Assume that Jeff Heun has reviewed his workschedule and decided that it makes sense to complete this project on time. Assuming that he now believes that the probability for completing the project on time is 90% and otherwise it will be finished 1 week late, determine the transaction price. Transaction price
Q: Use the following for the next 2 questions: A facility is to be built with construction costs of…
A: Variable cost means the cost which vary with the level of output and fixed cost means the cost which…
Q: A precision lathe costs $11,300 and will cost $26,500 a year to operate and maintain. If the…
A: Here, Lathe Costs is $11,300 Operation and Maintenance Cost is $26,500 Time Period is 4 years…
Q: An analyst predicts that an 80 percent experience curve should be an accurate pre- dictor of the…
A: The cost of producing the unit can be find out by using the following formula: Y(u) = au-b where, a…
Q: You are the project manager for kpl project and since you don’t sleep much, you get a lot of roject…
A: The investment in the project involves the cost and return factor. The investor compares the cost…
Q: Old Southwest Canning Co. has determined that any one of four machines can be used in a certain…
A: a.
Q: Given a project with the following characteristics, answer the following questions: You are the…
A: As per our protocol we provide solution to one question only or in case of sub-parts then first…
Q: The market values and M&O costs associated with a presently owned machine and a possible…
A: Deciding whether the asset will be replaced with the other asset or not is known as replacement…
Q: a) Laser beams are being used in a large construction project to achieve the exact alignment of…
A: MARR = 15% N = 4 years
Q: Your manager has asked you to advise your client Kofi Gyato, owner and director of Kofi Gyato…
A: Depreciation means the amount of expenses due to usage of fixed assets due to normal wear and tear…
Q: Annual Ashley Foods, Inc. has determined that any one of five machines can be used in one phase of…
A: Calculation of PVAF for all machines Annual Operating Cost, $ per year: Machine PVAF (20%,4…
Q: You and your team are continuing your work on the Global Treps Project. Your project sponsor, Dr. K.…
A: The project costs are capitalized costs that are incurred after initiating or after a successful…
Q: A new biomaterial used for prosthetic devices was developed by engineers in the laboratory that…
A:
Q: mahager of a considering whetner to produce a product vould require leasing some special equipment…
A: The question is based on the concept of calculation of production profit. The production profit is…
Q: determine the total equivalent cost in present worth at an interest rate of 10%.
A: Total Equivalent Cost = Initial Payment + Present Value of Future Payments Present Value of Future…
Q: A new project being considered by BLW Co would require 1,000 hours of skilled labour. The current…
A: We have the following information: A new project being considered by BLW Co would require 1,000…
Q: A project has cost $50,000. The project is scheduled to complete three months from now and is…
A: Sunk cost is a cost which has already being incurred and cannot be recovered. For a continuing…
Q: Assume that Jeff Heun has reviewed his work schedule and decided that it makes sense to complete…
A: Answer Suppose work contract is amount to $ 200,000 And bonus is $ 40,000 , if one week is later…
Q: A mixing process has an estimated first cost of $200,000. Income is expected to be $78,000 per year.…
A: First cost = $ 200,000 Annual income = $ 78,000 MARR = 20%
Q: In a new, highly automated factory, labor costs are expected to decrease at an annual rate of 5%;…
A: The value of labor, material and energy costs during the fifth year are $2,443,518.75, $2,524,953.92…
Q: A production company is planning to open up another manufacturing setup in order to cope up with…
A: A study that proves that the future worth of the money is lower than its current value due to…
Q: Lockwood Company would like to purchase a production machine for $900,000. The machine is expected…
A: Here, Purchase Cost of Machine is $900,000 Life of Machine is 5 Years Salvage Value of Machine is…
Q: You are evaluating a product for your company. You estimate the sales price of product to be $150…
A: Excel computation of year 2 cash flow:Hence, the cash flow for the year 2 is $922,655.Answer: Option…
Q: A construction firm is considering establishing an engineering computing center. The center will be…
A: Given annual operating and maintenance cost for each workstation is $25,000 MARR = 15% Service life…
Q: You need to select a machine for the robotized welding process at your factory. There are two…
A: The net present value is the difference between the present value of cash inflows and the present…
Q: In evaluating projects, LeadTech’s engineers use a rate of 15%. One year ago a robotic transfer…
A: EUAC stands for Equivalent Uniform Annual Cost. The annual uniform series of payment which can…
Q: A metallurgical engineer is considering the two ceramics estimated below for use in a…
A: Present Worth(PW) is worth of proposed investment in current point of time. It is computed by…
Q: You have been asked to determine the most fınancially advantageous option for a new Product…
A: The question is based on the calculation of annual worth for long term investment. Annual worth is…
Q: Two different copying machines are being considered in your company. The Mortar copier would be…
A: The capital budgeting is a technique that helps to analyze the profitability of the project.
Q: You are constantly trying to save your company some money. One decision you encounter is a make or…
A: There are two methods, make or buy decisions. The break-even point (in months) is the number of…
Q: A Facility Manager is evaluating the installation of Invert current non inverter type). The cost of…
A: Pay back period is period required to recover initial amount of investment and normally should be…
Q: You are considering developing 2 buildings (32 units each) on a 4-Acre lot (2-Acre waterfront,…
A:
Q: A design engineer must select the horsepower for a motor to drive a pump. Horsepower rating is a…
A: The cost function is a measure for determining the minimum cost that should be incurred to produce a…
Q: You are evaluating a project for your company. You estimate the sales price to be $580 per unit and…
A: Calculation of Change in NWC at the end of Year 1:The change in NWC at the end of year 1 is…
Q: You are evaluating a project for your company. You estimate the sales price to be $380 per unit and…
A:
Q: Your IT company is working on a four-month project for a local mining company. The total planned…
A: Earned value calculation is done in order to determine the performance of the project. It is used to…
Q: You are the project manager for kpl project and since you don’t sleep much, you get a lot of roject…
A: Project Cost = GH¢ 575,000 Cash inflows per quarter for 2 years = GH¢ 25,000 Cash Inflows per…
Q: The Engineers in a certain company are considering introducing a new product line. The initial…
A: NPV is the net current worth of cash flows that are expected to happen in the future.
