Question
Chapter B, Problem 37P
Summary Introduction
To determine: The mix of class of containers will maximize the weekly profit.
Introduction:
Linear programming:
It is a linear optimization technique followed to develop the best outcome for the linear programming problem. The outcome might be to maximize profit, minimize cost, or to determine the optimal product mix. The outcome will take the constraints present in achieving the solution into consideration.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Sitka Industries uses a cost system that carries direct materials inventory at a standard cost. The controller has established these standards for one ladder (unit):
StandardQuantity
x
StandardPrice
=
StandardCost
Direct materials
3 pounds
$4.50 per pound
$13.50
Direct labor
2.00 hours
12.00 per hour
24.00
Total cost
$37.50
Sitka Industries made 2,900 ladders in July and used 8,500 pounds of material to make these units. Sitka Industries bought 15,400 pounds of material in the current period. There was a $300 unfavorable direct materials price variance.
Enter all amounts as positive numbers.
A. How much in total did Sitka pay for the 15,400 pounds?
B. What is the direct materials quantity variance?
C. What is the total direct materials cost variance?
D. What if 9,200 pounds were used to make these ladders, what would be the direct materials quantity variance?
E. If there was a $340 favorable direct materials price variance, how much did Sitka pay…
In a large microelectronics plant, the assembly cell for circuitboards has a demand for 200 units an hour. Two feeder cellssupply parts A and B to the assembly cell (one A and one Bfor each board). Standard containers that look like dividedtrays are used. A container will hold 20 As or 10 Bs. It takes10 minutes to fill up a container with As and 20 minutes tofill up a container with Bs. Transit time to the assembly cell is5 minutes for both A and B. No safety factor is used. Set up akanban control system for the assembly process.
A company produces and sells
electronic components that are
purchased by computer
manufacturers. The company just
received an order for 3000 circuit
boards that must be delivered to the
customer in 28 days. Shipping takes 4
days and every production run for this
component takes 3 days for any
quantity of circuit boards between
1800 and 4200.
The Bill of Materials (listing the
materials and quantities required to
produce a single circuit board ordered)
is in the table below:
Quantity
Component Required
Input
Bare printed
1
board
Сарacitor
8
Op amp
Resistor
4
Transistor
3.
Chapter B Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
Ch. B - Prob. 1DQCh. B - Prob. 2DQCh. B - Prob. 3DQCh. B - Prob. 4DQCh. B - Prob. 5DQCh. B - Prob. 6DQCh. B - Prob. 7DQCh. B - Prob. 8DQCh. B - Prob. 9DQCh. B - Prob. 10DQ
Ch. B - Prob. 11DQCh. B - Where a constraint crosses the vertical or...Ch. B - Prob. 13DQCh. B - Prob. 2PCh. B - Prob. 3PCh. B - Prob. 25PCh. B - B.4. Consider the following linear programming...Ch. B - Prob. 26PCh. B - Prob. 27PCh. B - Prob. 5PCh. B - Prob. 6PCh. B - Green Vehicle Inc. manufactures electric cars and...Ch. B - Prob. 8PCh. B - Prob. 28PCh. B - Prob. 29PCh. B - The LP relationships that follow were formulated...Ch. B - Prob. 22PCh. B - Prob. 9PCh. B - Prob. 34PCh. B - Prob. 35PCh. B - Prob. 36PCh. B - Prob. 10PCh. B - Prob. 11PCh. B - Prob. 12PCh. B - Prob. 30PCh. B - Prob. 37PCh. B - How many corner points are there in the feasible...Ch. B - Prob. 13PCh. B - Prob. 38PCh. B - Prob. 40PCh. B - Prob. 15PCh. B - Prob. 16PCh. B - Prob. 17PCh. B - Prob. 18PCh. B - Prob. 19PCh. B - Prob. 20PCh. B - Prob. 33PCh. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...Ch. B - Quain Lawn and Garden, Inc Bill and Jeanne Quain...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A tricycle factory uses 3 tires , 1 frame, and 2 pedals . If the factory. has available 270 tires, 90 frames, and 170 pedals , which item would limit the number of complete tricycles that can be assembled ? Explain your choice. A)tires. B) frames C) pedals D) both tires and framesarrow_forwardA company processes feathers and ships them loose in a covered truck. The linehaul cost for an average shipment is $600, and the truck carries 2000 pounds offeathers. A bright new graduate has just been hired and has suggested that theyshould bale the feathers into 500-pound bales. This would make them easier tohandle and also allow them to be compressed into about one-tenth of the space theynow occupy. How many pounds of feathers can the truck now carry? What is thepresent line haul cost per pound? What will it be if the proposal is adopted?arrow_forwardCryolab Inc makes and sells a lawn fertilizer called Hypergro. The company has developed standard costs for one bag of Hypergro as follows: Standard Quantity/Hours Standard Price/Rate Standard Cost per Bag Direct Material 25 pounds ₱ 0.75 ₱18.75 Direct Labor 0.25 hours ₱69.00 ₱17.30 Variable overhead 0.25 hours ₱24.00 ₱ 6.00 Total ₱42.05 The company had no beginning inventories of any kind on January 1. Variable overhead is applied to production on the basis of standard direct labor hours. During January, the following activity was recorded by the company: Production of Fastgro: 23,000 bags Direct materials purchased: 585,000 pounds at a cost of ₱436,250 Direct labor worked: 5,800 hours at a cost of ₱397,300 Variable overhead incurred: ₱140,650 Inventory of direct materials on January 31: 8,000 pounds Compute the variances and indicate whether it is FAVORABLE (F) or UNFAVORABLE (U) in your solution sheet. The raw…arrow_forward
