Question

Why might a contractor prefer having liquidated damages in a contract (rather than no provision for liquidated damages)?

Contractors prefer to pay at the beginning of a project rather than at the end.
Liquids generally don’t cause much damage.
Liquidated damages reduce the likelihood of litigation in the event of late completion
Liquidated damages are accompanied by bonuses for early completion.
Contractors usually can avoid paying them by documenting problems during the project.
Expert Solution
Check Mark
Step 1

Liquidated damages will be considered to be a penalty if they are extravagant or oppressive in relation to the conceivable loss the owner would suffer from late completion. If liquidated damages are found to be a penalty, a Court will compensate the owner based on its actual losses.

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.