Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows:
Activity | Activity Description | Immediate Predecessor | Activity time (days) |
---|---|---|---|
A | Identify Client Base | ― | 33 |
B | Develop Client Prospectus | ― | 21 |
C | Perform Design Analysis | ― | 35 |
D | Program Back End | A, B, C | 47 |
E | Program Front End | A | 13 |
F | Project Consolidation | D, E | 11 |
(a) For the given project, fill in the nodes of the network diagram below.
A | E | |||||||||||||
33 | 13 | |||||||||||||
Start | B | D | F | Finish | ||||||||||
Time | 21 | 47 | 11 | Time | ||||||||||
C | ||||||||||||||
35 |
(b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns.
Activity | Earliest Start (ES) | Latest Start (LS) | Earliest Finish (EF) | Latest Finish (LF) | Slack (LS-ES) | Critical Path? | ||||||||
A | ||||||||||||||
B | ||||||||||||||
C | ||||||||||||||
D | ||||||||||||||
E | ||||||||||||||
F |
(c) Using parts (a) and (b), determine the critical path.
If you get more than one critical path, please select the upper one. For example, if you have found the paths A-E-F and C-D-F, then you should select A-E-F.
The critical path is −- −-
(d) The project completion time is days.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 4 steps with 3 images
Knowledge Booster
Similar questions
- Activity time estimates for a production line design & implementation project at the CBA factory are as follows: Activity Time (in days) Immediate predecessors A 60 --- B 72 --- C 50 A D 60 B, C E 45 B, C F 77 D G 40 E, F Find early start, early finish, late start, and late finish times for every activity.arrow_forwardPaul Silver, owner of Sculptures International, just initiated a new art project. The following data are available for the project: Activity Time (days) Activity ABCDE 43424 Immediate Predecessor(s) | | < C, Darrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activir immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A 3 D. B 10 E A, D G E, F 10 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = days. d) Slack time for each of the activities is: Activity Slack Time A B F Garrow_forward
- A T= 4 T= 3 F T= 3 T= 3 D E G T= 1 T= 2 T= 2 The network diagram of a project along with the activity durations (T) is given in the figure. Which activities form one of the critical paths? @orsdemir. Copyrighted Content. Cannot be posted. CDEG O ABF О СВF O CF O None of thesearrow_forwardIMPORTANT NOTE: All Project Management Questions are from the same Project. You only need to solve the project one time. The CEO of Carol O'Lights Manufacturing, produces custom-built relay devices for auto makers. The most recent project undertaken by Ms. O'Ligi requires 11 different activities. The activities necessary to build an experimental relay model and related data are given in the following table. What is the Late Finish on Activity A? ACTIVITY DESCRIPTION PREDECESSOR A B C 0000000 D 7 E F G H 1 J K 10 11 12 13 14 Order new Machinery Plan new physical layout Determine safety changes in existing machinery Receive equipment Hire new employees Make plant alterations Make changes in existing machinery Train new employees Install new machinery Relocate old machinery Conduct employee safety orientation C B, D A, E E F, G F, G D H, I, J TIME (WEEKS) 6 4 2 1 4 10 2 6 11 16 8arrow_forwardConstruction of a building is based on the followingCPM network:a. Draw the network for this project and label theactivities.b. What are the normal project completion time and normal cost?c. Identify the critical path.d. How much will it cost to crash the project completion by one day? by two days?e. What is the minimum time for project completion?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.