You are in charge of the new project at work which is
|
|
|
Time (in weeks) |
||
Activity |
Description |
Immediate Predecessor |
Optimistic |
Most Probable |
Pessimistic |
A |
Meet with board |
------ |
1 |
3 |
5 |
B |
Hire staff |
A |
4 |
6 |
8
|
C |
Brian storm |
A |
1 |
2 |
3
|
D |
Write up proposal |
B, C |
2 |
3 |
4 |
E |
Pitch proposal at meeting |
B, C |
2 |
4 |
6 |
F |
Revise Proposal |
A |
2 |
3 |
4 |
G |
Pitch proposal to Board |
D |
1 |
2 |
3 |
H |
Await Board decision |
E, G |
2 |
4 |
6
|
I |
Implement plan |
H, F |
2 |
2 |
2 |
a) What is the critical path?
b) What is the project expected time?
c) What is the probability of completing in 19 weeks?
d) What is the probability of completing in 21 weeks?
Trending nowThis is a popular solution!
Step by stepSolved in 4 steps with 4 images
d) What is the probability of completing in 21 weeks?
d) What is the probability of completing in 21 weeks?
- Issues in project management include a. level of effort. b. period of performance. c. budget. d. all of the above. e. a and c only.arrow_forwardAppendix A: Project Management Plan Approval Signature: Date: Print Name: Title: Role: I am making a project management plan and I am confused what the difference between title and role are.arrow_forwardwoody 2000 project Communication and People Management a. Draw a project organization chart. What were the real relationships? b. Should Leadbetter have been left to run the project? Would training have helped? c. How should the Woody 2000 project plan be communicated and when? d. What communication (coordination) would you expect to see during execution?arrow_forward
- Don't use AI PERT and CPM are NOT used in which phase of project management? A Controlling B. Planning C. Scheduling D. PERT and CPM are used in all three phases GIVE CORRECT ANSWER WITH FULL EXPLANATIONarrow_forwardWhat are the main characteristics of a Project? a. Budget, Scope, Schedule, Change Management b. Focused on IT, Engineering, Risk Management c. All of the options listed d. Broad, exceed one year in duration, operational e. Unique, Specific Deliverables, Specific due date..arrow_forward28 The beta distribution is used in project management to: Select one: a. calculate pessimistic and optimistic activity times. b. calculate slack on activities not on the critical path. c. calculate the probability that a project will be completed within its budget. d. determine which activity should be crashed. e. none of thesearrow_forward
- One of Mary's employees, Shira, has obtained a new job and given her two weeks' notice. Shira was responsible for updating the company website with information on the new bag policy. Mary gave Shira's responsibilities to another employee in the Marketing department who has similar knowledge and skills.What is the probability of this risk occurring and what is the impact on the project? a.) Low probability and medium impact b.) High probability and high impact c.) Medium probability and low impact d.) High probability and low impactarrow_forwardNote:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardDuring the __________ stage of the project lifecycle, there is no significant difference in the importance that project managers place on the three goals of cost, time, and scope. a. phaseout b. main c. buildup d. formationarrow_forward
- Directed reading "what it takes to be a good project manager". What are the three most critical skills for project management according to a study in "What it takes to be a good project manager"?arrow_forwardi. Give your own example of WBS in Chart Form. ii. Represent the contents of a project charter with your own example. iii. Discuss the “Project Integration Management”. iv. Discuss the Processes Project Scope Management.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.