be mention separately, An Accident occurred somewhere and the security officials were trying to conduct an investigation of the accident. They initially collected the evidence and after making analysis and integrating the facts some conclusions were drawn. Some recommendations were aligned after validation. However in order to collect the evidence the official need to visit the site and the evidence after identification must be preserved. Along with the evidence witness collection and interviewing those witnesses is very important. And the integrated information is reviewed. Moreover, interviewing a witness needs a proper place. The officials can provide a meeting room and let the witness explain the incident details. Officials must ask some open ended questions that must ensure 5Ws (What, Where, Who, When, Why) and 1H (How).arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.