Weathereye, Inc. manufactures weather satellites. The final assembly and testing of the satellites is a largely manual operation involving dozens of highly trained electronics technicians. The following learning curve has been estimated for the firm’s newest satellite model, which is about to enter production.
Required:
1. What will be the average labor time required to assemble and test each satellite when the company has produced four satellites? Eight satellites?
2. What will be the total labor time required to assemble and test all satellites produced if the firm manufactures only four satellites? Eight satellites?
3. How can the learning curve be used in the company’s budgeting process? In setting cost standards?
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 2 images
how to calculate average labor time?
how to calculate average labor time?
- The production department is proposing the purchase of an automatic insertion machine. It has identified three machines and has asked the accountant to analyze them to determine which one has the best average rate of return. Line Item Description Machine A Machine B Machine C Estimated average income $47,060.44 $72,961.50 $73,785.60 Average investment 336,146.00 243,205.00 491,904.00 a. Machine C b. Machine A c. Machines B and C have the same preferred average rate of return. d. Machine Barrow_forwardBoardman Gases and Chemicals is a supplier of highly purified gases to semiconductor manufacturers. A large chip producer has asked Boardman to build a new gas production facility close to an existing semiconductor plant. Once the new gas plant is in place, Boardman will be the exclusive supplier for that semiconductor fabrication plant for the subsequent 10 years. Boardman is considering one of two plant designs. The first is Boardman's "standard" plant which will cost $38.8 million to build. The second is for a "custom" plant which will cost $53.4 million to build. The custom plant will allow Boardman to produce the highly specialized gases required for an emergency semiconductor manufacturing process. Boardman estimates that its client will order $12.8 million of product per year if the standard plant is constructed, but if the custom design is put in place, Boardman expects to sell $17.1 million worth of product annually to its client. Boardman has enough money to build…arrow_forwardYour firm has acquired a bag of 29 pills of the cognitive-enhancing, nootropic drug called NZT-48. This has opened up four new potential projects for your firm that would not be possible with only your regular unenhanced employees’ feeble meatbag brains. Each project is non-repeatable and of equal time. You have calculated the NPV of each project as well as the requested number of NZT-48 pills by each project’s exploratory team: Project Codename NPV Pills Requested Commodus $42,800 14 Caligula $70,500 20 Nero $24,150 5 Elagabalus $72,200 19 Assume that you can do partial projects whereby you can allocate less pills than the number requested by the team. This would give you a pro-rata portion of that project’s NPV (i.e. the amount of pills you allocate as a proportion of the number requested). The maximum total NPV your firm can achieve through allocating its 29 NZT-48 pills across these four projects is $$.(Round up to the nearest dollar)arrow_forward
- The following scenario relates to 5 questions. Bear Co has developed a new model of television. The estimated labour time for the first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight units produced Note: The learning index for a 75% learning curve is -0.415. Overhead production costs must be estimated based on a previous model, the Leonardo, that was made by Bear Co. Production quantities and total overhead costs for the last four months of production of the Leonardo were as follows: Month Output Total overhead cost (units) $ September 1,800 278,200 October 2,000 310,000 November 1,700 252,900 December 200,000 1,000 You have been asked to estimate the variable overhead cost per unit of the new television by assuming that it will be the same as for the Leonardo, using the information provided for the last four months of its manufacture, and applying a 6% inflation rate. What is the variable cost per unit using the high-low method (to two decimal…arrow_forward38. A start-up company, Macrotech, plans to produce a device to translate Morse code to a written message on a home computer and to send written messages in Morse code over the airwaves. The device is primarily of interest to ham radio enthusi- asts. The president, Ron Lodel, estimates that it would require a $30,000 initial investment. Each unit costs him $20 to produce and each sells for $85. a. How many units must be sold in order for the firm to recover its initial investment? b. What is the total revenue at the break-even volume? c. If the price were increased to $100 each, find the break-even volume.arrow_forwardYou are a head of division in Kinetic Robotics Ltd, a large robotics company, and your team has put together a project proposal to develop a new home robot. The expected NPV of the project is $17.7 million, and the project will require 50 engineers. Your division has a total of 190 engineers available, and the project must compete with the following other projects for these engineering resources:arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education