FINANCIAL ACCOUNTING
10th Edition
ISBN: 9781259964947
Author: Libby
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year
were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue, cost, and gross profit will the company recognize in the first
and second year of the contract applying the cost recovery method that is required by IFRS?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete the project are $5,000,000. Tullis billed $5,000,000 in year 1 and collected $3,100,000 by the end of the end of the year. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of year 1 on the balance sheet assuming the use of the completed - contract method? O A. asset of $2,000,000 O B. liability of $1,900,000 O C. asset of $1,900,000 O D. liability of $2,000,000arrow_forwardShumpert, Inc., entered into a contract that was to take two years to complete, with an estimated cost of $ 1,348,800. The contract price was $1,888,320. Costs of the contract for 2022, the first year, totaled $1,011, 600. If required, round any division to two decimal places and round your final answers to the nearest dollar. a. What was the gross profit reported by the percentage of completion method for 2022? Sfill in the blank 1 b. After the contract was completed at the end of 2023 at a total cost of $1,416, 240, what was the gross profit reported by the percentage of completion method for 2023? Sfill in the blank 2arrow_forwardColorado Inc. constructed a factory during 2020 and 2021 under contract with Pacific Machinery Co. Relevant data are summarized below: Contract price Cost Gross profit Contract billings $3,000,000 2020 1,200,000 2021 600,000 2020 800,000 2021 400,000 2020 1,500,000 2021 1,500,000 Colorado Inc. recognizes revenue over time with respect to this contract. In its December 31, 2020, balance sheet, Colorado would report: ● The contract asset, cost and profit in excess of billings, $500,000. The contract liability, billings in excess of cost, of $300,000. The contract asset, contract amount in excess of billings, of $1,500,000. The contract asset, deferred profit, of $400,000.arrow_forward
- Winett Corporation is considering an investment in special-purpose equipment to enable the company to obtain a four-year municipal contract. The equipment costs $291,000 and would have no salvage value when the contract expires at the end of four years. Estimated annual operating results of the project are as follows. Revenue from contract sales Expenses other than depreciation Depreciation (straight-line basis) Increase in net income from contract work $211,000 72,750 All revenue and all expenses other than depreciation will be received or paid in cash in the same period as recognized for accounting purposes. Compute the following for Winett's proposal to undertake this contract. a. Payback period b. Return on average investment c. Net present value $308,000 283,750 $ 24,250 a. Payback period. b. Return on average investment. (Round your percentage answer to 1 decimal place (i.e., 0.123 to be entered as 12.3).) c. Net present value of the proposal to undertake contract work,…arrow_forward(Recognition of Profit on Long-Term Contract) Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,000 $450,000 $610,000 Estimated costs to complete 330,000 150,000 –0– Progress billings to date 270,000 550,000 900,000 Cash collected to date 240,000 500,000 900,000 Instructions(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.arrow_forwardOn February 1, 2023, Sandhill Contractors agreed to construct a building at a contract price of $3,460,000. The total estimated construction costs would be $1,890,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Gross profit/ (loss) 689,850 1,200,150 1,100,000 1,000,000 2023 2024 573050 $1,162,000 $ 2,365,000 913,000 1,890,000 1,750,000 2025 Calculate the gross profit / (loss) that should be recognized for 2023, 2024, and 2025 using the percentage completion method. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round percentage complete to 1 decimal place, e.g. 15.2% and final answers to O decimal places, e.g. 5,125.) 2024 -0- 3,460,000 2,950,000 -107450 $ LA 2025 40450arrow_forward
- Star Construction Corporation has a contract to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,850,000. Construction commenced on 4 February 20×5. Actual costs were in line with estimated costs for 20×5 and 20×6. In 20×7, actual costs exceeded estimated costs by $150,000. Total construction costs incurred in each year were as follows: 20X5: $2,700,00020X6: $4,500,00020X7: $1,800,000 Progress billings based on the amount of work completed were collected each year. Star Construction uses the percentage-of-completion method. The percentage-of-completion is based on costs incurred compared with estimated total costs of the project. Company also billed the client and collected the following payments Year Billings Payments Received 20X5: $2,300,000 $2,100,000 20X6: $4,900,000 $4,700,000 20X7: $3,750,000 $4,150,000…arrow_forwardPlease help mearrow_forwardLark Corp. appropriately determined that each of its long-term projects represents a single performance obligation that is satisfied over time. At the end of the current year, Lark estimates that its costs to complete a project exceed the contract price, so that an overall loss on the contract is anticipated. Required: What journal entry will Lark record at the end of the current year, given the following information? • Revenue to date is $350,000 ($175,000 of which is to be recognized in the current year). • The expense recognized previously was $100,000. • An overall loss of $30,000 is anticipatedarrow_forward
- A construction company entered into a fixed-price contract to build a soccer stadium for $15,000,000. Construction costs incurred during the first year were $3,675,000, and estimated costs to complete at the end of the year were $6,825,000. The company recognizes revenue over time according to percentage of completion. Fixed-price contract amount: $15,000,000 Construction costs incurred in first year: $3,675,000 Estimated costs to complete at end of first year: $6,825,000 How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract? Percentage of completion at end of first year Revenue Gross profit (loss) Nothing in this area will be graded, but it will be submitted with your assignment.arrow_forwardOriole Construction Company began operations on January 1, 2025. During the year, Oriole Construction entered into a contract with Winds Corp. to construct a manufacturing facility. At that time, Oriole estimated that it would take 5 years to complete the facility at a total cost of $4.484,000. The total contract price for construction of the facility is $5,972,000. During the year, Oriole incurred $1,082,400 in construction costs related to the construction project. The estimated cost to complete the contract is $4,329,600. Winds Corp. was billed and paid 25% of the contract price. (a) Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31, 2025, and the amount to be shown as "costs and recognized profit in excess of billings" or "billings in excess of costs and recognized profit" at December 31, 2025, under each of the following methods. (Enter negative amounts using either a negative sign preceding the number eg.-45 or parentheses…arrow_forwardA construction company entered into a fixed-price contract to build an office building for $42 million. Construction costs incurred during the first year were $12 million, and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? Note: Enter your answers in whole dollars and not in millions (i.e., $4 million should be entered as $4,000,000). Revenuearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education