Question
Book Icon
Chapter 9, Problem 9PROB
Summary Introduction

Net Present Value (NPV) of a project is the sum of the present value of all its cash outflows and inflows. When this value is positive, it indicates that the project would add value to the organization and hence should be accepted. On the other hand, if the NPV of the project is negative, the project should be rejected.

NPV=CF0^+CF^1(1+r)1+CF^2(1+r)2+.......+CFn^(1+r)n=t=0nCFt^(1+r)t          

Here,

Expected net cash flow in Period t is “CFt^

Required rate of return is “r

NPV profile of a project is created by first determining the NPV of the project at varying discount rate and then plotting the same. The point when the graph crosses the X-axis is the Internal rate of Return (IRR) of the project, as IRR of a project is the required rate at which the NPV is zero. It helps in determining which project is more sensitive to the changes in the discount rate by analysing the steepness of the project.

A capital budgeting project has an initial cost of $64,000 which is expected to generate $18,200 for five years. Discount rates are 10%, 13% 15%.

Blurred answer
Students have asked these similar questions
Terra Landscape is evaluating a capital budgeting project that is expected to generate $80, 100 per year during its eight-year life. If its required rate of return is 14 percent, what is the value of the project to Terra Landscape?
Wandering RV is evaluating a capital budgeting project that is expected to generate $36,950 per year during its six-year life. If its required rate of return is 10 percent, what is the value of the project to Wandering RV?
A project has an initial cost of $40,000, expected net cash inflows of $9,000 per year for 7 years, and a cost of capital of 11%.   Requirements: What is the project’s NPV? What is the project’s IRR? What is the project’s PI? What is the project’s payback period? What is the project’s discounted payback period?
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Text book image
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License