- A warehouse, just outside of Montreal, gets a daily shipment of a USB connector product. The daily demand of this product is 1850. The products are first placed in storage (waiting stage) at the entrance of the warehouse where on average there are 320 products. A Receiving clerk picks the products from storage and verifies them (assure quality stage). It takes the clerk 0.01 days to verify each product. Then the products are sorted and packaged (sorting stage) into three streams: Ottawa (20% of products), Laval (30% of products), and Montreal (50% of products). On average, there are 380 products being sorted. After, three shipping stations load the products into trucks heading to each location respectively (Montreal, Laval, and Ottawa). The loading stage takes 0.004, 0.01 days, and 0.08 days for the destination of Montreal, Laval, and Ottawa respectively for each product (last stage of process). On Average, how many hours does a product spend in the warehouse (assuming 8 hours in a…arrow_forwardBhatti Company produces plastic photo frames. Two departments, molding and finishing, are involved in the manufacturing. The molding department fills the molds with hot liquid plastic that is left to cool and then opens them. The finishing department removes the plastic frame from the mold and strips the edges of the frames of extra plastic. The following information is available for the month of January: January 1 Quantity (pounds) January 31 Quantity (pounds) Work-in-Process Inventory Cost Cost Molding department Finishing department None None 5,000 $ 15,000 2,000 The WIP Inventory in the finishing department is estimated to be 40% complete for conversion both at the beginning and end of January. Costs of production for January follow: Direct Costs of Production Materials Conversion Molding department Finishing department $ 450,000 $ 90,000 80,290 The molding department started 50,000 pounds of product in January. The firm uses the FIFO method of process costing. Required: 1. Prepare…arrow_forwardVGHC, humanitarian aid service in the Sub-Saharan Africa, operates its laboratory on-site. The lab maintains an inventory of test kits for a variety of procedures. VGHC uses 780 A1C kits each year. Ordering costs are $15 and holding costs are $3 per kit per year. The new price list indicates that orders of fewer than 73 kits will cost $60 per kit, 73 through 144 kits will cost $56 per kit, and orders of more than 144 kits will cost $53 per kit. Determine the optimal order quantity and the total cost.arrow_forward
- As a logistics specialist, you are responsible for meeting customer demand. One of your customers places orders for you to supply four products by the end of October. You have limited capacity for raw material and other facilities. You are required to satisfy customer demand by manufacturing the products and/or buying from a supplier. After consulting with the production department, you obtained the following information. Product A Product B Product C Product D Order quantity 2000 3500 1500 2500 Hours required on machine X per unit 2 4 5 3 Hours required on machine Y per unit 4 3 6 2 Raw material in kilos 5 1 4 6 Time needed for Packaging per unit 36 minutes 30 minutes 45 minutes 24 minutes Available monthly hours per month: 8,000 on machine X, 6000 on machine Y, and 3,000 hours for packaging. Purchased items from your supplier are already packaged. Available raw material per month: 5,000 kilos…arrow_forwardUpton Enterprises produces a variety of switches. Below, you will find a bill-of-material file for their simplest switch: Part A. The number in the parentheses represents the number of units required for the upper level. LT stands for the lead time, measured in weeks.Assuming that Upton Enterprises has none of Switch A in inventory, and the inventory levels of Parts B, C, D, E, and F are also zero, how many weeks would it take to produce 100 units of Switch A? What would be the total requirement for part E?arrow_forwardThe Goodparts Company produces a component that is subsequently used in the aerospace industry. The component consists of three parts (A, B, and C) that are purchased from outside and cost 35, 30, and 10 cents per piece, respectively. Parts A and B are assembled first on assembly line 1, which produces 185 components per hour. Part C undergoes a drilling operation before being finally assembled with the output from assembly line 1. There are, in total, six drilling machines, but at present only three of them are operational. Each drilling machine drills part C at a rate of 80 parts per hour. In the final assembly, the output from assembly line 1 is assembled with the drilled part C. The final assembly line produces at a rate of 205 components per hour. At present, components are produced eight hours a day and five days a week. Management believes that if the need arises, it can add a second shift of eight hours for the assembly lines. The cost of assembly labor is 30 cents per part for…arrow_forward
- Mpho is an avid seamstress and want to sew and sell high quality, reusable, designer face masks during the current Covid-19 pandemic. She will design and sew the masks herself and use her automatic embroidery machine to put her logo on each mask sold. With the help of her son, deliveries will be made all over Gauteng within 3 days of placing the order. Every mask will have a unique threelayer design with adjustable straps to ensure comfort and fit. Mpho’s only expense is the material needed to sew the masks and delivery costs. At this stage, Mpho’s target market is limited to Gauteng. Draw a diagram to illustrate the transformation process of Mpho’s new business. Be sure to include all relevant elements, headings and arrows to indicate the flow of products/ servicesarrow_forwardThere are 500 wood pallets for the transportation of the final product cases. Each pallet has a cost of$88. If the pallet holds 329 cases each, what will be unit cost?arrow_forwardJosie’s Sports Accessories has 12 operators who work 9 hours a day (no breaks), 7 days a week. They manufacture headbands with a standard minute value of 1.35 minutes. The workers produce 4,450 headband a day. How long will it take them to complete an order for 5,000 headbands?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,