Question

What is the probability that the simple project will be completed in 29 days? and How long will it take for the project to most probably complete?

Situation: A project has a critical path of 1-2-3-4-5. In the parentheses are the probabilistic
durations of each activity: 1-2 (4,6,8), 2-3 (7, 10, 14), 3-4 (3, 7, 12), 4-5 (5, 9, 13). *Given
durations are in days.
expand button
Transcribed Image Text:Situation: A project has a critical path of 1-2-3-4-5. In the parentheses are the probabilistic durations of each activity: 1-2 (4,6,8), 2-3 (7, 10, 14), 3-4 (3, 7, 12), 4-5 (5, 9, 13). *Given durations are in days.
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Text book image
Structural Analysis
Civil Engineering
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:Cengage,
Text book image
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Text book image
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Text book image
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning