If partway through the project we discover that more money has actually been spent to that point than was planned:
we do not know if the situation is good or bad until we examine earned value
|
||
we know the project is in trouble because there is a cost overrun
|
||
we know we are ahead of
|
||
we know the project is in trouble because there is a budget shortfall
|
||
we should attempt to convince management to cancel the project immediately
|
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Similar questions
- The most complex form of the project termination process is? Extinction Addition Integration Starvation Motivationarrow_forwardAll of the following represent the purpose of the project schedule BEFORE the project starts, EXCEPT: (multiple answers can be picked) To create 'what-if' scenarios to analyze alternatives To force detailed thinking To identify the critical path To identify the needed resources To identify who needs to do what and when To keep track of the budget for the project To show the project status To establish the timeframe and organize activities 0000000arrow_forwardYou are a project manager for a project in the execution phase that is on schedule and on budget. Your sponsor asks you for a project status update. What information about your project would you want to include in an update and explain why you picked each.arrow_forward
- If it is a project at work, that means meeting with your boss and/or relevant parties. . 2) Conduct a 'needs analysis' for the projectarrow_forward1. Which of the following is NOT an objective of the Monitor Risks process? a. Determine if implemented risk responses are effective b. Project assumptions are still valid c. Determine if risk management policies are being followed d. Determine methods to eliminate all residual risksarrow_forwardYou are managing a software development project. Only 35% of the work has so far been completed, while the planned schedule called for 50% completion by this date. Originally budgeted for $250,000, the team has already spent $150,000 on the project. What is the best way to describe the state of this project? Ahead of schedule, within budget Behind schedule, within budget Ahead of schedule, over budget Behind schedule, over budgetarrow_forward
- Part of monitoring a project as well as closing a project is to assess the project team's performance. In your opinion, why is it necessary for the project manager to assess the performance of both the individual team members and the project team as a whole? Is it necessary to assess both? Provide your opinion and support your answer with an explanation.arrow_forwardConsider a situation where an urgent IT project is nearing completion, and it is becoming clear to the Project Manager that many of the users of the new system are not pleased about the changes this will cause. Many attempts have been made to explain why the changes are necessary, but the users remain unconvinced – they feel the training has been inadequate, the new system is confusing, and their job descriptions appear to be significantly different as a result. The Project Manager has reported to the Project Steering Committee that resistance seems likely, and this will further delay full implementation at a time of urgency. It is decided that those users who engage with the new system and get through the urgent work will be offered a one-off bonus in their pay once the urgency has passed. Which one of the following best describes this change strategy? Normative-re-education approach Rational-empirical approach Environmental-adaptive approach…arrow_forwardWhat is programme management? O A. Defining all work that needs to be done to achieve all project deliverables O B. The management of projects exploiting synergies across projects in order to reduce overall costs O C. The management of projects or programmes and other work with a common strategic business purpose O D. The application of knowledge, skills, tools and techniques to satisfy stakeholder expectations from a project.arrow_forward
- Talk about the four different ways an organization that's working on a project might deal with or lessen the impact of risk in a certain circumstance.arrow_forwardOffice Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Activity A B с D E F Description Plan needs Order equipment Install equipment Set up training lab Conduct training course Test system Immediate Predecessor A B A D C, E Time (weeks) Normal Crash 10 8 10 7 10 3 6 7 6 8 3 Cost ($1,000s) Normal 30 120 100 40 50 60 Crash 70 150 160 50 75arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.