Act. Dur. 5-10 A 5-15 B 7. 10-20 C 2. 10-25 E 15-30 F 21 20-35 G 25-35 H 12 30-40 I 10 35-50 K 25-50 I 40-45 L 45-50 M 15-25 D1 25-40 D2 Find total duration to finish the project And find critical path By AoA method 3:33 PM /

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter8: Intersection Control
Section: Chapter Questions
Problem 19P
icon
Related questions
Question
Act.
Dur.
5-10 A
5-15 B
7.
10-20 C
2.
10-25 E
15-30 F
20-35 G
25-35 H
12
30-40 J
10
35-50 K
25-50 I
40-45 L
45-50 M
15-25 D1
25-40 D2
Find total duration to finish the project And find critical
path By AoA method
3:33 PM /
Transcribed Image Text:Act. Dur. 5-10 A 5-15 B 7. 10-20 C 2. 10-25 E 15-30 F 20-35 G 25-35 H 12 30-40 J 10 35-50 K 25-50 I 40-45 L 45-50 M 15-25 D1 25-40 D2 Find total duration to finish the project And find critical path By AoA method 3:33 PM /
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Advanced framing techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning
Residential Construction Academy: House Wiring (M…
Residential Construction Academy: House Wiring (M…
Civil Engineering
ISBN:
9781337402415
Author:
Gregory W Fletcher
Publisher:
Cengage Learning