A construction project is broken down into the following 10 activities: IMMEDIATE PREDECESSOR TIME (WEEKS) 4 2 4 3 5 ACTIVITY 1 2 3 4 5 6 7 8 9 10 1 1 1 2, 3 3 4 5 6, 7 8, 9 b-1. Find the critical path. O1-3-5-8-10 1-3-6-9-10 1-4-7-9-10 1-2-5-8-10 Number of weeks 6 2 3 7 b-2. How many weeks will the project take to complete? c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which of the following options would reduce the project duration by four weeks? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question 998
A construction project is broken down into the following 10 activities:
IMMEDIATE
PREDECESSOR
ACTIVITY
1
2
3
4
5
6
7
8
9
10
1
1
1
2, 3
3
4
5
6, 7
b-1. Find the critical path.
O 1-3-5-8-10
1-3-6-9-10
1-4-7-9-10
1-2-5-8-10
Number of weeks
TIME
(WEEKS)
4
2
4
3
5
6
2
b-2. How many weeks will the project take to complete?
c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of
$10,000 per week, which of the following options would reduce the project duration by four weeks? (You may select more than one
answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with
Transcribed Image Text:A construction project is broken down into the following 10 activities: IMMEDIATE PREDECESSOR ACTIVITY 1 2 3 4 5 6 7 8 9 10 1 1 1 2, 3 3 4 5 6, 7 b-1. Find the critical path. O 1-3-5-8-10 1-3-6-9-10 1-4-7-9-10 1-2-5-8-10 Number of weeks TIME (WEEKS) 4 2 4 3 5 6 2 b-2. How many weeks will the project take to complete? c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which of the following options would reduce the project duration by four weeks? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with
8
9
10
>
6, 7
8, 9
b-1. Find the critical path.
O 1-3-5-8-10
1-3-6-9-10
1-4-7-9-10
O 1-2-5-8-10
b-2. How many weeks will the project take to complete?
Number of weeks
c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of
$10,000 per week, which of the following options would reduce the project duration by four weeks? (You may select more than one
answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with
the question mark to empty the box for a wrong answer.)
?Cut activity 3 by 3 weeks, and then reduce activity 6 or 9 by one week.
?Cut activity 5 by 4 weeks.
?Reduce activities 6 and 9 by a total of 3 weeks, and then reduce activity 3 by one week.
?Cut activity 4 by 3 weeks, and then reduce activity 6 or 5 by one week.
? Cut activity 5 by 3 weeks, and then reduce activity 4 or 9 by one week.
Transcribed Image Text:8 9 10 > 6, 7 8, 9 b-1. Find the critical path. O 1-3-5-8-10 1-3-6-9-10 1-4-7-9-10 O 1-2-5-8-10 b-2. How many weeks will the project take to complete? Number of weeks c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which of the following options would reduce the project duration by four weeks? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) ?Cut activity 3 by 3 weeks, and then reduce activity 6 or 9 by one week. ?Cut activity 5 by 4 weeks. ?Reduce activities 6 and 9 by a total of 3 weeks, and then reduce activity 3 by one week. ?Cut activity 4 by 3 weeks, and then reduce activity 6 or 5 by one week. ? Cut activity 5 by 3 weeks, and then reduce activity 4 or 9 by one week.
Expert Solution
Step 1

Network diagram of given activities: 

Operations Management homework question answer, step 1, image 1

 

 

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.