Q: A new manufacturing facility will produce two products, each of which requires a drilling operation…
A: Given data Total hour of operation, r = 2000 hours per year Machine availability of machine D, . 80%…
Q: erating cost
A:
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
- On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million. The promise to transfer the warehouse is determined to be a performance obligation. The contract states that if the warehouse is usable by November 30, 2019, Elkhart will receive a bonus of 600,000. For every week after November 30 that the warehouse is not usable, the bonus will decrease by 150,000. Elkhart provides the following completion schedule: Required: 1. Assume that Elkhart uses the expected value approach. What amount should Elkhart use for the transaction price? 2. Assume that Elkhart uses the most likely amount approach. What amount should Elkhart use for the transaction price? 3. Next Level What is the purpose of assessing whether a constraint on the variable consideration exists?Jeff Heun, president of Ayayai Always, agrees to construct a concrete cart path at Dakota Golf Club. Ayayai Always enters into a contract with Dakota to construct the path for $195,000. In addition, as part of the contract, a performance bonus of $44,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $11,000 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 50% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 20% probability that he will be 2 weeks late. Determine the transaction price that Ayayai…Jeff Heun, president of Concrete Always, agrees to construct a concrete cart path at Dakota Golf Club. Concrete Always enters into a contract with Dakota to construct the path for $200,000. In addition, as part of the contract, a performance bonus of $40,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,000 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. Instructions a. Determine the transaction…
- Jeff Heun, president of Bridgeport Always, agrees to construct a concrete cart path at Dakota Golf Club. Bridgeport Always enters into a contract with Dakota to construct the path for $181,000. In addition, as part of the contract, a performance bonus of $39,600 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $9,900 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 60% probability that he will complete the project on time, a 25% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. (a) Determine the…Jeff Heun, president of Wildhorse Always, agrees to construct a concrete cart path at Dakota Golf Club. Wildhorse Always enters into a contract with Dakota to construct the path for $233,000. In addition, as part of the contract, a performance bonus of $42,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,700 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. a.) Determine the transaction…John William, president of Crane Always, agrees to construct a concrete cart path at Windsor Golf Club. Crane Always enters into a contract with Windsor to construct the path for $212,000. In addition, as part of the contract, a performance bonus of $46,800 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $11,700 per week for every week beyond the agreed-upon completion date. John has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. John estimates, given the constraints of his schedule related to other jobs, that there is 50% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 20% probability that he will be 2 weeks late. Determine the transaction price that Crane…
- Jeff Heun, president of Pina Always, agrees to construct a concrete cart path at Dakota Golf Club. Pina Always enters into a contract with Dakota to construct the path for $184,000. In addition, as part of the contract, a performance bonus of $36,400 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $9,100 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. Determine the transaction price that Pina…Jeff Heun, president of Flounder Always, agrees to construct a concrete cart path at Dakota Golf Club. Flounder Always enters into a contract with Dakota to construct the path for $232,000. In addition, as part of the contract, a performance bonus of $41,600 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $10,400 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. (a) Determine the transaction price that…Jeff Heun, president of Larkspur Always, agrees to construct a concrete cart path at Dakota Golf Club. Larkspur Always enters into a contract with Dakota to construct the path for $191,000. In addition, as part of the contract, a performance bonus of $48,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $12,000 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 55% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 15% probability that he will be 2 weeks late. Determine the transaction price…
- Jeff Heun, president of Flint Always, agrees to construct a concrete cart path at Dakota Golf Club. Flint Always enters into a contract with Dakota to construct the path for $238,000. In addition, as part of the contract, a performance bonus of $34,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,500 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 50% probability that he will complete the project on time, a 25% probability that he will be 1 week late, and a 25% probability that he will be 2 weeks late.ssume that Jeff Heun has reviewed his work schedule…Joseph Taylor, president of Carla Vista Always, agrees to construct a concrete cart path at Vaughn Golf Club. Carla Vista Always enters into a contract with Vaughn to construct the path for $202, 000. In addition, as part of the contract, a performance bonus of $46, 400 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed - upon date. The performance bonus decreases by $11,600 per week for every week beyond the agreed - upon completion date. Joseph has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Joseph estimates, given the constraints of his schedule related to other jobs, that there is 50% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 20% probability that he will be 2 weeks late. Assume that Joseph Taylor…Marin Construction Inc. agrees to construct a boat dock at the Smooth Sailing Marina for $32,400. In addition, under the terms of the contract, Smooth Sailing will pay Marin a performance bonus of up to $12,000 based on the timing of completion. The performance bonus will be paid fully if construction is completed by the agreed-upon date. The performance bonus decreases by $2,400 per week for every week beyond the agreed-upon completion date. Marin has constructed a number of boat docks under similar agreements. Marin’s management estimates, that it has a 60% probability of completing the project on time, a 20% probability of completing the project one week late, and a 20% probability of completing the project two weeks late. Management does not believe the project will be more than two weeks late.Determine the transaction price that Marin should compute for this agreement.