FINANCIAL ACCOUNTING
10th Edition
ISBN: 9781259964947
Author: Libby
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Question
A Company began a construction project on a building for P3,000,000. The project
was completed during 2020. The accounting records disclosed the following:
Description 2019 2020
Progress billings during the year P1,100,000 P1,900,000
Cost incurred during the year 900,000 1,800,000
Collections on billings during the year 700,000 2,300,000
Estimated cost to complete 1,800,000
What is the balance of construction in progress account at the end of 2020 using
overtime and point-in time method of recording revenue?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- The Leto Construction Company began work on a $15,000 contract on 1/1/22. Planned completion was in 2024. The Percentage-of Completion method is used. Given the following at 12/31/22: Costs incurred to date Estimated costs to complete Billings to date Collections to date December 31, 2022 $2,500 9,500 4,000 3,800 The balance sheet location and the net amount of the 12/31/22 Combined CIP and Billings accounts are: Select one: O a. Current Liability of $1,500 O b. Current Liability of $200 c. Current Asset of $1,500 d. Current Liability of $875arrow_forwardSheridan Construction Co. contracted to build a bridge for $10,500,000. Construction began in 2024 and was completed in 2025. Data relating to the construction are: Costs incurred during the year Estimated costs to complete (a) 2024 $4,095,000 Revenue $ 2,730,000 Sheridan uses the percentage-of-completion method. How much revenue should be reported for 2024? 2025 $2,780,000arrow_forwardKingbird Construction Company began work on a $418,500 construction contract in 2020. During 2020, Kingbird incurred costs of $285,500, billed its customer for $233,000, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $155,765.Prepare Kingbird’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No entry" for the account titles and enter 0 for the amounts. Round answers to 0 decimal places, e.g. 5,275.) No. Account Titles and Explanation Debit Credit (a) enter an account title to record the transaction using the percentage-of-completion method enter a debit amount enter a credit amount enter an account title to record the transaction using the percentage-of-completion method enter a debit…arrow_forward
- McCombs Contractors received a contract to construct a mental health facility for $2,500,000. Construction was begun in 2023 and completed in 2024. Cost and other data are presented below 2023 Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year $ 1,500,000 1,200,000 2024 $ 1,300,000 0 1,200,000 1,000,000 1,300,000 1,500,000 Assume that McCombs recognizes revenue on this contract over time according to percentage of completion. Required: Compute the amount of gross profit recognized during 2023 and 2024, Note: Loss amounts should be indicated with a minus sign. Amount of gross profit (or loss) recognized in 2023 Amount of gross profit (or loss) recognized in 2024arrow_forward1. Prepare a schedule showing the revenue, cost and gross profit earned each year using thepercentage of completion method, using the engineer’s estimate as a measure ofcompletion.2. Prepare all journal entries required to reflect the contract3. Prepare journal entries for 2020 assuming zero profit method is used.arrow_forwardThe Leto Construction Company began work on a $15,000 contract on 1/1/22. Planned completion was in 2024. The Percentage-of Completion method is used. Given the following at 12/31/22: Costs incurred to date Estimated costs to complete Billings to date Collections to dato December 31, 2022 $2,500 9,500 4,000 3,800 The balance sheet location and the net amount of the 12/31/22 Combined CIP and Billings accounts are: Select one: a. Current Liability of $1,500 O b. Current Liability of $200 O c. Current Asset of $1,500 d. Current Liability of $875arrow_forward
- Manson Construction Corp. has consistently used the percentage-of-completion method. In 2020, Manson started work on a $10,500,000 construction contract that was completed in 2021. The following information was taken from Manson’s 2020 accounting records: Billings to date $3,300,000 Costs incurred 3,150,000 Collections to date 2,100,000 Estimated costs to complete 6,300,000 What is the amount of revenue that will be recorded in 2020? In 2020, Pop Construction Corp. began work on a contract for $ 3,700,000. Other details follow: 2020 Costs incurred during the year.................................................................... $ 1,800,000 Estimated costs to complete as of December 31................................... 1,200,000 Billings during the year................................................................................. 1,650,000 Collections during the…arrow_forwardIn 2020, Zeta Construction Corp. began work on a contract for $3,700,000. Other details follow: 2020 Costs incurred during the year $1,800,000 Estimated costs to complete as of December 31 1,200,000 Billings during the year1,650,000 Collections during the year 975,000 Zeta uses the percentage-of-completion method. For calendar 2020, Zeta should report gross profit of?arrow_forwardSalmania Co. began working on a project on August 2019, to construct a BD8,250,000 bridge that is expected to be completed in October 2020, at an estimated cost of BD6,000,000. At the end of 2019, the costs to date were BD2,400,000 and the estimated total costs to complete had not changed. The progress billings during 2019 were BD1,600,000 and the cash collected during 2019 was BD1,475,000. Salmania uses the percentage-of-completion method. What amount would be reported in Construction in Process at December 31, 2019?arrow_forward
- On January 1, 2022, Winter Harvest Ltd. started a construction project for $4,500,000. Relevant data for 2022 and 2023 are as follows: 2022 2023 Current year construction costs $ 3,300,000 $ 620, 000 Estimated remaining costs to complete 600,000 - 0- Current year billings 3, 100, 000 1,400,000 Current year collections 3,000,000 1,500, 000 Required 1. Calculate the following amounts for each method: 2. Completed Contract Percentage of Completion 2022 2023 2022 2023 Gross Profit $ ? $ ? $ ? $ ? Construction in progress year - end balance. $ ? $ ? $ ? $ ? Costs in excess of billi\table[[, \table[[Completed], [Contract]], \table[[Percentage of], [Completion]]], [, 2022, 2023, 2022, 2023], [Gross Profit,$?, $?, $ ?, $?ngs (Billings in excess of costs) $ ? $ ? $ ? $ ?arrow_forwardIn 2021, Montana Corp. entered into a contract to begin work on a two-year project. Montana recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2021 (from construction progress billings) $37.5 $140 Actual construction costs incurred in 2021 Cash collected on project during 2021 $105 Construction in progress, 12/31/2021 $210 Estimated percentage of completion during 2021 Selected Amounts O $70,000,000 What is the amount of gross profit on the project recognized by Montana during 2021? O $60,000,000 $35,000,000 O $105,000,000 50 %arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education