a. Rattan commenced a contract to build an asset for a customer in the year ended 30 September 20X4. The contract price was agreed at £1.5 million, and the total expected costs of the contract are £800,000. Rattan will satisfy the performance obligations over time. The following figures are relevant in relation to this contract for the year ended 30 September: C. Costs incurred to date Work certified to date b. £320,000 Rattan recognises progress on the basis of work certified compared to contract price. Question 10Select one: What should Rattan include in its statement of profit or loss for the year ended 30 September 20X5 for cost of sales in respect of the contract in accordance with IFRS 15 'Revenue from Contracts with Customers'? £560,000 d. 20X4 20X5 £'000 £'000 £250,000 325 575 450 1,050 £240,000

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 16RE
icon
Related questions
Question
a.
Rattan commenced a contract to build
an asset for a customer in the year
ended 30 September 20X4. The
contract price was agreed at £1.5
million, and the total expected costs of
the contract are £800,000. Rattan will
satisfy the performance obligations
over time.
The following figures are relevant in
relation to this contract for the year
ended 30 September:
b.
C.
Costs incurred to
date.
Work certified to
date
£320,000
Question 10Select one:
Rattan recognises progress on the
basis of work certified compared to
contract price.
What should Rattan include in its
statement of profit or loss for the year
ended 30 September 20X5 for cost of
sales in respect of the contract in
accordance with IFRS 15 'Revenue
from Contracts with Customers'?
£560,000
d.
20X4 20X5
£'000 £'000
£250,000
325 575
450 1,050
£240,000
Transcribed Image Text:a. Rattan commenced a contract to build an asset for a customer in the year ended 30 September 20X4. The contract price was agreed at £1.5 million, and the total expected costs of the contract are £800,000. Rattan will satisfy the performance obligations over time. The following figures are relevant in relation to this contract for the year ended 30 September: b. C. Costs incurred to date. Work certified to date £320,000 Question 10Select one: Rattan recognises progress on the basis of work certified compared to contract price. What should Rattan include in its statement of profit or loss for the year ended 30 September 20X5 for cost of sales in respect of the contract in accordance with IFRS 15 'Revenue from Contracts with Customers'? £560,000 d. 20X4 20X5 £'000 £'000 £250,000 325 575 450 1,050 £240,000
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning