Work Performance Data: End of Day Oct 3/11 Duratio Task Name System Installation System Analysis 10 System Design 20 System Developme 30 System Testing 5 System Deploymen 5 Project Complete 0 a) $900 +-10 Ob) -$900 +-10 n (days) 70 c) None of these d) $3.500 +-10 Start Aug 1/11 Aug 1/11 Aug 9/11 Aug 23/11 Oct 4/11 Oct 10/11 Oct 17/11 Finish Oct 17/11 Aug 12/11 Sept 5/11 Oct 3/11 Oct 10/11 Oct 17/11 Oct 17/11 Planned Actual Value $9,000 % Cost Complete $3,500 48.9% D'Arcy is managing a software development project. The Work Performance Report above, shows the project schedule and current performance information. What is the current CV for D'Arcy's project? A $500 $700 $1,000 $800 $2,000 $6,000 $1,000 $500 88 100.0% 90.0% 50.0% 0% 0%

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

KA

Work Performance Data: End of Day Oct 3/11
Duratio
Task Name
System Installation
System Analysis
10
System Design
20
30
System Developme
System Testing
5
System Deploymen 5
Project Complete 0
a) $900 +-10
Ob) -$900 +-10
n (days)
70
c) None of these
d) $3.500 +-10
Start
Aug 1/11
Aug 1/11
Aug 9/11
Aug 23/11
Oct 4/11
Oct 10/11
Oct 17/11
Finish
Oct 17/11
Aug 12/11
Sept 5/11
Oct 3/11
Oct 10/11
Oct 17/11
Oct 17/11
D'Arcy is managing a software development project. The Work Performance Report
above, shows the project schedule and current performance information. What is the
current CV for D'Arcy's project?
Planned Actual
%
Value Cost Complete
$9,000 $3,500
48.9%
$500 $700
$1,000 $800
$6,000
$2,000
$1,000
$0
$500
$0
100.0%
90.0%
50.0%
0%
0%
Transcribed Image Text:Work Performance Data: End of Day Oct 3/11 Duratio Task Name System Installation System Analysis 10 System Design 20 30 System Developme System Testing 5 System Deploymen 5 Project Complete 0 a) $900 +-10 Ob) -$900 +-10 n (days) 70 c) None of these d) $3.500 +-10 Start Aug 1/11 Aug 1/11 Aug 9/11 Aug 23/11 Oct 4/11 Oct 10/11 Oct 17/11 Finish Oct 17/11 Aug 12/11 Sept 5/11 Oct 3/11 Oct 10/11 Oct 17/11 Oct 17/11 D'Arcy is managing a software development project. The Work Performance Report above, shows the project schedule and current performance information. What is the current CV for D'Arcy's project? Planned Actual % Value Cost Complete $9,000 $3,500 48.9% $500 $700 $1,000 $800 $6,000 $2,000 $1,000 $0 $500 $0 100.0% 90.0% 50.0% 0% 0%
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.